Skyi Star City Phase III

By Pate Future Constructions LLP

RG-MH-21484 · RERA P52100029474 · Last updated on MahaRERA portal: 23 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Litigation declared, 1 case
  • 3 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
10 of 11Construction stages donefurthest along: Installation of Lifts, 50%
0 of 64Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

Skyi Star City Phase III is a Residential / Group Housing project by Pate Future Constructions LLP in Pune, Maharashtra, registered with MahaRERA as P52100029474 on 4 Jun 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 64 of the 64 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSkyi Star City Phase III
  • TypeResidential / Group Housing
  • Location
    • Kirkatwadi
    • Haveli
    • Pune
    • 411024
  • Pincode411024
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100029474
  • ReraGenie IDRG-MH-21484

Builder

  • NamePate Future Constructions LLP
  • Entity typePartnership
  • GSTIN27AAQFP7738N1Z7
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersRakeshkumar Agarwal, Ramlakhan Shukla, Pramod Wani, Lalit Ajgaonkar, Amit Anil Jagtap
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live4 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredJun 2021First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Jun 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed88 files

Current status

100%64 of 64 units booked

Figures as on 23 Apr 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower INA9864064

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 50%.

Tower I: 95% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities16

As on 23 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Labour camp and other infraYes100%

Parking filed70

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots70
Closed/Covered35
Open Space35

Land and ownership26

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,839 sq m
Land owned byThe promoter, with other names on the file
Named landowners26
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Aug 2025
LandownerVillageDistrict
Ramchandra alias Chandrakant HagawaneKIRKATWADIPune
Balasaheb HagawaneKIRKATWADIPune
Raosaheb HagawaneKIRKATWADIPune
Shekhar HagawaneKIRKATWADIPune
Shakuntala Ramchandra HagawaneKIRKATWADIPune
Ganesh Ramchandra HagawaneKIRKATWADIPune
Shubhangi Ganesh HagawaneKIRKATWADIPune
Mangesh Ramchandra HagawaneKIRKATWADIPune
Deepali Mangesh HagawaneKIRKATWADIPune
Umesh Ramchandra HagawaneKIRKATWADIPune
Rupali Umesh HagawaneKIRKATWADIPune
Yuvraj Raosaheb HagawaneKIRKATWADIPune
Sarika Yuvraj HagawaneKIRKATWADIPune
Sachin Raosaheb HagawaneKIRKATWADIPune
Manasi Sachin HagawaneKIRKATWADIPune
Vaishali Raosaheb HagawaneKIRKATWADIPune
Meena Balasaheb HagawaneKIRKATWADIPune
Amit Balasaheb HagawaneKIRKATWADIPune
Komal Amit HagawaneKIRKATWADIPune
Reshma Balasaheb HagawaneKIRKATWADIPune
Mayuri Balasaheb HagawaneKIRKATWADIPune
Shobha Devidas HagawaneKIRKATWADIPune
Poonam Shekhar HagawaneKIRKATWADIPune
Nileema Devidas HagawaneKIRKATWADIPune
Ashabai Shivaji DhawadeKIRKATWADIPune
Sagunabai Baburao MurkuteKIRKATWADIPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI5497.21
Proposed, not sanctioned4,497 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhandarkar Road Pune

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDhananjay S. Deshmukh
EngineerSANDIP RANGDAL &ASSO. STRUCTURAL CONSULTANT
Chartered AccountantSPCM & Associates
Chartered AccountantAS Jinturkar & Co.
PartnerRole in project
Pate Future Constructions LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025183Dec 2024 → Dec 2025

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, and coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work As of now, 70% of the project is completed. We are closely monitoring progress and taking all necessary steps to ensure timely completion. We kindly request an extension until 31-12-2025 to complete the project and fulfil all regulatory requirements.

Litigation declared1

CaseCourtStatus
1752/2014/2014Pune Civil Sr Division CourtAwating Summons

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000258848Skyi Property Ventures LLPPankaj Bhagwat Misal16/05/2023
CC005000000238588AMOL ROHIDAS LOKAREM/S SKYI PROPERTY VENTURES LLP03/04/2023
CC12602676Skyi Property Ventures LLPPravin Pandit Bansode08/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Skyi Star City Phase III.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SPVLLP-PH III-Building I-Form-1.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Skyi Star City Phase III.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SPVLLP-PH III-Building I-Form-2.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Skyi Star City Phase III_compressed.pdf29 Jan 2025
Declaration about Commencement CertificateFile: Phase III-Tower I.pdf23 Jan 2025
Layout approvalFile: 1-36-Layout.pdf21 Jan 2025
Building plan approvalFile: 12-36-Bldg I-Floor plan.pdf21 Jan 2025
Building plan approvalFile: 11-36-Bldg I-Floor plan.pdf21 Jan 2025
Copy of Layout Approval (in case of layout)File: 1-36-Layout.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-building I.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Skyi Star City Phase III.pdf21 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Building I.pdf21 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Letter.pdf21 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 12-36-Bldg I-Floor plan.pdf21 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 11-36-Bldg I-Floor plan.pdf21 Jan 2025
Disclosure of sold/ booked inventoryFile: Star city III-I.pdf21 Jan 2025
Declaration in FORM BFile: FORM -B.pdf25 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf25 Nov 2024
CERSAI detailsFile: CERSAI_Star City.pdf15 Nov 2024
Disclosure of sold/ booked inventoryFile: Star City Phase III.pdf5 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Bldg I-PH III.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Skyi Star City Phase 3.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-PH III-Build I.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: From 5-SPVLLP-Star City Phase III.pdf8 Oct 2024
Disclosure of sold/ booked inventoryFile: Star City-Phase III.pdf31 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Arch Certificate-PH III Build I.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Engg Certificate- PH III Build I.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Skyi Star City Phase lll.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: I-III.pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Building I Form 1 Arch Certifcate.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Star City Ph III form 2 Building I.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Skyi Star City Phase III.pdf19 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Letter.pdf17 Apr 2024
Declaration about Commencement CertificateFile: ST-PHASE III-CC dec.pdf23 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ST-PHASE III-Quality-21-22.pdf23 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ST-PHASE III-Quality-22-23.pdf23 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: ST-PHASE III-Seprate bank.pdf23 Jan 2024
Details of encumbrances concerned to FinanceFile: Mortgage Index.pdf19 Jan 2024
Details of encumbrances concerned to LegalFile: Mortgage Index.pdf19 Jan 2024
CERSAI detailsFile: Mortgage Index.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: Star City-Phase III-I.pdf19 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Other organisation.pdf19 Jan 2024
Proforma of Agreement for saleFile: ATS Draft.pdf19 Jan 2024
Deviation Report with respect to Allotment letterFile: Allotment Letter.pdf19 Jan 2024
Deviation Report with respect to model copy of AgreementFile: ATS Draft.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BULD-I-Form 1-STAR CITY.pdf12 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3-SPVLLP BUILD I FORM-1 Arch Certifcate 311223.pdf12 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3_SPVLLP-SKYI STAR CITY PH III BUILD I FORM 2 Engg Certificate.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BUILD-I-Form 2-STAR CITY.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3_SPVLLP-SKYI STAR CITY PH III BUILD I FORM 2 Engg Certificate.pdf12 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: BUILD-I-FORM-3-STAR CITY.pdf12 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Ph III SPVLLP.pdf19 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3_Form 2 Engg Certificate Ph III SPVLLP.pdf19 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SkyiStar City Phase III.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Star City-PH III-Build I.pdf16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PH-III Building I Form 1-Arch Certificate.pdf12 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH-III Building I Form 2-Engg Certificate.pdf12 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Skyi star City Phase III.pdf12 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Arch- Certificate-SCT PH III.pdf17 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engg Certificate-SCT PH III.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Star City-PH1-Form5-Build-I.pdf24 Jan 2023
Layout approvalFile: LAYOUT.pdf28 Dec 2022
Building plan approvalFile: I-Floor Plan.pdf28 Dec 2022
Building plan approvalFile: I-Floor Plan1.pdf28 Dec 2022
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf28 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: I-Floor Plan.pdf28 Dec 2022
Building Plan Approval / NA Order for plotted developmentFile: I-Floor Plan1.pdf28 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Star City-PH1-Form5-Build-I.pdf17 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH Star City Ph III.pdf12 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH-STAR CITY -PH-III.pdf12 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng-Star City PH-III.pdf12 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG-Star City Ph III.pdf12 Nov 2022
Proforma of Allotment letterFile: Agreement Draft.pdf23 Apr 2022
OtherFile: Change of Name Certificate.pdf20 Dec 2021
Layout approvalFile: 1-42_Building Layout.pdf2 Jun 2021
Building plan approvalFile: 31-42_Tower I-J.pdf2 Jun 2021
Building plan approvalFile: 32-42_Tower I-J.pdf2 Jun 2021
Copy of the legal title reportFile: Revised Title Report.pdf2 Jun 2021
Copy of Layout Approval (in case of layout)File: 1-42_Building Layout.pdf2 Jun 2021

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Skyi Star City Phase III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kirkatwadi13,700+ in Pune

2 kmSkyi Star City Phase IIICompleted 24Lapsed / revoked 25Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 86 registered projects within 2 km.

Builder: Pate Future Constructions LLP

Pate Future Constructions LLP has 5 registrations on MahaRERA, including LIFE MAXIMA PHASE 1 and LIFE MAXIMA PHASE 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Skyi Star City Phase III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Skyi Star City Phase III is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Skyi Star City Phase III?

The registered promoter entity is Pate Future Constructions LLP, a partnership as per the filing. Its GSTIN 27AAQFP7738N1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Skyi Star City Phase III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Skyi Star City Phase III?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Skyi Star City Phase III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Skyi Star City Phase III?

The professionals named in the filing: Architect: Dhananjay S. Deshmukh; Engineer: SANDIP RANGDAL &ASSO. STRUCTURAL CONSULTANT; Chartered Accountant: SPCM & Associates; Chartered Accountant: AS Jinturkar & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Skyi Star City Phase III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Skyi Star City Phase III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Skyi Star City Phase III to a free account