SOLITAIRE

By M/s. Panache Realty

RG-MH-25054 · RERA P52000004091 · Last updated on MahaRERA portal: 27 Aug 2020

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2020Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

SOLITAIRE is a Others project by M/s. Panache Realty in Raigarh, Maharashtra, registered with MahaRERA as P52000004091 on 7 Aug 2017. The registration is recorded completed; possession was promised by 29 Dec 2020. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameSOLITAIRE
  • TypeOthers
  • Location
    • New Panvel
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000004091
  • ReraGenie IDRG-MH-25054

Builder

  • NameM/s. Panache Realty
  • Entity typePartnership
  • GSTIN27AAQFP1660F1Z3
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersRahul Bhagwanji Minat, Bhagwanji Dharamshi Minat
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseJun 2019Revised toDec 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on7 Aug 2017
  • Promised completion29 Dec 2020
  • Revised completionRevised to 29 Dec 2020 (originally 30 Jun 2019)
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SOLITAIRENA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Aug 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SOLITAIRE: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Aug 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed41

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots41
Closed/Covered28
Open Space13

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,851 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/s. KUNDKUND ENTERPRISESKurlaMumbai Suburban

Approvals and building plan

Permissible FSI2776.45
Proposed, not sanctioned2,776 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch239, Garodia Chambers, Kalbadevi Road 400002

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMIT N PATIL ARCHITECTS
EngineerAdharshila Consultants
PartnerRole in project
M/s. Panache Realty-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000002079Jun 2019 → Jun 2020

Reason as filed by the promoterThat we had submitted our application towards obtaining the Occupancy Certificate for the above mentioned Project through our appointed Architect vide Application No.-13389 on 06-08-2018. After a joint site visit with the concerned officer of PMC, we were informed vide letter No.-8627 dated 31-08-2018 stating reason that certain directives were awaited from the Urban Development Dept. until which our OC application would be kept on hold. The work is completed 100% and we are awaiting for the occupancy certificate from the competent authority

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Aug 2020

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Final Certificate of Architect (form 4)27-08-20.pdf27 Aug 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc.pdf24 Aug 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 PANACHE.pdf21 Nov 2019
Certificates of CA (Form 5)File: PANACHE REALTY.pdf17 Oct 2018
Building plan approvalFile: 3rd and typical.pdf27 Jul 2017
Building plan approvalFile: second floor and terace floor.pdf27 Jul 2017
Building plan approvalFile: typical and 11th floor.pdf27 Jul 2017
Building plan approvalFile: 12th and 13th floor.pdf27 Jul 2017
Building plan approvalFile: 14th floor.pdf27 Jul 2017
Building plan approvalFile: first floor.pdf27 Jul 2017
Layout approvalFile: ground floor.pdf27 Jul 2017
PAN CardFile: PANACHE PANCARD.pdf27 Jul 2017
PAN CardFile: KUNDKUND PAN.pdf27 Jul 2017
Copy of the legal title reportFile: Search title.pdf27 Jul 2017
Details of encumbrancesFile: Details of Encumbrances.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: ground floor.pdf27 Jul 2017
Building Plan Approval (IOD)File: first floor.pdf27 Jul 2017
Building Plan Approval (IOD)File: second floor and terace floor.pdf27 Jul 2017
Building Plan Approval (IOD)File: 3rd and typical.pdf27 Jul 2017
Building Plan Approval (IOD)File: typical and 11th floor.pdf27 Jul 2017
Building Plan Approval (IOD)File: 12th and 13th floor.pdf27 Jul 2017
Building Plan Approval (IOD)File: 14th floor.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC copy.pdf27 Jul 2017
Declaration in FORM BFile: FORM B - PANACHE.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf27 Jul 2017
Certificates of CA (Form 3)File: Form 3.pdf27 Jul 2017
Proforma of Allotment letterFile: PANACHE REALTY-MASTER FILE-AS PER RERA ACT.pdf27 Jul 2017
Proforma of Allotment letterFile: KUNDKUNAD_ENTERPIRSIES-MASTER_FILE-AS_PER_RERA_ACT.pdf27 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationRegisteredStatusPromisedDelivered
Vard VinayakP52000023341Ulwe, RaigarhDec 2019CompletedJun 2022Registered original: Mar 2022Late, Aug 2022

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 18 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SOLITAIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near New Panvel5,900+ in Raigarh

2 kmSOLITAIRECompleted 51Lapsed / revoked 13Other 89Dot size: filed unitsN

Filed coordinates, straight-line distance. 153 registered projects within 2 km.

Builder: M/s. Panache Realty

M/s. Panache Realty has 3 registrations on MahaRERA, including SOLITAIRE and Vard Vinayak. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SOLITAIRE is delayed beyond 29 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SOLITAIRE?

The registered promoter entity is M/s. Panache Realty, a partnership as per the filing. Its GSTIN 27AAQFP1660F1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SOLITAIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SOLITAIRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SOLITAIRE?

The professionals named in the filing: Architect: AMIT N PATIL ARCHITECTS; Engineer: Adharshila Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SOLITAIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SOLITAIRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SOLITAIRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.