Home / Browse projects / Mumbai Suburban, Maharashtra / SONI ARCADE, BUILDING NO 2

Registered Litigation declared Others project

SONI ARCADE, BUILDING NO 2

By SONI & ASSOCIATES

RG-MH-34853 · RERA P51800013002 · Last updated on MahaRERA portal: 31 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 3 complaints at MahaRERA
  • Completion date moved by 96 months
  • 6 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 96 months from the original
8 of 11Construction stages donefurthest along: Installation of Lifts, 95%
21 of 69Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

SONI ARCADE, BUILDING NO 2 is a Others project by SONI & ASSOCIATES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013002 on 11 Sep 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 96 months from the original filing. 48 of the 69 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSONI ARCADE, BUILDING NO 2
  • TypeOthers
  • Location
    • MUMBAI
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800013002
  • ReraGenie IDRG-MH-34853

Builder

  • NameSONI & ASSOCIATES
  • Entity typeOthers

Key dates

this monthRegisteredSep 2017First promiseDec 2018Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed82 files

Current status

70%48 of 69 units booked
93.8%Work done, per cost certificate

Figures as on 31 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SONI ARCADE IINA2323551469

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

SONI ARCADE II: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed64

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots64
Closed/Covered64

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,544 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Jul 2025

Approvals and building plan

Sanctioning authorityBMC
Permissible FSI3606.37
Proposed, not sanctioned3,606 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMEGHNA APARTMENT CHSL, 64, SV ROAD, SANTACRUZ WEST MUMBAI 400054
Estimated costRs 32.00 cr
Cost incurredRs 30.00 cr
Work done93.75%
BuildingWingEstimatedIncurred
SONI ARCADE IINARs 32.00 crRs 30.00 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBHAVESH RAMESH PAWAR
EngineerNitinkumar Hiralal Jain
EngineerAshok N Prajapati
Chartered AccountantMEENA N SHETTY
Chartered AccountantVISHAL
PartnerRole in project
SONI & ASSOCIATES-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000762Dec 2018 → Dec 2021

Reason as filed by the promoterPending of some approvals

EXT51800005304Dec 2018 → Dec 2021

Reason as filed by the promoterDue to lack of fund and permission issues project is been delayed

EXT51800012783Dec 2018 → Jun 2025

Reason as filed by the promoterDue to Covid and changes in the Plan we where not able to complete the Project in time.

EA22082502413Dec 2018 → Mar 2026

Reason as filed by the promoterDeath of Partner and changes in promoter from partnership firm to Proprietor.

EA14042620631Dec 2018 → Jun 2026

Reason as filed by the promoterwaiting of receipt of Full OC

EA31072621951Dec 2018 → Dec 2026

Reason as filed by the promoterAt the outset, we submit that the construction and development work of the project has been substantially completed. Further, an application for issuance of Occupancy Certificate (OC) has already been submitted to the Competent Authority on 30.06.2026. We further submit that the Competent Authority is presently processing the said application and we have been informed that the Completion Certificate / Occupancy Certificate is expected to be issued shortly. We anticipate receiving the requisite certificate within a period of approximately four weeks. Immediately upon receipt of the same, a copy

