Sparsh Phase-II
RG-MH-61981 · RERA P52000016230 · Last updated on MahaRERA portal: 29 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 45 months
- 4 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sparsh Phase-II is a Residential / Group Housing project by Shree Enterprises in Raigarh, Maharashtra, registered with MahaRERA as P52000016230 on 25 Apr 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 45 months from the original filing. 146 of the 158 units on this registration are recorded sold or booked, and 30 of 55 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameSparsh Phase-II
- TypeResidential / Group Housing
- Location
- NH4 Old Mumbai Pune Highway
- Shedung
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000016230
- ReraGenie IDRG-MH-61981
Builder
- NameShree Enterprises
- Entity typePartnership
- GSTIN27ACAFS4593E1Z0
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnerAjay P Patil
- Other registrations23 more →
- Completed7 of 24
- No longer live10 lapsed, de-registered or revoked
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on25 Apr 2018
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Mar 2022)
- Buildings5 building records
- Documents filed220 files
Current status
Figures as on 29 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building no 4 | NA | 8 | 8 | 46 | 0 | 46 |
| Building no 5 Wing A | NA | 8 | 7 | 28 | 0 | 28 |
| Building no 5 Wing B | NA | 8 | 7 | 28 | 0 | 28 |
| Building no 6 Wing A | NA | 8 | 7 | 28 | 0 | 28 |
| Building no 6 Wing B | NA | 8 | 7 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 29 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
Building no 467%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Building no 5 Wing A71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Building no 5 Wing B71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Building no 6 Wing A71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Building no 6 Wing B71%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities19
As on 29 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 50% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 85% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Party Lawn with performing stage | Yes | 0% |
| Walking Trail | Yes | 0% |
| Club House with Gymnasium | Yes | 0% |
| Children Play Area | Yes | 0% |
Parking filed96
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Building no 4 | 7 | 7 |
| Building no 5 Wing A | 20 | 20 |
| Building no 5 Wing B | 21 | 21 |
| Building no 6 Wing A | 24 | 24 |
| Building no 6 Wing B | 24 | 24 |
Land and ownership3
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Dinesh Mangalchand Jain | Borivali | Mumbai Suburban |
| Jawanmal Chimanlal Shah | Andheri | Mumbai Suburban |
| Pandurang Raoji Patil | Navi Mumbai (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Building no 4 | NA | Rs 3.73 cr | Rs 3.72 cr |
| Building no 6 Wing A | NA | Rs 1.77 cr | Rs 1.76 cr |
| Building no 6 Wing B | NA | Rs 1.77 cr | Rs 1.76 cr |
| Building no 5 Wing A | NA | Rs 1.77 cr | Rs 1.76 cr |
| Building no 5 Wing B | NA | Rs 1.77 cr | Rs 1.76 cr |
| - | NA | Rs 1.39 cr | Rs 1.36 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AN Arch Architect & Planner |
| Engineer | Sabu Scaria ( Structural Engineer) |
| Engineer | Amol R Dhumal |
| Chartered Accountant | M G Suthar & Associates |
| Chartered Accountant | Brijesh Goyal & Associates |
| Partner | Role in project |
|---|---|
| Shree Enterprises | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir, That there is delay in getting revised approvals for “Proposed but not sanctioned area” from the Planning Authority on the account of changes in Regulations governing the development of real estate of projects. The Planning Authority took some time to implement the Unified DCPR 2034 and therefore the construction work could not be carried out for the additional area declared at the time of registration. We have completed the construction work of the structure and envelope as well as majority of the finishing work for the building. Photographs showing the completed building and work i
Reason as filed by the promoterRespected Sir, The structure of the buildings along with the Brickwork and plaster is completed. The internal finishes including gypsum, Floor tiles and Dado, Kitchen Platform and doors have been installed. Currently, the work of electrical and plumbing fittings is going on. The external paint work will be started soon. We expect to finish the balance work by 15th November and obtain Occupation Certificate by December end. Accordingly, we are requesting this Hon’ble Authority to allow extension of project registration till 31st December 2024. Thanking you. Yours faithfully, For Shree Enterpris
Reason as filed by the promoterThat there was delay in approval of UDCPR governing the development of Real Estate projects within the Maharashtra State except the Municipal Corporation of Greater Mumbai issued by Government of Maharashtra due to ongoing pandemic situation. That there is resultant delay in revised approvals for Proposed but not sanctioned area and therefore the construction work could not be carried out for the additional area declared at the time of registration. That the revised approvals are in process and shall be issued soon. The construction work of building shall be completed accordingly after getting
Reason as filed by the promoterRequired Project extension for project completion purpose.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000375141 | Vinesh Kumar Balakrishnan | DINESH MANGALCHAND JAIN | 10/04/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Jun 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed220
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 220 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Sparsh P-II Form-1 June 2025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: Sparsh P-II Form-2 June 2025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: Sparsh P-II Form-3 June 2025.pdf | 29 Jan 2026 |
| Form 1File: 202203_Ar.pdf | 10 Jan 2026 |
| Form 2File: 202203_Er.pdf | 10 Jan 2026 |
| Form 3File: 202203_CA.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 202203_Sold.pdf | 10 Jan 2026 |
| Form 1File: 202212_Ar.pdf | 10 Jan 2026 |
| Form 2File: 202212_Er.pdf | 10 Jan 2026 |
| Form 3File: 202212_CA.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 202212_Sold.pdf | 10 Jan 2026 |
| Form 1File: 202303_Ar.pdf | 10 Jan 2026 |
| Form 2File: 202303_Er.pdf | 10 Jan 2026 |
| Form 3File: 202303_CA.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 202303_Sold.pdf | 10 Jan 2026 |
| Form 1File: 202306_Ar.pdf | 10 Jan 2026 |
| Form 2File: 202306_Er.pdf | 10 Jan 2026 |
| Form 3File: 202306_CA.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 202306_Sold.pdf | 10 Jan 2026 |
| Form 1File: 202309_Ar.pdf | 10 Jan 2026 |
| Form 2File: 202309_Er.pdf | 10 Jan 2026 |
| Form 3File: 202309_CA.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 202309_sold.pdf | 10 Jan 2026 |
| Form 1File: 202312_Ar.pdf | 10 Jan 2026 |
| Form 2File: 202312_Er.pdf | 10 Jan 2026 |
| Form 3File: 202312_CA.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 202312_Sold.pdf | 10 Jan 2026 |
| Form 1File: 202403_Ar.pdf | 10 Jan 2026 |
| Form 2File: 202403_Er.pdf | 10 Jan 2026 |
| Form 3File: 202403_CA.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: 202403_Sold.pdf | 10 Jan 2026 |
| Form 1File: SP II Form 1 202406.pdf | 10 Jan 2026 |
| Form 2File: SP II Form 2 202406.pdf | 10 Jan 2026 |
| Form 3File: SP II FORM 3 202406.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SP II Sold invt Disclr 202406.pdf | 10 Jan 2026 |
| Form 1File: SP II Form 1 202409.pdf | 10 Jan 2026 |
| Form 2File: SP II Form 2 202409.pdf | 10 Jan 2026 |
| Form 3File: SP II Form 3 202409.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SP II Sold invt Dislr 202409.pdf | 10 Jan 2026 |
| Form 1File: SP II Form 1 202412.pdf | 10 Jan 2026 |
| Form 2File: SP II Form 2 202412.pdf | 10 Jan 2026 |
| Form 3File: SP II Form 3 Dec 24.pdf | 10 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SP II Sold Invt Disclr 202412.pdf | 10 Jan 2026 |
| Form 5 (FY 2022-2023)File: Form-5 - 2022-23.pdf | 10 Jan 2026 |
| Form 5 (FY 2021-2022)File: 2021-22_Form-5.pdf | 10 Jan 2026 |
| Form 1File: FORM 1.pdf | 8 Jul 2025 |
| Form 2File: FORM 2.pdf | 8 Jul 2025 |
| Form 3File: Form 3.pdf | 8 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf | 8 Jul 2025 |
| Form 2A (FY 2023-2024)File: FORM 2A.pdf | 8 Jul 2025 |
| Form 5 (FY 2023-2024)File: From 5.pdf | 8 Jul 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1 Sparsh Ph II 30062024.pdf | 25 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F 1 Sparsh Ph II 30092024.pdf | 25 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: F1 Sparsh Ph II 31122024.pdf | 25 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 Phase II 31122024.pdf | 25 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 Phase II 30092024.pdf | 25 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 PH II 30092024.pdf | 25 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: F2 PH II31122024.pdf | 25 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sparsh Phase II sold inventory June 2024.pdf | 25 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sparsh Phase II sold inventory SEP 2024.pdf | 25 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sparsh Phase II sold inventory DEC 2024.pdf | 25 Feb 2025 |
| Declaration in FORM BFile: JCS.pdf | 31 Jan 2025 |
| Declaration in FORM BFile: Prp.pdf | 31 Jan 2025 |
| Declaration in FORM BFile: Shree.pdf | 31 Jan 2025 |
| Declaration in FORM BFile: DMJ.pdf | 31 Jan 2025 |
| Certificates of CA (Form 3)File: PHASE II FORM 3 30062024.pdf | 10 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATESPARSH PHASEII 30062024.pdf | 10 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From 5 Sparsh PH II.pdf | 10 Dec 2024 |
| Declaration in FORM BFile: Shree.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: 202303_Sold.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: 202306_Sold.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: 202309_sold.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: 202312_Sold.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: 202403_Sold.pdf | 28 May 2024 |
| Certificates of CA (Form 3)File: 202312_CA.pdf | 28 May 2024 |
| Certificates of CA (Form 3)File: 202403_CA.pdf | 28 May 2024 |
| Other - TechnicalFile: JCS.pdf | 28 May 2024 |
| Other - TechnicalFile: DMJ.pdf | 28 May 2024 |
| Other - TechnicalFile: PRP.pdf | 28 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202309_Ar.pdf | 26 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 23 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 220 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Sparsh Phase-II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shedung5,900+ in Raigarh
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: Shree Enterprises
SHREE ENTERPRISES has 24 registrations on MahaRERA, including SHREE TULSI KUNJ and SILVER DREAMS. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that Sparsh Phase-II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Sparsh Phase-II is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sparsh Phase-II?
The registered promoter entity is Shree Enterprises, a partnership as per the filing. Its GSTIN 27ACAFS4593E1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sparsh Phase-II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Sparsh Phase-II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Sparsh Phase-II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sparsh Phase-II?
The professionals named in the filing: Architect: AN Arch Architect & Planner; Engineer: Sabu Scaria ( Structural Engineer); Engineer: Amol R Dhumal; Chartered Accountant: M G Suthar & Associates; Chartered Accountant: Brijesh Goyal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sparsh Phase-II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback