Home / Browse projects / Mumbai Suburban, Maharashtra / SORRENTO
SORRENTO
RG-MH-25032 · RERA P51800003022 · Last updated on MahaRERA portal: 26 Dec 2019
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SORRENTO is a Residential / Group Housing project by SAHAJ ANKUR DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003022 on 4 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2019. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameSORRENTO
- TypeResidential / Group Housing
- Location
- Andheri
- Mumbai Suburban
- 400054
- Pincode400054
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003022
- ReraGenie IDRG-MH-25032
Builder
- NameSAHAJ ANKUR DEVELOPERS
- Entity typePartnership
- PartnersDINESH VINODCHANDRA SHAH, CHANDRAVADAN SUNDERLAL SHAH, NIMESH SUBODH DALAL
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on4 Aug 2017
- Promised completion31 Dec 2019
- Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
- Buildings2 building records
- Documents filed33 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SORRENTO WING A | NA | 12 | 0 | 0 | 0 | 0 |
| SORRENTO WING B | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 26 Dec 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
19 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.
SORRENTO WING A90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
SORRENTO WING B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 26 Dec 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 90% |
Parking filed61
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| SORRENTO WING A | 30 | 30 |
| SORRENTO WING B | 31 | 31 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | BHAVIN HEMAL ARCHTECTS |
| Partner | Role in project |
|---|---|
| SAHAJ ANKUR DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Construction of building is Complete and we have already submitted an application to B.M.C for O.C./B.C.C. However certain compliances are pending which will take 12 months and therefore it is requested to extend the project by 12 months.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196760 | Asha Sainani | Sahaj Ankur Developers | 19/04/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 24 Dec 2019
Documents filed33
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4- Rera Form.pdf | 26 Dec 2019 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sahaj Completion Certificate.pdf | 24 Dec 2019 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Sorrento Registration Certificate for Society Formation.pdf | 24 Dec 2019 |
| Certificates of CA (Form 5)File: Form-5 of Sahaj.pdf | 1 Oct 2019 |
| Certificates of CA (Form 3)File: Form-3.pdf | 12 Jun 2019 |
| Certificates of CA (Form 5)File: FORM 5.PDF | 6 Feb 2019 |
| OtherFile: Architech Certificate.pdf | 2 Feb 2019 |
| OtherFile: CFO Noc.pdf | 2 Feb 2019 |
| OtherFile: OC Submission Documents-.pdf | 2 Feb 2019 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 1 Feb 2019 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 1 Feb 2019 |
| Building plan approvalFile: IOD LETTER.PDF | 28 Jul 2017 |
| Layout approvalFile: LAYOUT.PDF | 28 Jul 2017 |
| Building plan approvalFile: IOD PLAN ANKUR compressed.pdf | 28 Jul 2017 |
| PAN CardFile: Sahaj Ankur Developers.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: Opinion.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: encumbrance ankur.PDF | 28 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.PDF | 28 Jul 2017 |
| Building Plan Approval (IOD)File: IOD LETTER.PDF | 28 Jul 2017 |
| Building Plan Approval (IOD)File: IOD PLAN ANKUR compressed.pdf | 28 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.PDF | 28 Jul 2017 |
| Declaration in FORM BFile: FORM B compressed.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: 1.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: 2.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: 3.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: 4.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: 5.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: 6.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate compressed.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate compressed.pdf | 28 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate compressed.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: Sahaj Ankur Developers - Declaration Letter.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: SAD - Title Certificate.pdf | 27 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 33 filed documents as one ZIP, foldered, with a manifest
Keep SORRENTO on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 309 registered projects within 2 km.
AVIARA
BALUWALA BUILDERS
Ruparel Panache
Ruparel Infra & Realty Pvt Ltd
Vascon Orchids
Vascon Engineers Ltd
COMMERZ 54
SHREE VINAYAK REALITY PRIVATE LIMITED
Vascon Onyx Residences
Vascon Engineers Ltd
REDEVELOPMENT OF SHINING STAR CHSL
PRANAV CONSTRUCTIONS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: SAHAJ ANKUR DEVELOPERS
SAHAJ ANKUR DEVELOPERS has 1 registration on MahaRERA, including SORRENTO. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SORRENTO is delayed beyond 31 Dec 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SORRENTO?
The registered promoter entity is SAHAJ ANKUR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SORRENTO?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SORRENTO?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SORRENTO?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SORRENTO?
The professionals named in the filing: Architect: BHAVIN HEMAL ARCHTECTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SORRENTO?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback