Home / Browse projects / Raigarh, Maharashtra / Sparsh Phase-II

Registration lapsed No litigation declared Residential / Group Housing project

Sparsh Phase-II

By Shree Enterprises

RG-MH-61981 · RERA P52000016230 · Last updated on MahaRERA portal: 29 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 45 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
30 of 55Construction stages doneacross 5 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
12 of 158Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 220 documents Report an error

Sparsh Phase-II is a Residential / Group Housing project by Shree Enterprises in Raigarh, Maharashtra, registered with MahaRERA as P52000016230 on 25 Apr 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 45 months from the original filing. 146 of the 158 units on this registration are recorded sold or booked, and 30 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSparsh Phase-II
  • TypeResidential / Group Housing
  • Location
    • NH4 Old Mumbai Pune Highway
    • Shedung
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000016230
  • ReraGenie IDRG-MH-61981

Builder

  • NameShree Enterprises
  • Entity typePartnership
  • GSTIN27ACAFS4593E1Z0
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerAjay P Patil
  • Other registrations23 more →
  • Completed7 of 24
  • No longer live10 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

10 months past promisethis monthRegisteredApr 2018First promiseMar 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Apr 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Mar 2022)
  • Buildings5 building records
  • Documents filed220 files

Current status

92%146 of 158 units booked
99.7%Work done, per cost certificate

Figures as on 29 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building no 4NA8846046
Building no 5 Wing ANA8728028
Building no 5 Wing BNA8728028
Building no 6 Wing ANA8728028
Building no 6 Wing BNA8728028

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 29 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

Building no 467%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Building no 5 Wing A71%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Building no 5 Wing B71%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Building no 6 Wing A71%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Building no 6 Wing B71%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities19

As on 29 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Party Lawn with performing stageYes0%
Walking TrailYes0%
Club House with GymnasiumYes0%
Children Play AreaYes0%

Parking filed96

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots96
Closed/Covered96
BuildingClosed/CoveredTotal
Building no 477
Building no 5 Wing A2020
Building no 5 Wing B2121
Building no 6 Wing A2424
Building no 6 Wing B2424

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,322 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Oct 2025
LandownerVillageDistrict
Dinesh Mangalchand JainBorivaliMumbai Suburban
Jawanmal Chimanlal ShahAndheriMumbai Suburban
Pandurang Raoji PatilNavi Mumbai (M Corp.)Thane

Approvals and building plan

Sanctioning authorityCity & Industrial Development Corporation (CIDCO)
Permissible FSI6069.07
Proposed, not sanctioned2,794 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSector 01 Vashi Navi Mumbai 400703
Estimated costRs 12.18 cr
Cost incurredRs 12.14 cr
Work done99.65%
BuildingWingEstimatedIncurred
Building no 4NARs 3.73 crRs 3.72 cr
Building no 6 Wing ANARs 1.77 crRs 1.76 cr
Building no 6 Wing BNARs 1.77 crRs 1.76 cr
Building no 5 Wing ANARs 1.77 crRs 1.76 cr
Building no 5 Wing BNARs 1.77 crRs 1.76 cr
-NARs 1.39 crRs 1.36 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAN Arch Architect & Planner
EngineerSabu Scaria ( Structural Engineer)
EngineerAmol R Dhumal
Chartered AccountantM G Suthar & Associates
Chartered AccountantBrijesh Goyal & Associates
PartnerRole in project
Shree Enterprises-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000015051Mar 2022 → Mar 2024

Reason as filed by the promoterDear Sir, That there is delay in getting revised approvals for “Proposed but not sanctioned area” from the Planning Authority on the account of changes in Regulations governing the development of real estate of projects. The Planning Authority took some time to implement the Unified DCPR 2034 and therefore the construction work could not be carried out for the additional area declared at the time of registration. We have completed the construction work of the structure and envelope as well as majority of the finishing work for the building. Photographs showing the completed building and work i

EXT52000019819Mar 2022 → Dec 2024

Reason as filed by the promoterRespected Sir, The structure of the buildings along with the Brickwork and plaster is completed. The internal finishes including gypsum, Floor tiles and Dado, Kitchen Platform and doors have been installed. Currently, the work of electrical and plumbing fittings is going on. The external paint work will be started soon. We expect to finish the balance work by 15th November and obtain Occupation Certificate by December end. Accordingly, we are requesting this Hon’ble Authority to allow extension of project registration till 31st December 2024. Thanking you. Yours faithfully, For Shree Enterpris

EXT52000011545Mar 2022 → Mar 2023

Reason as filed by the promoterThat there was delay in approval of UDCPR governing the development of Real Estate projects within the Maharashtra State except the Municipal Corporation of Greater Mumbai issued by Government of Maharashtra due to ongoing pandemic situation. That there is resultant delay in revised approvals for Proposed but not sanctioned area and therefore the construction work could not be carried out for the additional area declared at the time of registration. That the revised approvals are in process and shall be issued soon. The construction work of building shall be completed accordingly after getting

EXT52000027378Mar 2022 → Dec 2025

Reason as filed by the promoterRequired Project extension for project completion purpose.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000375141Vinesh Kumar BalakrishnanDINESH MANGALCHAND JAIN10/04/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed220

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 220 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Sparsh P-II Form-1 June 2025.pdf29 Jan 2026
Withdrawal Update Form 2File: Sparsh P-II Form-2 June 2025.pdf29 Jan 2026
Withdrawal Update Form 3File: Sparsh P-II Form-3 June 2025.pdf29 Jan 2026
Form 1File: 202203_Ar.pdf10 Jan 2026
Form 2File: 202203_Er.pdf10 Jan 2026
Form 3File: 202203_CA.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 202203_Sold.pdf10 Jan 2026
Form 1File: 202212_Ar.pdf10 Jan 2026
Form 2File: 202212_Er.pdf10 Jan 2026
Form 3File: 202212_CA.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 202212_Sold.pdf10 Jan 2026
Form 1File: 202303_Ar.pdf10 Jan 2026
Form 2File: 202303_Er.pdf10 Jan 2026
Form 3File: 202303_CA.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 202303_Sold.pdf10 Jan 2026
Form 1File: 202306_Ar.pdf10 Jan 2026
Form 2File: 202306_Er.pdf10 Jan 2026
Form 3File: 202306_CA.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 202306_Sold.pdf10 Jan 2026
Form 1File: 202309_Ar.pdf10 Jan 2026
Form 2File: 202309_Er.pdf10 Jan 2026
Form 3File: 202309_CA.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 202309_sold.pdf10 Jan 2026
Form 1File: 202312_Ar.pdf10 Jan 2026
Form 2File: 202312_Er.pdf10 Jan 2026
Form 3File: 202312_CA.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 202312_Sold.pdf10 Jan 2026
Form 1File: 202403_Ar.pdf10 Jan 2026
Form 2File: 202403_Er.pdf10 Jan 2026
Form 3File: 202403_CA.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: 202403_Sold.pdf10 Jan 2026
Form 1File: SP II Form 1 202406.pdf10 Jan 2026
Form 2File: SP II Form 2 202406.pdf10 Jan 2026
Form 3File: SP II FORM 3 202406.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: SP II Sold invt Disclr 202406.pdf10 Jan 2026
Form 1File: SP II Form 1 202409.pdf10 Jan 2026
Form 2File: SP II Form 2 202409.pdf10 Jan 2026
Form 3File: SP II Form 3 202409.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: SP II Sold invt Dislr 202409.pdf10 Jan 2026
Form 1File: SP II Form 1 202412.pdf10 Jan 2026
Form 2File: SP II Form 2 202412.pdf10 Jan 2026
Form 3File: SP II Form 3 Dec 24.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: SP II Sold Invt Disclr 202412.pdf10 Jan 2026
Form 5 (FY 2022-2023)File: Form-5 - 2022-23.pdf10 Jan 2026
Form 5 (FY 2021-2022)File: 2021-22_Form-5.pdf10 Jan 2026
Form 1File: FORM 1.pdf8 Jul 2025
Form 2File: FORM 2.pdf8 Jul 2025
Form 3File: Form 3.pdf8 Jul 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf8 Jul 2025
Form 2A (FY 2023-2024)File: FORM 2A.pdf8 Jul 2025
Form 5 (FY 2023-2024)File: From 5.pdf8 Jul 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1 Sparsh Ph II 30062024.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F 1 Sparsh Ph II 30092024.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1 Sparsh Ph II 31122024.pdf25 Feb 2025
Certificates of CA (Form 3)File: Form 3 Phase II 31122024.pdf25 Feb 2025
Certificates of CA (Form 3)File: Form 3 Phase II 30092024.pdf25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 PH II 30092024.pdf25 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 PH II31122024.pdf25 Feb 2025
Disclosure of sold/ booked inventoryFile: Sparsh Phase II sold inventory June 2024.pdf25 Feb 2025
Disclosure of sold/ booked inventoryFile: Sparsh Phase II sold inventory SEP 2024.pdf25 Feb 2025
Disclosure of sold/ booked inventoryFile: Sparsh Phase II sold inventory DEC 2024.pdf25 Feb 2025
Declaration in FORM BFile: JCS.pdf31 Jan 2025
Declaration in FORM BFile: Prp.pdf31 Jan 2025
Declaration in FORM BFile: Shree.pdf31 Jan 2025
Declaration in FORM BFile: DMJ.pdf31 Jan 2025
Certificates of CA (Form 3)File: PHASE II FORM 3 30062024.pdf10 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATESPARSH PHASEII 30062024.pdf10 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From 5 Sparsh PH II.pdf10 Dec 2024
Declaration in FORM BFile: Shree.pdf28 May 2024
Disclosure of sold/ booked inventoryFile: 202303_Sold.pdf28 May 2024
Disclosure of sold/ booked inventoryFile: 202306_Sold.pdf28 May 2024
Disclosure of sold/ booked inventoryFile: 202309_sold.pdf28 May 2024
Disclosure of sold/ booked inventoryFile: 202312_Sold.pdf28 May 2024
Disclosure of sold/ booked inventoryFile: 202403_Sold.pdf28 May 2024
Certificates of CA (Form 3)File: 202312_CA.pdf28 May 2024
Certificates of CA (Form 3)File: 202403_CA.pdf28 May 2024
Other - TechnicalFile: JCS.pdf28 May 2024
Other - TechnicalFile: DMJ.pdf28 May 2024
Other - TechnicalFile: PRP.pdf28 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202309_Ar.pdf26 May 2024

How this compares with Raigarh

92%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 45 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sparsh Phase-II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shedung5,900+ in Raigarh

2 kmSparsh Phase-IICompleted 6Lapsed / revoked 3Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: Shree Enterprises

SHREE ENTERPRISES has 24 registrations on MahaRERA, including SHREE TULSI KUNJ and SILVER DREAMS. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Sparsh Phase-II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sparsh Phase-II is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sparsh Phase-II?

The registered promoter entity is Shree Enterprises, a partnership as per the filing. Its GSTIN 27ACAFS4593E1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sparsh Phase-II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sparsh Phase-II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sparsh Phase-II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sparsh Phase-II?

The professionals named in the filing: Architect: AN Arch Architect & Planner; Engineer: Sabu Scaria ( Structural Engineer); Engineer: Amol R Dhumal; Chartered Accountant: M G Suthar & Associates; Chartered Accountant: Brijesh Goyal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sparsh Phase-II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sparsh Phase-II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sparsh Phase-II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.