Home / Browse projects / Mumbai Suburban, Maharashtra / SONAL HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

SONAL HEIGHTS

By SONAL DEV-CON PVT LTD

RG-MH-23885 · RERA P51800008992 · Last updated on MahaRERA portal: 7 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 18 months past the filed date
  • Completion date moved by 54 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2025Possession promised18 months past this date
7 of 11Construction stages donefurthest along: Installation of Lifts, 75%
109 of 141Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 100 documents Report an error

SONAL HEIGHTS is a Residential / Group Housing project by SONAL DEV-CON PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008992 on 19 Aug 2017. Possession was promised by 30 Apr 2025 and is now 18 months past that date. The completion date has moved by 54 months from the original filing. 32 of the 141 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameSONAL HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • B.B Magre Marg
    • Nehru Nagar
    • Kurla
    • Mumbai Suburban
    • 400024
  • Pincode400024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008992
  • ReraGenie IDRG-MH-23885

Builder

  • NameSONAL DEV-CON PVT LTD
  • Entity typeCompany
  • Managing DirectorRAMDAS NATHA NILAKH
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked

Key dates

18 months past promisethis monthRegisteredAug 2017First promiseOct 2020Revised toApr 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion30 Apr 2025
  • Revised completionRevised to 30 Apr 2025 (originally 30 Oct 2020)
  • Buildings1 building record
  • Documents filed100 files

Current status

23%32 of 141 units booked

Figures as on 7 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SONAL HEIGHTS-A AND B WINGNA181712615141

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 75%.

SONAL HEIGHTS-A AND B WING: 70% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 7 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered15

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,431 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Oct 2025

Approvals and building plan

Sanctioning authorityTHE SLUM REHABILITATION AUTHORITY
Permissible FSI5118.0
Proposed, not sanctioned5,118 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVASHI NAVI MUMBAI

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMAHALE & ASSOCIATES
EngineerVIRENDRA KUMAR JAIN
EngineerBIPIN G GAIKAR
Chartered AccountantRAMESH D KATHIRIA
Chartered AccountantNILESH M KALSARIYA
PartnerRole in project
SONAL DEV-CON PVT LTD-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800006284Oct 2020 → Oct 2021

Reason as filed by the promoterDue to COVID-19 the construction activities came to be on stands still and further approvals were delayed resulting into the delay in the project. We have been granted the further approval by slum rehabilitation authority by 28/07/2020 copy enclosed to complete the work. Since this have been a slum rehabilitation project and the members were passed in the year 2019 by the slum authority and thereafter the permission for further construction were granted only on 14/08/2020 requiring extension.

EXT51800011836Oct 2020 → Apr 2023

Reason as filed by the promoterTHIS IS THE SRA PROJECT. ON ACCOUNT OF INCREASE IN THE TENANTS AS PER THEIR ELIGIBILITY IOA & LOI IS TO BE RENEWED WHICH WAS RENEWED ONLY IN AUGUST 2020 INCREASING THE NUMBER OF FLOORS UPTO 16TH FLOOR AND WE HAVE COMPLETED. WE HAVE COMPLETED THE 90 PERCENT WORK OF THE BUILDING PROJECT AND NEED TIME TO COMPLETE THE 100 PERCENT WORK AND TO OBTAIN THE OCCUPANCY CERTIFICATE. THEREFORE THIS EXTENSION.

EXT51800017220Oct 2020 → Apr 2024

Reason as filed by the promoterAlthough, we have completed 100% work of the building project and have obtained the full occupancy certificate from Slum Rehabilitation Authority dated 04/07/2023 for rehab Wing-B and Part Occupancy Certificate for Wing-A comprising of Ground plus 12 Upper Floors as per the procedure including water and electricity connection and the complete and final occupancy certificate is expected to be issued in a short time. It is therefore prayed that the extension may be granted.

EXT51800019811Oct 2020 → Apr 2025

Reason as filed by the promoterWe have completed 100% construction work of both the buildings comprising A & B Wing and received Part Occupancy Certificate for A Wing upto 12th Floor and Full Occupancy Certificate for B Wing. After handing over to B Wing Rehab people, we are required to handover the plot area gone into the road to government authority thereafter we will get the remaining Occupancy Certificate for 13th floor to 16th floor of A Wing.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Nov 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Jul 2023

Documents filed100

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 100 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: ARCHITECT CERTIFICATE - 30-06-2024.pdf7 Oct 2025
Form 2File: ENGINEER CERTIFICATE - 30-06-2024.pdf7 Oct 2025
Form 3File: CA CERTIFICATE - 30-06-2024.pdf7 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY - 30-06-2024.pdf7 Oct 2025
Form 1File: ARCHITECT CERTIFICATE - 30-09-2024.pdf7 Oct 2025
Form 2File: ENGINEER CERTIFICATE - 30-09-2024.pdf7 Oct 2025
Form 3File: CA CERTIFICATE - 30-09-2024.pdf7 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY - 30-09-2024.pdf7 Oct 2025
Form 1File: ARCHITECT CERTIFICATE - 31-12-2024.pdf7 Oct 2025
Form 2File: ENGINEER CERTIFICATE - 31-12-2024.pdf7 Oct 2025
Form 3File: CA CERTIFICATE - 31-12-2024.pdf7 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE IF SOLD INVENTORY - 31-12-2024.pdf7 Oct 2025
Form 1File: ARCHITECT CERTIFICATE - 31-03-2025.pdf7 Oct 2025
Form 2File: ENGINEER CERTIFICATE - 31-03-2025.pdf7 Oct 2025
Form 3File: CA CERTIFICATE - 31-03-2025.pdf7 Oct 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD INVENTORY - 31-03-2025.pdf7 Oct 2025
Form 2A (FY 2024-2025)File: FORM 2A - 2024 - 2025.pdf7 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5 - 2024 - 2025.pdf23 Sep 2025
Declaration in FORM BFile: FORM B - SONAL HEIGHTS.pdf16 May 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY - SONAL HEIGHTS.pdf16 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: from 2 A.pdf15 May 2024
Certificates of CA (Form 3)File: form 3 Q-1 c.pdf15 May 2024
Certificates of CA (Form 3)File: form 3 Q - 2_compressed.pdf15 May 2024
Certificates of CA (Form 3)File: form 3 Q- 3_compressed.pdf15 May 2024
Certificates of CA (Form 3)File: form 3 Q - 4_compressed.pdf15 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5.pdf15 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: from 1 7 2023.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: from 1 10 2023.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: from 1 01 2024.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: from 1 04 2024.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 1 7 2023.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 7 2023.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 10 2023.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 1 2024.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: from 2 4 2024.pdf29 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: from 2 A.pdf29 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: kurla OC.pdf24 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 07-08-2021.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 07-11-2020.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 09-08-2019.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 10-07-2022.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 15-10-2022.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 16-01-2023.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 20-08-2018.pdf14 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - 25-01-2023.pdf14 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2 - 31-03-2022.pdf14 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - 2022-23.pdf14 Jul 2023
Certificates of CA (Form 3)File: FORM 3 - 2017-18.pdf12 Jul 2023
Certificates of CA (Form 3)File: FORM 3 - 2018-19.pdf12 Jul 2023
Certificates of CA (Form 3)File: FORM 3 - 2019-20.pdf12 Jul 2023
Certificates of CA (Form 3)File: FORM 3 - 2020-21.pdf12 Jul 2023
Certificates of CA (Form 3)File: FORM 3 - 2021-22.pdf12 Jul 2023
Certificates of CA (Form 3)File: FORM 3 - 2022-23 - Q 1.pdf12 Jul 2023
Certificates of CA (Form 3)File: FORM 3 - 2022-23 - Q 2.pdf12 Jul 2023
Certificates of CA (Form 3)File: FORM 3 - 2022-23 - Q 3.pdf12 Jul 2023
Certificates of CA (Form 3)File: FORM 3 - 2022-23 - Q 4.pdf12 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 10-01-2022.pdf11 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 10-04-2022.pdf11 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 10-07-2022.pdf11 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 10-10-2022.pdf11 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - 10-01-2023.pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A - 2021-22.pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - 2022-23.pdf11 Jul 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY.pdf11 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 - 2021-22.pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A - 2019-2020 - SONAL HEIGHTS.pdf4 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A - 2020 - 2021 - SONAL HEIGHTS.pdf4 May 2022
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY - SONAL HEIGHTS.pdf4 May 2022
CERSAI detailsFile: CERSAI_Search_Report_200236603940_For_Asset_Based_Search_04_05_2022_15_57_34_363.pdf4 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE - SONAL HEIGHTS.pdf21 Apr 2022
Declaration about Commencement CertificateFile: DECLARATION OF COMMENCEMENT CERTIFICATE.pdf30 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE (2).pdf30 Aug 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD - BOOKED INVENTORY.pdf30 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 - 2017 - 2018.pdf30 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - 2018 - 2019.pdf30 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 - 2019 - 2020.pdf30 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 - 2020 - 2021.pdf30 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Deva consultant 2021 certificate_compressed.pdf4 May 2021
Proforma of Allotment letterFile: PROFORMA FOR AGREEMENT FOR SALE - SONAL HEIGHTS.pdf13 Nov 2020
Building plan approvalFile: AMENDED LOI.pdf12 Nov 2020

How this compares with Mumbai Suburban

23%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 54 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SONAL HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nehru Nagar6,700+ in Mumbai Suburban

2 kmSONAL HEIGHTSCompleted 120Lapsed / revoked 115Other 148Dot size: filed unitsN

Filed coordinates, straight-line distance. 383 registered projects within 2 km.

Builder: SONAL DEV-CON PVT LTD

SONAL DEV-CON PVT LTD has 3 registrations on MahaRERA, including YOGI KRISHNA and GOPAL KRISHNA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that SONAL HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SONAL HEIGHTS is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SONAL HEIGHTS?

The registered promoter entity is SONAL DEV-CON PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SONAL HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SONAL HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SONAL HEIGHTS?

The professionals named in the filing: Architect: MAHALE & ASSOCIATES; Engineer: VIRENDRA KUMAR JAIN; Engineer: BIPIN G GAIKAR; Chartered Accountant: RAMESH D KATHIRIA; Chartered Accountant: NILESH M KALSARIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SONAL HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SONAL HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SONAL HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.