Home / Browse projects / Raigarh, Maharashtra / SOUND DELIGHT
SOUND DELIGHT
RG-MH-92965 · RERA P51900002485 · Last updated on MahaRERA portal: 11 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 5 complaints at MahaRERA
- Completion date moved by 123 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SOUND DELIGHT is a Residential / Group Housing project by SOUNDLINES ECOHOMES in Raigarh, Maharashtra, registered with MahaRERA as P51900002485 on 1 Aug 2017. Possession is promised by 31 Dec 2030. The completion date has moved by 123 months from the original filing. 97 of the 162 units on this registration are recorded sold or booked, and 56 of 143 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NameSOUND DELIGHT
- TypeResidential / Group Housing
- Location
- NAGAR RACHNA ANI MULYA NIRDHARAN VIBHAG RAIGAD - ALIBAG
- Ashte
- Panvel
- Raigarh
- 410206
- Pincode410206
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900002485
- ReraGenie IDRG-MH-92965
Builder
- NameSOUNDLINES ECOHOMES
- Entity typePartnership
- PartnersOBAID MOHAMMED YUSUF SHAIKH, MOAZZAM MOHAMMED YUSUF SHAIKH, MUZAMMIL MOHAMMED YUSUF SHAIKH, MAAZ MOHAMMED YUSUF SHAIKH, MUKESH GHEWARCHAND JAIN, SHABBIR GULAM HUSAIN MORBIWALA, IBRAHIM ISMAIL KHAN
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Aug 2017
- Promised completion31 Dec 2030
- Revised completionRevised to 31 Dec 2030 (originally 30 Sep 2020)
- Buildings13 building records
- Documents filed170 files
Current status
Figures as on 11 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 8 | 4 | 16 | 0 | 16 |
| B WING | NA | 7 | 4 | 16 | 0 | 16 |
| C WING | NA | 7 | 4 | 24 | 0 | 24 |
| D WING | NA | 4 | 4 | 24 | 0 | 24 |
| E WING | NA | 12 | 4 | 16 | 0 | 16 |
| F WING | NA | 0 | 0 | 0 | 0 | 0 |
| G WING | NA | 14 | 4 | 18 | 0 | 18 |
| H WING | NA | 13 | 4 | 18 | 0 | 18 |
| I WING | NA | 12 | 4 | 14 | 0 | 14 |
| J WING | NA | 6 | 0 | 16 | 0 | 16 |
| K WING | NA | 10 | 0 | 0 | 0 | 0 |
| L WING | NA | 0 | 0 | 0 | 0 | 0 |
| BUNGLOWS | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building13
As on 11 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
56 of 143 construction stages are filed complete across 13 buildings. The stage furthest along is Installation of Lifts, at 90%.
A WING68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
B WING68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
C WING68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
D WING68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
E WING81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
F WING81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
G WING81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
H WING81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
I WING81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
J WING3%
| Activity | Progress |
|---|---|
| Excavation | 30% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
K WING0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
L WING0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGLOWS0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 11 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 70% |
| Landscaping & Tree Planting | Yes | 70% |
| Street Lighting | Yes | 70% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 70% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 70% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 70% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed444
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A WING | 32 | 0 | 32 |
| B WING | 32 | 0 | 32 |
| C WING | 48 | 0 | 48 |
| D WING | 48 | 0 | 48 |
| E WING | 30 | 0 | 30 |
| F WING | 71 | 0 | 71 |
| G WING | 34 | 0 | 34 |
| H WING | 34 | 0 | 34 |
| I WING | 27 | 0 | 27 |
| J WING | 32 | 0 | 32 |
| K WING | 6 | 0 | 6 |
| L WING | 3 | 5 | 8 |
| BUNGLOWS | 12 | 30 | 42 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 67.48 cr | Rs 31.23 cr |
| D WING | NA | Rs 10.07 cr | Rs 4.31 cr |
| C WING | NA | Rs 9.58 cr | Rs 4.12 cr |
| A WING | NA | Rs 6.52 cr | Rs 2.94 cr |
| J WING | NA | Rs 6.43 cr | Rs 34.08 lakh |
| B WING | NA | Rs 6.11 cr | Rs 2.43 cr |
| F WING | NA | Rs 5.90 cr | - |
| G WING | NA | Rs 5.05 cr | Rs 4.54 cr |
| H WING | NA | Rs 5.05 cr | Rs 4.54 cr |
| I WING | NA | Rs 4.61 cr | Rs 4.15 cr |
| E WING | NA | Rs 4.29 cr | Rs 3.86 cr |
| BUNGLOWS | NA | Rs 2.51 cr | - |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | APICES STUDIO PVT LTD |
| Engineer | HANWARE CONSULTANTS |
| Engineer | ZAINUDDIN TOLE |
| Engineer | kk associates |
| Engineer | SMI CONSULTANTS |
| Chartered Accountant | NEHALI DOSHI |
| Chartered Accountant | F.A. ANSARI & ASSOCIATES |
| Partner | Role in project |
|---|---|
| SOUNDLINES ECOHOMES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL
Reason as filed by the promoterDespite our best efforts to maintain the construction timeline, the project has faced unavoidable delays due to the prolonged slowdown in the real estate sector post-COVID led to drastically reduced sales and booking velocity, adversely affecting project fund flows. The project faced acute liquidity constraints. Despite our best efforts to arrange additional funding, the economic distress in the sector made it extremely challenging to mobilize resources at reasonable terms. And also, Severe Shortage of Essential Construction Materials and Labors: Over the Past Months, the Market has experience
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000195174 | Tapan Visaria | Soundlines Ecohomes | 11/12/2020 |
| CC006000000591162 | Prashant Pawar | Soundlines EcoHomes | 12/07/2024 |
| SM12500034 | Amolika Bandiwadekar | SOUNDLINES ECOHOMES | 12/02/2025 |
| CC12502150 | Santhosh Sekharan Alikkal | SOUNDLINES ECOHOMES | 29/06/2025 |
| CC12602387 | Prashant Pawar | SOUNDLINES ECOHOMES | 23/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Jun 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2030
Documents filed170
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 170 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Architects Certificate.pdf | 11 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Architects Certificate.pdf | 11 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Architects Certificate.pdf | 11 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Engneer Certificate.pdf | 11 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Engneer Certificate.pdf | 11 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Engneer Certificate.pdf | 11 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate.pdf | 11 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate.pdf | 11 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate.pdf | 11 Jul 2026 |
| Form 2A (FY 2025-2026)File: Quality assurance certificate panvel.pdf | 20 May 2026 |
| Withdrawal Update Form 1File: form 1_compressed (3).pdf | 28 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 Signed.pdf | 28 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3_compressed (16).pdf | 28 Apr 2026 |
| Form 2A (FY 2024-2025)File: Form 2A FY 24-25_11zon.pdf | 6 Mar 2026 |
| Form 5 (FY 2024-2025)File: Form 5.pdf | 6 Mar 2026 |
| Withdrawal Update Form 1File: FORM 1 final jan 26.pdf | 13 Jan 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 13 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 final.pdf | 13 Jan 2026 |
| Withdrawal Update Form 1File: sound delight merge pdf form1 sept 25.pdf | 23 Dec 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 23 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 final 1.pdf | 23 Dec 2025 |
| Withdrawal Update Form 1File: form1 a wing to f wing final.pdf | 18 Dec 2025 |
| Withdrawal Update Form 2File: Form -2.pdf | 18 Dec 2025 |
| Withdrawal Update Form 3File: form no 3 final echo light compressed.pdf | 18 Dec 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 A B C D.pdf | 12 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 E G H I.pdf | 12 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 J F L.pdf | 12 Apr 2025 |
| Certificates of CA (Form 3)File: Form -3-compressed.pdf | 12 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 12 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1_Architect Cert.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: Form-3 CA Cert (1).pdf | 20 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2_Engineer cert.pdf | 20 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1.pdf | 15 Oct 2024 |
| Certificates of CA (Form 3)File: Form-3.pdf | 15 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2.pdf | 15 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form -5 23-24.pdf | 15 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form -2A.pdf | 2 Aug 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 19 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 19 Jul 2024 |
| Certificates of CA (Form 3)File: form 3.pdf | 19 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ABC D.pdf | 19 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 EGF I.pdf | 19 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 JKL.pdf | 19 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 19 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 (1) (1).pdf | 19 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECT Certificate DEC 23.pdf | 16 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2.pdf | 13 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Invesntory Disclosure.pdf | 13 Jan 2024 |
| Certificates of CA (Form 3)File: CA certificate Form 3.pdf | 13 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for Q2_compressed.pdf | 13 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate form (oct) 3-10-2023 (July - Sept 2023).pdf | 13 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: CA certificate for Q2_compressed.pdf | 13 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate (1).pdf | 15 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Ecohomes Inventory Disclosures.pdf | 13 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ecohomes Engineer Certificate Form 2.pdf | 12 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate 2A 2022-23.pdf | 12 Jul 2023 |
| Certificates of CA (Form 3)File: Ecohomes Form3 CA Certificate.pdf | 12 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf | 12 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate _ A B C D.pdf | 15 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate _G H I E.pdf | 15 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate_ J,F,L.pdf | 15 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 15 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure.pdf | 14 Apr 2023 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 14 Apr 2023 |
| Certificates of CA (Form 3)File: CA certificate.pdf | 14 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2023-01-04-RERA Certificate PH-1 for E,G,H,I.pdf | 7 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2023-01-04-RERA Certificate PH-2 for A,B,C,D.pdf | 7 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2023-01-04-RERA Certificate PH-3 for J,F,L.pdf | 7 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure.pdf | 7 Jan 2023 |
| Certificates of CA (Form 3)File: Form_3 CA certificate RERA Submission Q3.pdf | 7 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate form (JAN) 3-10-2022 (jul-sept22).pdf | 13 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf | 12 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure.pdf | 8 Oct 2022 |
| Certificates of CA (Form 3)File: CA certificate (2).pdf | 8 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2022-10-07-RERA Certificate PH-1 for E,G,H,I.pdf | 7 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2022-10-07-RERA Certificate PH-2 for A,B,C,D.pdf | 7 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2022-10-07-RERA Certificate PH-3 for J,F,L.pdf | 7 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 for period 1-4-2022 to 30-6-2022.pdf | 9 Jul 2022 |
| Certificates of CA (Form 3)File: Ca certificate.pdf | 7 Jul 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 170 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SOUND DELIGHT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ashte5,900+ in Raigarh
Filed coordinates, straight-line distance. 32 registered projects within 2 km.
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: SOUNDLINES ECOHOMES
SOUNDLINES ECOHOMES has 1 registration on MahaRERA, including SOUND DELIGHT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if SOUND DELIGHT is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SOUND DELIGHT?
The registered promoter entity is SOUNDLINES ECOHOMES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SOUND DELIGHT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SOUND DELIGHT?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SOUND DELIGHT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SOUND DELIGHT?
The professionals named in the filing: Architect: APICES STUDIO PVT LTD; Engineer: HANWARE CONSULTANTS; Engineer: ZAINUDDIN TOLE; Engineer: kk associates; Engineer: SMI CONSULTANTS; Chartered Accountant: NEHALI DOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SOUND DELIGHT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.