Home / Browse projects / Pune, Maharashtra / SOHO

Registration lapsed Litigation declared Residential / Group Housing project

SOHO

By PRIDE BUILDERS LLP

RG-MH-67989 · RERA P52100046546 · Last updated on MahaRERA portal: 21 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 6 months past the filed date
  • Litigation declared, 1 case
  • 1 complaint at MahaRERA

Clear

  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2026Possession promised6 months past this date
18 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 90%
0 of 363Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

SOHO is a Residential / Group Housing project by PRIDE BUILDERS LLP in Pune, Maharashtra, registered with MahaRERA as P52100046546 on 10 Aug 2022. Possession was promised by 30 Apr 2026 and is now 6 months past that date. 363 of the 363 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSOHO
  • TypeResidential / Group Housing
  • Location
    • KNOWLEDGE CITY ROAD
    • CHARHOLI
    • Haveli
    • Pune
    • 412015
  • Pincode412015
  • RERA no.P52100046546
  • ReraGenie IDRG-MH-67989

Builder

  • NamePRIDE BUILDERS LLP
  • Entity typeOthers
  • GSTIN27AAPFP0869F1ZV
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Authorised SignatorySURYKANTH DHANAWADE DHANAWADE
  • PartnerPRIDE BUILDERS LLP LLP
  • Other registrations12 more →
  • Completed3 of 13
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date2
  • Declared earlier projects2 →

Key dates

6 months past promisethis monthRegisteredAug 2022PromisedApr 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Aug 2022
  • Promised completion30 Apr 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed78 files

Current status

100%363 of 363 units booked
99.8%Work done, per cost certificate

Figures as on 21 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA26231830183
BUILDING BNA26231800180

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 21 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

BUILDING A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING B92%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)80%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises55%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 21 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed368

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots368
Closed/Covered338
Open Space30
BuildingClosed/CoveredOpen SpaceTotal
BUILDING A16915184
BUILDING B16915184

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,446 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Oct 2025
LandownerVillageDistrict
MAHAVEER CO-OPERATIVE HOUSING SOCIETY LTDCHARHOLIPune

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION
Permissible FSI47131.64
Proposed, not sanctioned37,695 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD SHIVAJI NAGAR PUNE 411004
Estimated costRs 109.70 cr
Cost incurredRs 109.54 cr
Work done99.85%
BuildingWingEstimatedIncurred
BUILDING ANARs 42.56 crRs 42.56 cr
BUILDING BNARs 42.34 crRs 42.18 cr
-NARs 24.79 crRs 24.79 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPATIL & BUGADE ASSOCIATES
ArchitectAVINASH PATIL & ASSOCIATES
EngineerDNYANESHWAR RAJENDRA MANE
EngineerSHANTANU GANJAVE
Chartered AccountantSAC & CO LLP
Chartered AccountantShah Khandelwal Jain & Associates
PartnerRole in project
PRIDE BUILDERS LLP-

Litigation declared1

CaseCourtStatus
1981/2016SHIVAJAI NAGAR CIVIL JUDGE SENIOR DIVISIONFRAME ISSUES

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12500104Ram GawaliPRIDE BUILDERS LLP02/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jul 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: QTY ASSURANCE CERT FORM 2A SOHO.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1 Soho.pdf16 Apr 2026
Withdrawal Update Form 2File: Form 2 Soho.pdf16 Apr 2026
Withdrawal Update Form 3File: Form 3-Soho.pdf16 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERT FORM 1 SOHO 01012026.pdf30 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf30 Jan 2026
Withdrawal Update Form 3File: C A CERT FORM 3 SOHO 20012026.pdf30 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 upload.pdf2 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf1 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf1 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf1 Dec 2025
Form 1File: Form 1.pdf16 Oct 2025
Form 2File: Form 2.pdf16 Oct 2025
Form 3File: Form 3.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular upload.pdf16 Oct 2025
Form 1File: ARCHITECT CERT SOHO 30062025.pdf16 Oct 2025
Form 2File: ENGINEER CERT SOHO 30062025.pdf16 Oct 2025
Form 3File: Form 3 upload.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular upload.pdf16 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Pride SOHO.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT SOHO 31032025.pdf11 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERT SOHO 31032025.pdf11 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QTY ASSURANCE CERT SOHO 31032025.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERT SOHO 14012025.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT SOHO.pdf10 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERT SOHO 31122024.pdf10 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY CERT SOHO.pdf10 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SOHO.pdf16 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERT SOHO 30092024.pdf11 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QTY ASSURANCE CERT SOHO 30092024.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SOHO.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT SOHO 30062024.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERT SOHO 30062024.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QTY ASSURANCE CERT SOHO 30062024.pdf26 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERT SOHO 15042024.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT SOHO 31032024.pdf11 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERT SOHO 31032024.pdf11 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QTY ASSURANCE CERT SOHO 31032024.pdf11 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SOHO Form 3.pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SOHO.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SOHO ENG.pdf16 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SOHO.pdf16 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: C A CERT SOHO 01112023.pdf10 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SOHO QULITY.pdf10 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: qulity soho.pdf7 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SOHO QUALITY.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT SOHO 31122022.pdf10 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT SOHO CLUSTER 5 31122022.pdf10 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QTY ASSURANCE CERT SOHO 31122022.pdf10 Jan 2023
Building plan approvalFile: SOHO A BUILD TYP FLOOR PLAN.pdf15 Dec 2022
Building plan approvalFile: SOHO B BUILD TYP FLOOR PLAN.pdf15 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: SOHO A BUILD TYP FLOOR PLAN.pdf15 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: SOHO B BUILD TYP FLOOR PLAN.pdf15 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf15 Dec 2022
Proforma of Agreement for saleFile: agreement draft for revised CC.pdf15 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SOHO quality.pdf19 Oct 2022
Details of encumbrances concerned to LegalFile: self declaration on company letter head.pdf12 Jul 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER FOR SOHO.pdf12 Jul 2022
Proforma of Allotment letterFile: AGREEMENT DRAFT SOHO.pdf12 Jul 2022
Copy of the legal title reportFile: TITLE REPORT SET 4 09042011.pdf6 Jul 2022
Layout approvalFile: SOHO LAYOUT.pdf30 Jun 2022
Building plan approvalFile: cluster 5 floor plan soho.pdf30 Jun 2022
PAN CardFile: PBLLP PAN CARD COPY.pdf30 Jun 2022
Copy of the legal title reportFile: TITLE REPORT SOHO 28062022.pdf30 Jun 2022
Details of encumbrances concerned to FinanceFile: SELF DECLARATION SOHO 05082022.pdf30 Jun 2022
Details of encumbrances concerned to LegalFile: Plaint.pdf30 Jun 2022
Copy of Layout Approval (in case of layout)File: SOHO LAYOUT.pdf30 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: cluster 5 floor plan soho.pdf30 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencment certificate.pdf30 Jun 2022
Declaration about Commencement CertificateFile: DECLARATION CC SOHO 28062022.pdf30 Jun 2022
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION SOHO 28062022.pdf30 Jun 2022
CERSAI detailsFile: CERSAI UNDERTAKING SOHO 05082022.pdf30 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERT SOHO 30062022.pdf30 Jun 2022
Proforma of Allotment letterFile: Agreement to sale.pdf30 Jun 2022
Proforma of Allotment letterFile: Allotment letter SOHO.pdf30 Jun 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT LETTER SOHO 05082022.pdf30 Jun 2022
Deviation Report with respect to Allotment letterFile: ALLOTMENT LETTER FOR SOHO.pdf30 Jun 2022
Deviation Report with respect to model copy of AgreementFile: AGREEMENT DRAFT SOHO.pdf30 Jun 2022

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise4 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
MANHATTANP52100026529CHARHOLI BK, Pune-Sep 2020OngoingOct 2024Not delivered
MANHATTANP52100026529CHARHOLI BK, Pune-Sep 2020OngoingOct 2024Not delivered
MANHATTANP52100026529CHARHOLI BK, Pune-Sep 2020OngoingOct 2024Not delivered
MANHATTANP52100026529CHARHOLI BK, Pune-Sep 2020OngoingOct 2024Not delivered
BROOKLYNS NO 129 CHARHOLI NEAR DY PATIL COLLEGE PUNE550-CompletedDec 2016Oct 2016

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SOHO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHARHOLI13,700+ in Pune

Builder: PRIDE BUILDERS LLP

PRIDE BUILDERS LLP has 13 registrations on MahaRERA, including MANHATTAN and ATLANTIC. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SOHO shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SOHO is delayed beyond 30 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SOHO?

The registered promoter entity is PRIDE BUILDERS LLP, an others as per the filing. Its GSTIN 27AAPFP0869F1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SOHO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SOHO?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SOHO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SOHO?

The professionals named in the filing: Architect: PATIL & BUGADE ASSOCIATES; Architect: AVINASH PATIL & ASSOCIATES; Engineer: DNYANESHWAR RAJENDRA MANE; Engineer: SHANTANU GANJAVE; Chartered Accountant: SAC & CO LLP; Chartered Accountant: Shah Khandelwal Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SOHO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SOHO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SOHO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.