Litigation declared1

CaseCourtStatus
1660 /2016THE BOMBAY CITY CIVIL COURTOngoing

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000303181Suresh JashnaniM/s. Soni & Associates15/11/2022
CC12400213Atul Ramanlal ShahSONI & ASSOCIATES24/09/2024
CC12400211Ramanlal Keshavlal ShahSONI & ASSOCIATES24/09/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A March 2026.pdf31 Jul 2026
Withdrawal Update Form 1File: Rera certificate 29072026 SIGNED 260729 173610.pdf30 Jul 2026
Withdrawal Update Form 2File: FORM2_June 2026.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 as on 30 06 2026.pdf30 Jul 2026
Withdrawal Update Form 1File: Form No 1.pdf13 Apr 2026
Withdrawal Update Form 2File: FORM2.pdf13 Apr 2026
Withdrawal Update Form 3File: form 3.pdf13 Apr 2026
Withdrawal Update Form 1File: Form No1.pdf10 Feb 2026
Withdrawal Update Form 2File: FORM 2.pdf10 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf10 Feb 2026
Form 5 (FY 2024-2025)File: Form No 5 March 2025.pdf22 Jan 2026
Form 2A (FY 2024-2025)File: FORM-2A March 2025-new.pdf9 Dec 2025
Withdrawal Update Form 1File: Form No 1.pdf25 Nov 2025
Withdrawal Update Form 2File: FORM2_Sept 2025.pdf25 Nov 2025
Withdrawal Update Form 3File: Form 3 - Sep 2025.pdf25 Nov 2025
Withdrawal Update Form 1File: Form No 1 dt 30 06 2025.pdf17 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf17 Sep 2025
Withdrawal Update Form 3File: Form 3.pdf17 Sep 2025
Withdrawal Update Form 1File: Form 1.pdf22 Aug 2025
Withdrawal Update Form 2File: Form 2.pdf22 Aug 2025
Withdrawal Update Form 3File: Form 3.pdf22 Aug 2025
Form 1File: Form 1.pdf21 Aug 2025
Form 2File: FORM2_March 2025.pdf21 Aug 2025
Form 3File: Form 3.pdf21 Aug 2025
Disclosure of Sold and Booked InventoryFile: Stock details March 2025.pdf21 Aug 2025
Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf4 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A for the year 2023-24 - 310324.pdf4 Apr 2025
Certificates of CA (Form 3)File: FORM 3.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form No 1.pdf5 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2Dec 2024.pdf4 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form No 5.pdf14 Feb 2025
Certificates of CA (Form 3)File: Form 3.pdf11 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf27 Dec 2024
Certificates of CA (Form 3)File: FORM 3 - SONI ARCADE- MARCH 2024.pdf26 Dec 2024
Certificates of CA (Form 3)File: Form 3_compressed.pdf30 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf29 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf29 Jan 2024
Other - LegalFile: Order.pdf19 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2_Sep 2023.pdf28 Nov 2023
Certificates of CA (Form 3)File: Form 3.pdf28 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form No 5.pdf28 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert.pdf18 Aug 2023
Certificates of CA (Form 3)File: FORM 3-1.pdf16 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf30 Jun 2023
Certificates of CA (Form 3)File: Form 3.pdf29 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf3 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf3 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC UPTO 20.pdf28 Jan 2023
Disclosure of sold/ booked inventoryFile: Inventory.pdf11 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A as on 2020.pdf3 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A as on 2021.pdf3 Jan 2023
Declaration about Commencement CertificateFile: Declaration for CC.pdf9 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Engr Quality Assurance Certificate.pdf9 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form no 5 March 2022.pdf9 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf28 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf28 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Soni Arcade RERA form 5 March 2020.pdf28 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Soni Arcade RERA form 5 March 2021.pdf28 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.PDF30 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: form5UT010717to310318.pdf30 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form5march2019.pdf30 Dec 2019
Proforma of Allotment letterFile: agreement-SONI-11-20-1-5.pdf6 Sep 2017
Proforma of Allotment letterFile: agreement-SONI-11-20-6-10.pdf6 Sep 2017
Proforma of Allotment letterFile: agreement-SONI-21-30-1-5.pdf6 Sep 2017
Proforma of Allotment letterFile: agreement-SONI-21-30-6-10.pdf6 Sep 2017
Proforma of Allotment letterFile: agreement-SONI-31-40.pdf6 Sep 2017
Proforma of Allotment letterFile: agreement-SONI-41-50.pdf6 Sep 2017
Proforma of Allotment letterFile: agreement-SONI-51-59.pdf6 Sep 2017
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf6 Sep 2017
Layout approvalFile: Layout plan.pdf31 Jul 2017
Building plan approvalFile: APPROVAL2.pdf31 Jul 2017
Building plan approvalFile: APPROVAL1.pdf31 Jul 2017
PAN CardFile: PAN.pdf31 Jul 2017
Copy of the legal title reportFile: Title.pdf31 Jul 2017
Details of encumbrancesFile: encumbrances.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout plan.pdf31 Jul 2017
Building Plan Approval (IOD)File: APPROVAL1.pdf31 Jul 2017
Building Plan Approval (IOD)File: APPROVAL2.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf31 Jul 2017
Declaration in FORM BFile: affidevit 1.pdf31 Jul 2017

How this compares with Mumbai Suburban

70%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 96 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SONI ARCADE, BUILDING NO 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUMBAI6,700+ in Mumbai Suburban

2 kmSONI ARCADE, BUILDING NOCompleted 33Lapsed / revoked 19Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: SONI & ASSOCIATES

SONI & ASSOCIATES has 1 registration on MahaRERA, including SONI ARCADE, BUILDING NO 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SONI ARCADE, BUILDING NO 2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SONI ARCADE, BUILDING NO 2?

The registered promoter entity is SONI & ASSOCIATES, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SONI ARCADE, BUILDING NO 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SONI ARCADE, BUILDING NO 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SONI ARCADE, BUILDING NO 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SONI ARCADE, BUILDING NO 2?

The professionals named in the filing: Architect: BHAVESH RAMESH PAWAR; Engineer: Nitinkumar Hiralal Jain; Engineer: Ashok N Prajapati; Chartered Accountant: MEENA N SHETTY; Chartered Accountant: VISHAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SONI ARCADE, BUILDING NO 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SONI ARCADE, BUILDING NO 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SONI ARCADE, BUILDING NO 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.