SONAKSHI SANKUL
RG-MH-04770 · RERA P52700020538 · Last updated on MahaRERA portal: 20 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 43 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SONAKSHI SANKUL is a Residential / Group Housing project by YUVRAJ SHANKAR BHILARE in Satara, Maharashtra, registered with MahaRERA as P52700020538 on 22 Apr 2019. Possession is promised by 31 Dec 2027. The completion date has moved by 43 months from the original filing. 28 of the 64 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete.
At a glance
Project
- NameSONAKSHI SANKUL
- TypeResidential / Group Housing
- Location
- KARANJE TARF SATARA
- Karanje Tarf Satara (CT)
- Satara
- 415001
- Pincode415001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700020538
- ReraGenie IDRG-MH-04770
Builder
- NameYUVRAJ SHANKAR BHILARE
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Apr 2019
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 May 2024)
- Buildings2 building records
- Documents filed76 files
Current status
Figures as on 20 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SONAKSHI SANKUL VAIBHAV A | NA | 5 | 5 | 16 | 8 | 24 |
| SONAKSHI SANKUL VAIDEHI B | NA | 5 | 5 | 40 | 0 | 40 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.
SONAKSHI SANKUL VAIBHAV A90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SONAKSHI SANKUL VAIDEHI B57%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 68% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 55% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 88% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| RAHUL DAGADU BANSODE | Karanje Tarf Satara (CT) | Satara |
| ATUL DAGADU BANSODE | Karanje Tarf Satara (CT) | Satara |
| ROHINI DAGADU BANSODE | Karanje Tarf Satara (CT) | Satara |
| SONABAI DAGDU BANSODE | Karanje Tarf Satara (CT) | Satara |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SONAKSHI SANKUL VAIDEHI B | NA | Rs 3.34 cr | Rs 1.91 cr |
| SONAKSHI SANKUL VAIBHAV A | NA | Rs 2.01 cr | Rs 1.91 cr |
| - | NA | Rs 1.57 cr | Rs 52.45 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RUSHIKESH P LOKHANDE |
| Engineer | NITIN SHIVAJI THORAT |
| Chartered Accountant | VITTHAL JADHAV |
| Chartered Accountant | SAMADHAN RAMDAS KADAM |
| Partner | Role in project |
|---|---|
| YUVRAJ SHANKAR BHILARE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterEXTENSION PROJECT
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Apr 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Apr 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed76
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Sonakshi Sankul - Form 1 March 26.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: Sonakshi Sankul - Form 2 March 26.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: Yuvraj Shankar Bhilare Form no 3.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: Sonakshi Sankul - Form 1 Dec 2025.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: Sonakshi Sankul - Form 2 Dec 2025.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: Sonakshi Sankul - Form 3 Dec 2025.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: Sonakshi Sankul - Form 1 Sep 2025.pdf | 26 Dec 2025 |
| Withdrawal Update Form 2File: Sonakshi Sankul - Form 2 Sep 2025.pdf | 26 Dec 2025 |
| Withdrawal Update Form 3File: Sonakshi Sankul - Form 3 sEP 2025.pdf | 26 Dec 2025 |
| Form 5 (FY 2024-2025)File: Sonakshi Sankul - Form 5 Mar 2025.pdf | 26 Dec 2025 |
| Withdrawal Update Form 1File: Sonakshi Sankul - Form 1 jun 2025.pdf | 25 Dec 2025 |
| Withdrawal Update Form 2File: Sonakshi Sankul - Form 2 jun 2025.pdf | 25 Dec 2025 |
| Withdrawal Update Form 3File: Sonakshi Sankul - Form 3 jun 2025.pdf | 25 Dec 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare B Sonakshi Sankul Mar 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare A Sonakshi Sankul Jun 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare A Sonakshi Sankul Sep 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare A Sonakshi Sankul Dec 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare B Sonakshi Sankul Mar 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare B Sonakshi Sankul Dec 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare B Sonakshi Sankul Jun 24.pdf | 6 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare B Sonakshi Sankul Sep 24.pdf | 6 Mar 2025 |
| Certificates of CA (Form 3)File: RERA Certificate 3 Sonakshi -Mar 2024.pdf | 6 Mar 2025 |
| Certificates of CA (Form 3)File: RERA Certificate 3 Sonakshi -Jun 2024.pdf | 6 Mar 2025 |
| Certificates of CA (Form 3)File: RERA Certificate 3 Sonakshi -Sep 2024.pdf | 6 Mar 2025 |
| Certificates of CA (Form 3)File: RERA Certificate 3 Sonakshi -Dec 2024.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Sonakshi -Mar 2024.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Sonakshi -Jun 2024.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Sonakshi -Sep 2024.pdf | 6 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Sonakshi -Dec 2024.pdf | 6 Mar 2025 |
| Layout approvalFile: 1 Layout Up To 3MB.pdf | 1 Apr 2024 |
| Building plan approvalFile: 2 Revised Plan A Wing Uo To 3MB.pdf | 1 Apr 2024 |
| Building plan approvalFile: 3 Revised Plan B Wing Up To 3MB.pdf | 1 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: 1 Layout Up To 3MB.pdf | 1 Apr 2024 |
| Building Plan Approval (IOD)File: 2 Revised Plan A Wing Uo To 3MB.pdf | 1 Apr 2024 |
| Building Plan Approval (IOD)File: 3 Revised Plan B Wing Up To 3MB.pdf | 1 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Bandhkam Parwana.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare A Sonakshi Sankul Mar 2023.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare A Sonakshi Sankul Jun 2023.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare A Sonakshi Sankul Sep 2023.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare A Sonakshi Sankul Dec 2023.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare B Sonakshi Sankul Mar 2023.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare B Sonakshi Sankul Jun 2023.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare B Sonakshi Sankul Sep 2023.pdf | 1 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ark Certificare B Sonakshi Sankul Dec 2023.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Sonakshi -Mar 2022.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Sonakshi -Mar 2023.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Sonakshi -Jun 2023.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Sonakshi -Sep 2023.pdf | 1 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Sonakshi -Dec 2023.pdf | 1 Apr 2024 |
| Certificates of CA (Form 3)File: RERA Certificate 3 Sonakshi -Mar 2022 - 3MB.pdf | 1 Apr 2024 |
| Certificates of CA (Form 3)File: RERA Certificate 3 Sonakshi -Mar 2023 - 3MB.pdf | 1 Apr 2024 |
| Certificates of CA (Form 3)File: RERA Certificate 3 Sonakshi -Jun 2023 - 3MB.pdf | 1 Apr 2024 |
| Certificates of CA (Form 3)File: RERA Certificate 3 Sonakshi -Dec 2023 - 3MB.pdf | 1 Apr 2024 |
| Certificates of CA (Form 3)File: SONAKSHI SANKUL FORM 3 june 20.pdf | 24 Jul 2021 |
| Certificates of CA (Form 3)File: SONAKSHI SANKUL FORM 3 june 20.pdf | 24 Jul 2021 |
| Certificates of CA (Form 3)File: SONAKSHI SANKUL FORM 3 sep 20.pdf | 24 Jul 2021 |
| Certificates of CA (Form 3)File: SONAKSHI SANKUL FORM 3 dec 20.pdf | 24 Jul 2021 |
| Certificates of CA (Form 3)File: SONAKSHI SANKUL FORM 3 mar 21.pdf | 24 Jul 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arki Form 1 June 19 Sonakshi.pdf | 21 Dec 2019 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arki Form 1 Sep 19 Sonakshi.pdf | 21 Dec 2019 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enigineer Form 2 June 19 Sonakshi.pdf | 21 Dec 2019 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2 sep 19 sonakshi.pdf | 21 Dec 2019 |
| Building plan approvalFile: Building Plan 3 final.pdf | 13 Apr 2019 |
| Building plan approvalFile: building Plan A final.pdf | 13 Apr 2019 |
| Building plan approvalFile: Building Plan B Final.pdf | 13 Apr 2019 |
| Building Plan Approval (IOD)File: Building Plan 3 final.pdf | 13 Apr 2019 |
| Building Plan Approval (IOD)File: building Plan A final.pdf | 13 Apr 2019 |
| Building Plan Approval (IOD)File: Building Plan B Final.pdf | 13 Apr 2019 |
| Layout approvalFile: Layout.pdf | 28 Mar 2019 |
| Copy of the legal title reportFile: Search Tital Report.pdf | 28 Mar 2019 |
| Details of encumbrancesFile: NON ENCUMBRANCE.pdf | 28 Mar 2019 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 28 Mar 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf | 28 Mar 2019 |
| Declaration in FORM BFile: Form B Affidavit Declaration.pdf | 28 Mar 2019 |
| Certificates of CA (Form 3)File: Form No 3.pdf | 28 Mar 2019 |
| Proforma of Allotment letterFile: Rera - Agreement Allotment Marathi SONAKSHI SANKUL.pdf | 28 Mar 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 76 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SONAKSHI SANKUL on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KARANJE TARF SATARA1,100+ in Satara
Filed coordinates, straight-line distance. 77 registered projects within 2 km.
PRADHAN MANTRI AWAS YOJANA SATARA PHASE I
SATARA MUNICIPAL COUNCIL SATARA
LANDMARK TOWERS
KANGRALKAR INFRASTRUCTURE
Bhuvi Commercia
LAXMI NARAYAN INDUSTRIES
SAMARVEER SKYLINE
SHRI MANGALMURTI BUILDERS
Mathura
Balkrishna Pandurang Jadhav
BAJIRAO EMPIRE
SHREE SHESHACHAL DEVELOPERS
See every Satara project, with the district possession charts
Builder: YUVRAJ SHANKAR BHILARE
YUVRAJ SHANKAR BHILARE has 1 registration on MahaRERA, including SONAKSHI SANKUL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What are my rights if SONAKSHI SANKUL is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SONAKSHI SANKUL?
The registered promoter entity is YUVRAJ SHANKAR BHILARE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SONAKSHI SANKUL?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SONAKSHI SANKUL?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SONAKSHI SANKUL?
The professionals named in the filing: Architect: RUSHIKESH P LOKHANDE; Engineer: NITIN SHIVAJI THORAT; Chartered Accountant: VITTHAL JADHAV; Chartered Accountant: SAMADHAN RAMDAS KADAM. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SONAKSHI SANKUL?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback