Home / Browse projects / Pune, Maharashtra / MANHATTAN-E BUILDING

Registration lapsed No litigation declared Residential / Group Housing project

MANHATTAN-E BUILDING

By PRIDE BUILDERS LLP

RG-MH-81610 · RERA P52100045218 · Last updated on MahaRERA portal: 16 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 55%
1Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

MANHATTAN-E BUILDING is a Residential / Group Housing project by PRIDE BUILDERS LLP in Pune, Maharashtra, registered with MahaRERA as P52100045218 on 10 May 2022. Possession was promised by 31 Dec 2024 and is now 22 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMANHATTAN-E BUILDING
  • TypeResidential / Group Housing
  • Location
    • KNOWLEDGE CITY ROAD
    • CHARHOLI
    • Haveli
    • Pune
    • 412015
  • Pincode412015
  • RERA no.P52100045218
  • ReraGenie IDRG-MH-81610

Builder

  • NamePRIDE BUILDERS LLP
  • Entity typeOthers
  • GSTIN27AAPFP0869F1ZV
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Authorised SignatorySURYKANTH DHANAWADE DHANAWADE
  • PartnerPRIDE BUILDERS LLP LLP
  • Other registrations12 more →
  • Completed3 of 13
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date2
  • Declared earlier projects2 →

Key dates

22 months past promisethis monthRegisteredMay 2022PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 May 2022
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E-BUILDINGNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 55%.

E-BUILDING: 56% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%

Progress on shared amenities15

As on 16 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed130

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots130
Closed/Covered130

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,583 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Jun 2025

Approvals and building plan

Sanctioning authorityPCMC
Permissible FSI13269.74
Proposed, not sanctioned10,616 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD SHIVAJI NAGAR PUNE 411004

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAVINASH PATIL
ArchitectPATIL & BUGADE ASSOCIATES
EngineerDNYANESHWAR MANE
EngineerDNYANESHWAR RAJENDRA MANE
Chartered AccountantAmit Satish Shingvi
Chartered AccountantShah Khandelwal Jain & Associates
Chartered AccountantSAC & CO LLP
PartnerRole in project
PRIDE BUILDERS LLP-

Litigation declared1

CaseCourtStatus
1981/2016SHIVAJAI NAGAR CIVIL JUDGE SENIOR DIVISIONEVIDENCE STAGE

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12503894PRIDE BUILDERS LLP PRIDE BUILDERS LLPRICHARD SELVARAJ07/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Oct 2024

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Manhaatan E.pdf16 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: form 4 RERA.pdf23 Oct 2024
Architect’s Certificate on Completion of Project (Form 4)File: form 4 RERA.pdf10 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: complition e building.pdf10 Oct 2024
Other - TechnicalFile: Completion mail by PCMC to RERA.pdf10 Oct 2024
Other - TechnicalFile: complition e building.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT MANHATTAN E BLDG 30062024.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERT MANHATTAN 30062024.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QTY ASSURANCE CERT MANHATTAN 30062024.pdf26 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A CERT MANHATTAN E BLDG 15042024.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT MANHATTAN E BLDG 31032024.pdf11 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QTY ASSURANCE CERT MANHATTAN E BLDG 31032024.pdf11 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Manhattan E Form 3.pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MANHATTEN 2.pdf16 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: MANHATTEN E.pdf16 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: C A CERT MANHATTAN E BLDG 01112023.pdf10 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: MANHATTAN PH2QULITY.pdf10 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: qulity cluster ph 2.pdf7 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: MANHATTAN E QUALITY.pdf12 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIF MANHATTAN E.pdf2 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT MANHATTAN E BLDG 31122022.pdf10 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT MANHATTAN E BLDG 31122022.pdf10 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: QTY ASSURANCE CERT MANHATTAN E BLDG 31122022.pdf10 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Manhattan E Buil Quality.pdf14 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: manhaten qulity ph 2.pdf20 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf3 May 2022
Layout approvalFile: LAYOUT.pdf2 May 2022
Building plan approvalFile: scan1174.pdf2 May 2022
Building plan approvalFile: scan1175.pdf2 May 2022
PAN CardFile: PAN PBLLP.pdf2 May 2022
Copy of the legal title reportFile: LEGAL TITLE REPORT MANHATTAN E BLDG 28042022.pdf2 May 2022
Copy of the legal title reportFile: TITLE REPORT SET 4 09042011.pdf2 May 2022
Details of encumbrancesFile: SELF DECLARATION MANHATTAN E BLDG 28042022.pdf2 May 2022
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf2 May 2022
Building Plan Approval / NA Order for plotted developmentFile: scan1174.pdf2 May 2022
Building Plan Approval / NA Order for plotted developmentFile: scan1175.pdf2 May 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERT 16042021.pdf2 May 2022
Declaration about Commencement CertificateFile: DECLARATION CC MANHATTAN E BLDG 28042022.pdf2 May 2022
Declaration in FORM BFile: AFFIDAVIT MANHATTAN 28042022.pdf2 May 2022
CERSAI detailsFile: CERSAI undertaking.pdf2 May 2022
Proforma of Allotment letterFile: Allotment by LOI.pdf2 May 2022
Proforma of Allotment letterFile: Agreement draft.pdf2 May 2022

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise4 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
MANHATTANP52100026529CHARHOLI BK, Pune-Sep 2020OngoingOct 2024Not delivered
MANHATTANP52100026529CHARHOLI BK, Pune-Sep 2020OngoingOct 2024Not delivered
MANHATTANP52100026529CHARHOLI BK, Pune-Sep 2020OngoingOct 2024Not delivered
MANHATTANP52100026529CHARHOLI BK, Pune-Sep 2020OngoingOct 2024Not delivered
BROOKLYNS NO 129 CHARHOLI NEAR DY PATIL COLLEGE PUNE550-CompletedDec 2016Oct 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MANHATTAN-E BUILDING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHARHOLI13,700+ in Pune

Builder: PRIDE BUILDERS LLP

PRIDE BUILDERS LLP has 13 registrations on MahaRERA, including MANHATTAN and ATLANTIC. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that MANHATTAN-E BUILDING shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MANHATTAN-E BUILDING is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MANHATTAN-E BUILDING?

The registered promoter entity is PRIDE BUILDERS LLP, an others as per the filing. Its GSTIN 27AAPFP0869F1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MANHATTAN-E BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MANHATTAN-E BUILDING?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MANHATTAN-E BUILDING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MANHATTAN-E BUILDING?

The professionals named in the filing: Architect: AVINASH PATIL; Architect: PATIL & BUGADE ASSOCIATES; Engineer: DNYANESHWAR MANE; Engineer: DNYANESHWAR RAJENDRA MANE; Chartered Accountant: Amit Satish Shingvi; Chartered Accountant: Shah Khandelwal Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANHATTAN-E BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANHATTAN-E BUILDING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANHATTAN-E BUILDING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.