Home / Browse projects / Mumbai Suburban, Maharashtra / Skyline viha Wing B
Skyline viha Wing B
RG-MH-11488 · RERA P51800002495 · Last updated on MahaRERA portal: 21 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 28 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 66 months
- 5 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Skyline viha Wing B is a Residential / Group Housing project by Ankit Overseas in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002495 on 1 Aug 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 66 months from the original filing. 48 of the 76 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameSkyline viha Wing B
- TypeResidential / Group Housing
- Location
- Kirol Road
- Vidyavihar West
- Kurla
- Mumbai Suburban
- 400086
- Pincode400086
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800002495
- ReraGenie IDRG-MH-11488
Builder
- NameAnkit Overseas
- Entity typePartnership
- GSTIN27ACYFS9765Q1ZF
- PartnersRuxmani Valjibhai Daisaria, Maulik Harshad Dave, Harsha Jatin Daisaria, Kavita Jaysinh Dave, JAYSINH AMBAPRASAD DAVE, SHILPIN KHYALILAL TATER, SKYLINE VISION PRIVATE LIMITED, JATIN VALJI DAISARIA, JATIN VALJI DAISARIA, DEVANG HARSHAD DAVE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Aug 2017
- Promised completion30 Jun 2024
- Revised completionRevised to 30 Jun 2024 (originally 31 Dec 2018)
- Buildings1 building record
- Documents filed91 files
Current status
Figures as on 21 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Skyline Viha WIng B | NA | 16 | 13 | 76 | 0 | 76 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 86%.
Skyline Viha WIng B: 83% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 86% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 86% |
| Sanitary Fittings within the flats / premises | 86% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 79% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 86% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 86% |
Progress on shared amenities15
As on 21 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed76
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Manoj Daisaria |
| Engineer | Satish Duphalia |
| Chartered Accountant | Hay And Associate LLP |
| Chartered Accountant | Fofalia and Associate |
| Chartered Accountant | Hitesh Dedhia and company |
| Partner | Role in project |
|---|---|
| Ankit Overseas | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterIn absence of NOC from Naval Authority which was not a original condition when plans for 11th floors were approved and full C.C. was granted in respect thereof. We are unable to obtain occupation certificate from MCGM inspite of work being completed upto stilt plus 11 upper floors. Upon receipt of part occupation certificate (stilt plus 11 floors ) and upon further CC of remaining two floors, we will be able to commence the balance work of 12th and 13th floor hence require some more time for completing the Project.
Reason as filed by the promoterThe Promoter has completed the project as per the approved plan and application for part Occupation Certificate was also submitted to MCGM. However, the same is withheld by MCGM on account of NOC from Naval Authority, which was not the condition when the plan was passed. The delay is on account of NOC from Naval Authority, which was never the condition of MCGM while passing the Plan. The Promoter also submitted Completion Certificate of its Architect - Form -4 as prescribe under the RERA Act -2016 on the website of said Authority. In such circumstances we request to grant extension of one year
Reason as filed by the promoterWe are hereby applying for the Extension of our Project registered with the Regulatory Authority vide Project Certificate bearing No. P51800002495 which will be expire on 31.12.2018. We are annexing the following document for the kind perusal of Hon’ble Authority: a) Application for Extension of Time (Form- E) b) Rejection of NOC from Naval Authority c) Commencement Certificate issued by MCGM. We are humbly submits that the delay in completion of project was for the circumstances which is beyond our control. It is therefore prayed that the extension of registration of the project be granted fo
Reason as filed by the promoterWe submits that the building has been completed as per the approved permission, and the application for a part occupancy certificate is pending with MCGM. The Completion Certificated Form- 4 dated 13th July 2020 issued by the Architect in respect of said building has also been uploaded. In the absence of a naval noc, which was not a condition precedent, the MCGM is not issuing the part occupation certificate. The various builders/developers affected by the Naval Circular dated 11th May 2011 in the vicinity of Vidyavihar/Ghatkopar (Mumbai, Maharashtra) have challenged the said circular before t
Reason as filed by the promoterWe have registered the said Project and completed the said building as per the approved permission and application for part Occupation Certificate, is pending with MCGM and now the MCGM is not issuing the Occupation Certificate in the absence of NOC from Naval authority which was never a condition when the commencement certificate in respect of said project was issue. We have submitted the Architect Completion Certificated Form- 4 dated 13th July 2020 in respect of said Building to RERE Authority and have complied with all the obligation. Due to this act of force measure, which is beyond our c
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000078871 | bhaveshwarcomplex premises co operative society ltd. | Ankit overseas | 12/04/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 18 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed91
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2File: Form 2 Engi Certificate 30 June 2024.pdf | 21 May 2026 |
| Form 3File: 19 March 2025 CA Form 3.pdf | 21 May 2026 |
| Form 1File: ARCHITECT CERTIFICATE.PDF | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD.PDF | 21 May 2026 |
| Declaration in FORM BFile: FORM B AFFIDAVIT CUM DECLARATION.PDF | 12 Jun 2025 |
| Certificates of CA (Form 3)File: CA-CERTIFICATE-MARCH 25.pdf | 12 Jun 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEERS CERTIFICATE.PDF | 12 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD , BOOKED INVENTORY.PDF | 12 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD-PART-1.pdf | 12 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD PART 2.PDF | 12 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD-PART 3.pdf | 12 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD-PART-4.pdf | 12 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD-PART5.pdf | 12 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD-BOOKED-SUMMARY.pdf | 12 Jun 2025 |
| Other - TechnicalFile: PERT CHART.PDF | 12 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2 ENGINEERS CERTIFICATE.PDF | 12 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf | 25 Mar 2025 |
| Declaration in FORM BFile: FORM B AFFIDAVIT CUM DECLARATION.PDF | 25 Nov 2024 |
| Certificates of CA (Form 3)File: C A Certi Form 3.pdf | 25 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.PDF | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY CERT- FORM 2A.PDF | 20 Jul 2024 |
| Certificates of CA (Form 5)File: CA CERT FORM5.PDF | 20 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE.PDF | 16 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEERS CERTIFICATE.PDF | 16 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM -2A QUALITY ASSURANCE CERTIFICATE.PDF | 16 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 CA.PDF | 16 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.PDF | 25 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5-CA.pdf | 25 Oct 2023 |
| Declaration in FORM BFile: RERA-FORMB.PDF | 19 Oct 2023 |
| OtherFile: RERA-DECLARATIOM-UMD.PDF | 19 Oct 2023 |
| Declaration about Commencement CertificateFile: format d-cc declaration.PDF | 12 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Certificate Viha 21-22.PDF | 12 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: quality certificate 2021.PDF | 17 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: MH-RERA.PDF | 17 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality certificate 2021.PDF | 12 Oct 2022 |
| Certificates of CA (Form 5)File: Ankit Ove Anual Report.pdf | 19 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Ankit Ove Anual Report.pdf | 19 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 CA 18-19.pdf | 11 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 CA 19-20.pdf | 11 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 CA 20-21.pdf | 11 Apr 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form-4.pdf | 20 Jul 2020 |
| Engineers Certificate on Quality Assurance (Form 2A)File: quality certificate.pdf | 21 Oct 2019 |
| Certificates of CA (Form 5)File: Form- 5 Viha B Wing.PDF | 25 Sep 2019 |
| OtherFile: No Dues Certificate from fed bank.pdf | 23 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Acknowldgement0002.PDF | 27 May 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Acknowldgement0003.PDF | 27 May 2019 |
| OtherFile: Letter.PDF | 16 Mar 2019 |
| OtherFile: PART OC - APPLICATION.pdf | 14 Mar 2019 |
| Certificates of CA (Form 5)File: FORM 5- AO.PDF | 15 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: rera architect cert-07082018.PDF | 7 Aug 2018 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Name Reservation Certificate Viha.pdf | 30 Mar 2018 |
| Proforma of Allotment letterFile: allotment- VIHA-rera upload-19112017.pdf | 19 Nov 2017 |
| Proforma of Allotment letterFile: Sale_Agreement_final__REAR_1_BHK_EWS_CLAUSE.pdf | 7 Nov 2017 |
| Proforma of Allotment letterFile: viha_agreement_2bhk.pdf | 29 Oct 2017 |
| Proforma of Allotment letterFile: viha_agreement_1bhk.pdf | 29 Oct 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Skyline Viha Arch Certi for RERA_opt.pdf | 23 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate_opt.pdf | 23 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate Viha Wing B.PDF | 22 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate Viha.PDF | 20 Jul 2017 |
| Details of encumbrancesFile: Encumbrance Certificate Viha.PDF | 20 Jul 2017 |
| Declaration in FORM BFile: Form B Declaration Viha.PDF | 20 Jul 2017 |
| Certificates of CA (Form 3)File: CA CERIFICATE-RERA skyline viha wing B.pdf | 20 Jul 2017 |
| Proforma of Allotment letterFile: Allotment Letter .pdf | 20 Jul 2017 |
| Proforma of Allotment letterFile: Agreement for Sale .pdf | 20 Jul 2017 |
| Building plan approvalFile: IOD 11-05-06.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 2.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 3.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 4.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 5.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 6.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 7.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 8.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 9.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 10.pdf | 18 Jul 2017 |
| Building plan approvalFile: Sanctioned Plan 11.pdf | 18 Jul 2017 |
| Layout approvalFile: Sanctioned Plan 2.pdf | 18 Jul 2017 |
| PAN CardFile: SRLLP Pan Card.pdf | 18 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Sanctioned Plan 2.pdf | 18 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 11-05-06.pdf | 18 Jul 2017 |
| Building Plan Approval (IOD)File: Sanctioned Plan 2.pdf | 18 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 91 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Skyline viha Wing B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vidyavihar West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 370 registered projects within 2 km.
Atul Life Phase I
ATUL PROJECTS INDIA PVT LTD
SERENE CITY
SANGHVI BUILDTECH LLP
Neelyog Regent
Ratan Builders
Imperial Indrapuram B & C
Imperial Global Infra
HERITAGE AHURA RESIDENCY
KERSI JAMSHED RANDERIA
O AND S BUSINESS SUITES
SUCHITA ORANGE HDM PROJECT
See every Mumbai Suburban project, with the district possession charts
Builder: Ankit Overseas
Ankit Overseas has 1 registration on MahaRERA, including Skyline viha Wing B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Skyline viha Wing B shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Skyline viha Wing B is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Skyline viha Wing B?
The registered promoter entity is Ankit Overseas, a partnership as per the filing. Its GSTIN 27ACYFS9765Q1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Skyline viha Wing B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Skyline viha Wing B?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Skyline viha Wing B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Skyline viha Wing B?
The professionals named in the filing: Architect: Manoj Daisaria; Engineer: Satish Duphalia; Chartered Accountant: Hay And Associate LLP; Chartered Accountant: Fofalia and Associate; Chartered Accountant: Hitesh Dedhia and company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Skyline viha Wing B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback