Home / Browse projects / Raigarh, Maharashtra / SPACE GREENS

Registered No litigation declared Residential / Group Housing project

SPACE GREENS

By Space India Builders & Developer

RG-MH-38228 · RERA P52000032326 · Last updated on MahaRERA portal: 18 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 4 months from the original
12 of 66Construction stages doneacross 6 buildings; furthest along: Staircases, 75%
84 of 162Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 159 documents Report an error

SPACE GREENS is a Residential / Group Housing project by Space India Builders & Developer in Raigarh, Maharashtra, registered with MahaRERA as P52000032326 on 29 Dec 2021. Possession is promised by 30 Apr 2027. The completion date has moved by 4 months from the original filing. 78 of the 162 units on this registration are recorded sold or booked, and 12 of 66 construction stages are filed complete.

At a glance

Project

  • NameSPACE GREENS
  • TypeResidential / Group Housing
  • Location
    • Dundre and Dundrai
    • Dundre
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000032326
  • ReraGenie IDRG-MH-38228

Builder

  • NameSpace India Builders & Developer
  • Entity typePartnership
  • GSTIN27ABRFS3118H1ZW
  • PartnersVinay prakash Singh, Santosh Ravinath Shetty
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredDec 2021First promiseDec 2026Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Dec 2021
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2026)
  • Buildings6 building records
  • Documents filed159 files

Current status

48%78 of 162 units booked

Figures as on 18 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 1NA60000
BUILDING 2NA60000
BUILDING 3NA6572072
BUILDING 4NA6582082
BUILDING 5NA60000
BUILDING 6NA61808

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 18 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Staircases, at 75%.

BUILDING 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING 345%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING 448%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING 50%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING 627%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed77

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots77
Closed/Covered56
Open Space21
BuildingClosed/CoveredOpen SpaceTotal
BUILDING 2808
BUILDING 314014
BUILDING 412012
BUILDING 510010
BUILDING 6122133

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,630 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Jul 2026

Approvals and building plan

Sanctioning authorityNAVI MUMBAI AIRPORT INFLUENCE NOTIFIED AREA (NAINA)
Permissible FSI7040.7
Proposed, not sanctioned7,041 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNEW PANVEL, PANVEL RAIGAD

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMEENAKSHI & ASSOCIATES
EngineerVASTUKALP
EngineerAbhijeet Ashok Londhe
Chartered AccountantMANISH KUMAR GUPTA & CO
Chartered AccountantDipika Patel & CO
Chartered AccountantDipika Patel & Co.
Chartered AccountantAryan Patwari
PartnerRole in project
Space India Builders & Developer-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52000032326/WarDec 2026 → Apr 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed159

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 159 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2021-2022)File: Form 2A 21 22.pdf18 Sep 2026
Form 2A (FY 2022-2023)File: Form 2A 22 23.pdf18 Sep 2026
Form 2A (FY 2023-2024)File: Form 2A 23 24.pdf18 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A 24 25.pdf18 Sep 2026
Form 2A (FY 2025-2026)File: Form 2A 24 25.pdf18 Sep 2026
Form 5 (FY 2025-2026)File: Form 5.pdf18 Sep 2026
Form 5 (FY 2021-2022)File: Form 5 Space greens FY 2021-22.pdf17 Sep 2026
Form 5 (FY 2022-2023)File: Form 5 Space Greens FY 2022-23.pdf17 Sep 2026
Form 5 (FY 2023-2024)File: Form 5 Space Greens FY 2023-24.pdf17 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: Form 1.pdf16 Sep 2026
Form 2File: Form 2.pdf16 Sep 2026
Form 3File: Form 3.pdf16 Sep 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories.pdf16 Sep 2026
Form 1File: 16 Architects Certificate 31-03-2026.pdf11 May 2026
Form 2File: 16 Engineer certificate 31-03-2026.pdf11 May 2026
Form 3File: 15 CA Certificate 31-03-2026.pdf11 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventories Q4.pdf11 May 2026
Form 1File: 15 Architects Certificate 31-12-2025.pdf2 Mar 2026
Form 2File: 15 Engineer certificate 31-12-2025.pdf2 Mar 2026
Form 3File: 14 CA Certificate 31-12-2025.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLDBOOKED INVENTORY Space Greens 31-12-2025.pdf2 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 Space Greens FY 2024-25.pdf18 Dec 2025
Form 1File: 14 Architect's Certificate 30-09-2025.pdf19 Nov 2025
Form 2File: 14 Engineer certificate 30-09-2025.pdf19 Nov 2025

How this compares with Raigarh

48%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 4 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SPACE GREENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dundre and Dundrai5,900+ in Raigarh

Builder: Space India Builders & Developer

Space India Builders & Developer has 3 registrations on MahaRERA, including Space Gold Crest and SPACE GREENS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SPACE GREENS is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SPACE GREENS?

The registered promoter entity is Space India Builders & Developer, a partnership as per the filing. Its GSTIN 27ABRFS3118H1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SPACE GREENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SPACE GREENS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SPACE GREENS?

The professionals named in the filing: Architect: MEENAKSHI & ASSOCIATES; Engineer: VASTUKALP; Engineer: Abhijeet Ashok Londhe; Chartered Accountant: MANISH KUMAR GUPTA & CO; Chartered Accountant: Dipika Patel & CO; Chartered Accountant: Dipika Patel & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SPACE GREENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SPACE GREENS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SPACE GREENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.