Home / Browse projects / Mumbai Suburban, Maharashtra / SKYLON SUBURBIA

Registered Litigation declared Residential / Group Housing project

SKYLON SUBURBIA

By SAI KRUPA DEVELOPERS

RG-MH-70664 · RERA P51800034335 · Last updated on MahaRERA portal: 10 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
5 of 11Construction stages donefurthest along: Podiums (if any), 90%
1 of 1Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

SKYLON SUBURBIA is a Residential / Group Housing project by SAI KRUPA DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800034335 on 4 Apr 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 0 of the 1 unit on this registration is recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSKYLON SUBURBIA
  • TypeResidential / Group Housing
  • Location
    • HEMUKALANI ROAD NO 4
    • KANDIVALI WEST
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800034335
  • ReraGenie IDRG-MH-70664

Builder

  • NameSAI KRUPA DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAFFS3096K1ZQ
  • PartnersHARISH RAVJI CHHEDA, KOMAL RAVJI CHHEDA, NIKUL HEMENDRA MEHTA, NEEPA NIKUL MEHTA
  • Other registrations5 more →
  • Completed4 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredApr 2022First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Apr 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2025)
  • Buildings1 building record
  • Documents filed86 files

Current status

0%0 of 1 units booked
91.7%Work done, per cost certificate

Figures as on 10 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SKYLON SUBURBIANA2423101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 90%.

SKYLON SUBURBIA: 70% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)90%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes0%
Street LightingYes40%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed172

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots172
Closed/Covered172

Land and ownership10

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,113 sq m
Land owned byThe promoter, with other names on the file
Named landowners10
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jul 2025
LandownerVillageDistrict
F.E.DinshawBorivaliMumbai Suburban
VIMLA RAMADHAR DWIVEDIBorivaliMumbai Suburban
RAMADHAR SHIVSAMPAT DWIVEDIBorivaliMumbai Suburban
SUNITA RAMADHAR DWIVEDIBorivaliMumbai Suburban
ANITA RAMADHAR DWIVEDIBorivaliMumbai Suburban
RAJESH RAMADHAR DWIVEDIBorivaliMumbai Suburban
REKHA RAMADHAR DWIVEDIBorivaliMumbai Suburban
OMPRAKASH RAMRICHPAL JHUNJHUNWALABorivaliMumbai Suburban
JAIKISHAN CHATANIBorivaliMumbai Suburban
SURESH CHATANIBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI18998.0
Proposed, not sanctioned18,998 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNew KrIshna Niwas Roshan Nagar Borivali W Mumbai-400092
Estimated costRs 134.00 cr
Cost incurredRs 122.87 cr
Work done91.7%
BuildingWingEstimatedIncurred
SKYLON SUBURBIANARs 102.00 crRs 80.02 cr
-NARs 32.00 crRs 42.86 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHRI SANJAY NEVE OF M/S. SANJAY NEVE & ASSOCIATES
ArchitectVINOD GAIKWAD
EngineerSHRI ABHIJIT PHATARPEKAR
Engineerharish chheda
Chartered AccountantSHRI NITIN MARU
Chartered Accountantekta navin shah
PartnerRole in project
SAI KRUPA DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA31122519171Dec 2025 → Dec 2026

Reason as filed by the promoter1. Delay in Statutory Clearances/Utility Approvals The redesigning and revised approvals of the plans had to be procured from SRA, and other government authorities which led to a delay in the construction. which impacted construction timelines despite our continuous follow-up. We would like to assure the Authority that despite these unavoidable delays we remain committed to the completion of the project with full compliance to RERA guidelines and quality standards. The updated revised completion timeline is being submitted accordingly. We request the Authority to kindly consider the above tech

Litigation declared2

CaseCourtStatus
279/2013HIGH COURTAD INTERIM ORDER PASSED IN PROMOTERS FAVOUR AND NOTICE OF MOTION AND SUIT PENDING FOR FINAL HEARING
286/2013HIGH COURTAD INTERIM ORDER PASSED IN PROMOTERS FAVOUR AND NOTICE OF MOTION AND SUIT PENDING FOR FINAL HEARING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600469vijendra kamlaprasad yadavSAI KRUPA DEVELOPERS26/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Feb 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: SUB FORM 1 31032026.pdf10 Jun 2026
Withdrawal Update Form 2File: SUB FORM 2 31032026.pdf10 Jun 2026
Withdrawal Update Form 3File: SKD Form 3 31032026_0001.pdf10 Jun 2026
Withdrawal Update Form 1File: SKD FORM 1.pdf25 May 2026
Withdrawal Update Form 2File: SUB Form 2.pdf25 May 2026
Withdrawal Update Form 3File: SKD P2_11zon.pdf25 May 2026
Withdrawal Update Form 1File: SKD FORM 1.pdf21 May 2026
Withdrawal Update Form 2File: Form 2 - ENGINEER CERTIFICATE .pdf21 May 2026
Withdrawal Update Form 3File: SKD P2_11zon.pdf21 May 2026
Withdrawal Update Form 1File: SKD FORM 1 Architect Certificate 30062025.pdf30 Dec 2025
Withdrawal Update Form 1File: SKD FORM 1 Architect Certificate 30092025.pdf30 Dec 2025
Withdrawal Update Form 2File: SKD P2 FORM 2 - Engineer Certi 30062025 (1).pdf30 Dec 2025
Withdrawal Update Form 2File: SKD P2 FORM 2 - Engineer Certi 30092025.pdf30 Dec 2025
Withdrawal Update Form 3File: SKD Form 3 30062025.pdf30 Dec 2025
Withdrawal Update Form 3File: SKD P2 FORM 3 30092025 FINAL.pdf30 Dec 2025
Form 2A (FY 2024-2025)File: SKD P2 Form 2A Engineer Certi New Format 31032025.pdf24 Dec 2025
Form 5 (FY 2022-2023)File: SKD P2 form 5 01042022 to 31032023.pdf24 Dec 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SKD P2 FORM 3.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SKD FORM 1 Architect Certificate 31032025.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SKD FORM 2 Engineer Certificate 31032025.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1Q2.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1Q3.pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3Q2.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM2Q2.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2Q3.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SKD P2 RERA Form1 30062024.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SKD P2 Form 2 30062024.pdf22 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SKD P2 Form 2A 15042024.pdf22 Jul 2024
Proforma of Agreement for saleFile: SUB draft agreement.pdf22 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf23 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SKD P2 FORM1 ARCHIRTECT CERTI 20042024.pdf23 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SKD P2 ENGINEER CERTI 20042024.pdf23 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA FORM 1 _20240227_0001.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CAF3.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CAF5.pdf27 Feb 2024
Declaration about Commencement CertificateFile: SUB CC 03102023.pdf21 Nov 2023
Building plan approvalFile: 1.pdf30 Mar 2022
Building plan approvalFile: 2.pdf30 Mar 2022
Building plan approvalFile: 3.pdf30 Mar 2022
Building plan approvalFile: 4.pdf30 Mar 2022
Building plan approvalFile: 5.pdf30 Mar 2022
Building plan approvalFile: 6.pdf30 Mar 2022
Building plan approvalFile: 7.pdf30 Mar 2022
Building plan approvalFile: 8.pdf30 Mar 2022
Building plan approvalFile: 9.pdf30 Mar 2022
Building plan approvalFile: 10.pdf30 Mar 2022
Building plan approvalFile: 11.pdf30 Mar 2022
Building plan approvalFile: 12.pdf30 Mar 2022
Building plan approvalFile: 13.pdf30 Mar 2022
Building plan approvalFile: 14.pdf30 Mar 2022
Building plan approvalFile: 15.pdf30 Mar 2022
Building plan approvalFile: 16.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 5.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 6.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 7.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 8.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 9.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 10.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 11.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 12.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 13.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 14.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 15.pdf30 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: 16.pdf30 Mar 2022
Copy of the legal title reportFile: SSB RERA Title.pdf24 Mar 2022
Copy of the legal title reportFile: SSB Annexure A.pdf24 Mar 2022
Copy of the legal title reportFile: SSB Annexure-B.pdf24 Mar 2022
Copy of the legal title reportFile: SSB Annexure-C.pdf24 Mar 2022
Details of encumbrancesFile: SSB 279.pdf24 Mar 2022
Details of encumbrancesFile: SSB 286.pdf24 Mar 2022
Layout approvalFile: Layout Approval.pdf24 Feb 2022
PAN CardFile: PAN.pdf24 Feb 2022
Details of encumbrancesFile: Encumbrances.pdf24 Feb 2022
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf24 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf24 Feb 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SKYLON SPACESHEMUKALANI CROSS ROAD NO 4 IRANIWADI KANDIVALI WEST MUMBAI 400067170CompletedDec 2019Dec 2019

How this compares with Mumbai Suburban

0%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SKYLON SUBURBIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANDIVALI WEST6,700+ in Mumbai Suburban

2 kmSKYLON SUBURBIACompleted 150Lapsed / revoked 101Other 145Dot size: filed unitsN

Filed coordinates, straight-line distance. 396 registered projects within 2 km.

Builder: SAI KRUPA DEVELOPERS

SAI KRUPA DEVELOPERS has 6 registrations on MahaRERA, including SAI KRUPA VALLEY- PHASE 1 and Nida Amisha Heights. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SKYLON SUBURBIA is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SKYLON SUBURBIA?

The registered promoter entity is SAI KRUPA DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAFFS3096K1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SKYLON SUBURBIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SKYLON SUBURBIA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SKYLON SUBURBIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SKYLON SUBURBIA?

The professionals named in the filing: Architect: SHRI SANJAY NEVE OF M/S. SANJAY NEVE & ASSOCIATES; Architect: VINOD GAIKWAD; Engineer: SHRI ABHIJIT PHATARPEKAR; Engineer: harish chheda; Chartered Accountant: SHRI NITIN MARU; Chartered Accountant: ekta navin shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SKYLON SUBURBIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SKYLON SUBURBIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SKYLON SUBURBIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.