Home / Browse projects / Thane, Maharashtra / SNEHAM

Completed No litigation declared Residential / Group Housing project

SNEHAM

By Paridhi Developers

RG-MH-83375 · RERA P51700020410 · Last updated on MahaRERA portal: 2 Dec 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 7 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2025Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Basement (if any), 0%
13 of 42Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 153 documents Report an error

SNEHAM is a Residential / Group Housing project by Paridhi Developers in Thane, Maharashtra, registered with MahaRERA as P51700020410 on 9 Apr 2019. The registration is recorded completed; possession was promised by 19 Sep 2025. The completion date has moved by 7 months from the original filing. 29 of the 42 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSNEHAM
  • TypeResidential / Group Housing
  • Location
    • SATYANANDJI MAHARAG MARG
    • BHAYANDER WEST
    • BHAYANDAR
    • Thane
    • 401101
  • Pincode401101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700020410
  • ReraGenie IDRG-MH-83375

Builder

  • NameParidhi Developers
  • Entity typePartnership
  • PartnerParidhi Lalit Agarwal

Key dates

this monthRegisteredApr 2019First promiseFeb 2025Revised toSep 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on9 Apr 2019
  • Promised completion19 Sep 2025
  • Revised completionRevised to 19 Sep 2025 (originally 28 Feb 2025)
  • Buildings1 building record
  • Documents filed153 files

Current status

69%29 of 42 units booked
100.0%Work done, per cost certificate

Figures as on 2 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SNEHAMNA161542042

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

SNEHAM: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 2 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes100%

Parking filed23

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots23
Closed/Covered23

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area760 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Oct 2025

Approvals and building plan

Sanctioning authorityMIRA BHAYANDAR MUNICIPAL CORPORATION
Permissible FSI3040.0
Proposed, not sanctioned3,007 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJANKI HERITAGE, C WING, MIRA BHAYANDER - 401 101
Estimated costRs 11.00 cr
Cost incurredRs 11.00 cr
Work done100.0%
BuildingWingEstimatedIncurred
SNEHAMNARs 11.00 crRs 11.00 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHISH H CHOGLE
EngineerRAJESH B DUBEY
EngineerSAHIL SIDDIQUE
Chartered AccountantSANJAYKUMAR SHIVKUMAR SHARMA
Chartered AccountantVAIBHAV HARISHCHANDRA PATIL
Chartered AccountantVIVEK J THAR
PartnerRole in project
Paridhi Developers-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700027561Feb 2025 → Aug 2025

Reason as filed by the promoter1. We had started work of our project in the mid of 2019 and COVID-19 (Corona Virus) Pandemic has adversely affected the project work. 2. Due to Nationwide lockdown from March 2020, many of our labourers had migrated to their native places and therefore it was very difficult to arrange labourers to carry out pending construction & other activities of our project during the period. 3. Sir, you will also appreciate that there was a long break in supply chain of building and other related materials & services, which has severely impacted our project. 4. It was difficult to carry out the construct

EA17102518149Feb 2025 → Sep 2025

Reason as filed by the promoter1. We have completed 100% work of the Project. 2. We have also obtained Full Occupancy Certificate from planning authority on 19/09/2025. 3. We had duly applied for Occupancy Certificate (OC) in April 2025, well in advance, with the expectation of receiving the same within 2-3 months, i.e., before the stipulated completion date. 4. However, the Occupancy Certificate was issued to us on 19/09/2025 i.e., just 19 days beyond the registered completion date. 5. Since we were confident of receiving the OC before 31/08/2025, no application for extension was filed at that time. In light of the above,

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Mar 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed153

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 153 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: OC Plans.pdf2 Dec 2025
Occupational CertificateFile: Occupation Certificate.pdf24 Oct 2025
Withdrawal Update Form 1File: Form 1_Architect_Certificate_Sept 2025.pdf17 Oct 2025
Withdrawal Update Form 2File: Form 2_Engineers Certificate_Sep 2025.pdf17 Oct 2025
Withdrawal Update Form 3File: Form 3_CA Certificate_Sep 2025.pdf17 Oct 2025
Withdrawal Update Form 1File: Form 1_Architect Certificate.pdf16 Oct 2025
Withdrawal Update Form 2File: Form 2_Engineers Certificate_Jun 25.pdf16 Oct 2025
Withdrawal Update Form 3File: Form3_CA Certificate.pdf16 Oct 2025
Form 1File: Form_1_Architect Certificate_Mar 2025.pdf11 Oct 2025
Form 2File: Form_2_Engineers Certificate_Mar 2025.pdf11 Oct 2025
Form 3File: Form_3_CA Certificate_Mar 2025.pdf11 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_Booked Inventory_Mar 2025.pdf11 Oct 2025
Certificates of CA (Form 3)File: Form_3_CA Certificate_Mar 2025.pdf21 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_Engineers Certificate_Mar 2025.pdf21 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_1_Architect Certificate_Mar 2025.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form_2_Engineers Certificate_Mar 2025.pdf24 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Mar 2025.pdf24 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form_1_Architect Certificate.pdf24 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate.pdf24 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A_Quality Assurance.pdf24 Mar 2025
Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf19 Mar 2025
Certificates of CA (Form 3)File: CA RERA Certificate Form 3.pdf20 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA RERA Audit Form 5.pdf20 Feb 2025
Details of encumbrances concerned to FinanceFile: No Encumbrance Certificate Legal.pdf17 Feb 2025
Declaration in FORM BFile: Form B_Affidavit cum Declaration.pdf17 Feb 2025
CERSAI detailsFile: CERSAI Declaration.pdf17 Feb 2025
CERSAI detailsFile: CERSAI_Search_Report.pdf17 Feb 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Bank Declaration.pdf17 Feb 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Bank Declaration.pdf17 Feb 2025
Deviation Report with respect to Allotment letterFile: No Deviation in Allotment Letter.pdf17 Feb 2025
Details of encumbrances concerned to LegalFile: No Encumbrance Certificate Legal.pdf17 Feb 2025
Deviation Report with respect to model copy of AgreementFile: No Deviation in Agreement for Sale_Letter.pdf17 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_ for disclosure of Interest- Kimtilal K gupta.pdf17 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_ for disclosure of Interest- Paridhi Agrawal.pdf17 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form_2A_Qulaity Assurance Certificate_Dec 2024.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_Dec 2024.pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Certificate_Dec 2024.pdf25 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Dec 2024.pdf25 Jan 2025
Certificates of CA (Form 3)File: Form 3_CA_Sept 2024.pdf19 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architech Certificate_Sept 2024.pdf15 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_ Engineers Certificate_Sept 2024.pdf15 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Sep 2024.pdf15 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_June 2024.pdf17 Oct 2024
Certificates of CA (Form 3)File: Form 3_CA Certificate_Jun 2024.pdf17 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate_June 2024.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Jun 2024.pdf16 Jul 2024
Certificates of CA (Form 3)File: Form 3_CA Certificate_Mar 2024.pdf7 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architech Certificate_Mar 2024.pdf15 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer's Certificate_Mar 2024.pdf15 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form_2A_Qulaity Assurance Certificate_Mar 2024.pdf15 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Mar 2024.pdf15 Apr 2024
Certificates of CA (Form 3)File: Form 3_CA Certificate_Dec 2023.pdf5 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_CA Certificate_2022-23.pdf3 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_Dec 2023.pdf9 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Certificate_Dec 2023.pdf9 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Certificate_Dec 2023.pdf9 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory_Dec 2023.pdf9 Jan 2024
Certificates of CA (Form 3)File: Form 3_Sept 2023.pdf14 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_Sept 2023.pdf9 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate_Sept 2023.pdf9 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Quality Assurance_Sept 2023.pdf9 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventary_Sept 2023.pdf9 Oct 2023
Certificates of CA (Form 3)File: FORM-3_CA_June 2023.pdf13 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_June 2023.pdf12 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_ENGINEER CERTIFICATE_June 2023.pdf12 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Quality Assurance_June 2023.PDF12 Jul 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY_JUNE 2023.pdf12 Jul 2023
Details of encumbrances concerned to FinanceFile: Self Declaration_Legal.pdf9 Jun 2023
Details of encumbrances concerned to FinanceFile: Self Declaration_Finance.pdf9 Jun 2023
Details of encumbrances concerned to LegalFile: Self Declaration_Legal.pdf9 Jun 2023
Details of encumbrances concerned to LegalFile: Self Declaration_Finance.pdf9 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration About Seprate Bank Account.pdf9 Jun 2023
Other - FinanceFile: Self Declaration_Finance.pdf9 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_Quality Assurance_Mar 2021.PDF7 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_Quality Assurance_Mar 2022.PDF7 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.PDF7 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_2021-22.PDF7 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architect Certificate_Mar 2023.PDF31 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate_Mar 2023.PDF31 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 A_Quality Assurance_Mar 2023.pdf31 May 2023

How this compares with Thane

69%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 7 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SNEHAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BHAYANDER WEST7,600+ in Thane

2 kmSNEHAMCompleted 25Lapsed / revoked 15Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 76 registered projects within 2 km.

Builder: Paridhi Developers

Paridhi Developers has 1 registration on MahaRERA, including SNEHAM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SNEHAM is delayed beyond 19 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SNEHAM?

The registered promoter entity is Paridhi Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SNEHAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SNEHAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SNEHAM?

The professionals named in the filing: Architect: ASHISH H CHOGLE; Engineer: RAJESH B DUBEY; Engineer: SAHIL SIDDIQUE; Chartered Accountant: SANJAYKUMAR SHIVKUMAR SHARMA; Chartered Accountant: VAIBHAV HARISHCHANDRA PATIL; Chartered Accountant: VIVEK J THAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SNEHAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SNEHAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SNEHAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.