ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Skyi Park Phase I

Registered Litigation declared Residential / Group Housing project

Skyi Park Phase I

By Enerrgia Skyi Ventures

RG-MH-31346 · RERA P52100079680 · Last updated on MahaRERA portal: 24 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 2 complaints at MahaRERA

Clear

  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2029Possession promisedno revision filed
2 of 11Construction stages donefurthest along: Stilt Floor, 10%
33 of 88Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

Skyi Park Phase I is a Residential / Group Housing project by Enerrgia Skyi Ventures in Pune, Maharashtra, registered with MahaRERA as P52100079680 on 20 Mar 2025. Possession is promised by 31 May 2029. 55 of the 88 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSkyi Park Phase I
  • TypeResidential / Group Housing
  • Location
    • Gat No 294 (P)
    • at Bhukum
    • Bhukum
    • Pune
    • Bhukum
    • Mulshi
    • Pune
    • 412115
  • Pincode412115
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100079680
  • ReraGenie IDRG-MH-31346

Builder

  • NameEnerrgia Skyi Ventures
  • Entity typePartnership
  • PartnersSushant Mohan Jadhav, Amit Anil Jagtap
  • Other registrations5 more →
  • Completed2 of 6
  • Declared earlier projects2 →

Key dates

this monthRegisteredMar 2025PromisedMay 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Mar 2025
  • Promised completion31 May 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed69 files

Current status

62%55 of 88 units booked
11.6%Work done, per cost certificate

Figures as on 24 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building - ANA171588088

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 10%.

Building - A: 19% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor10%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed118

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots118
Closed/Covered30
Open Space88

Land and ownership32

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,404 sq m
Land owned byThe promoter, with other names on the file
Named landowners32
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Jun 2025
LandownerVillageDistrict
Varsha Santosh SatputeBhugaonPune
M/s. K M RealtyBhugaonPune
M/s. Skyline RealtyBhugaonPune
Sudha Arun PatilBhugaonPune
Suman Tukaram ChoudhariBhugaonPune
Nitin Tukaram ChoudhariBhugaonPune
Dattatray Shankar ChoudhariBhugaonPune
Sunanda Dattatray ChoudhariBhugaonPune
Vijay Dattatray ChoudhariBhugaonPune
Ajay Dattatray ChoudhariBhugaonPune
Sopan Shankar ChoudhariBhugaonPune
Asha Sopan ChoudhariBhugaonPune
Atul Sopan ChoudhariBhugaonPune
Abhijit Sopan ChoudhariBhugaonPune
Changdev Shankar ChoudhariBhugaonPune
Manda Changdev ChoudhariBhugaonPune
Akash Changdev ChoudhariBhugaonPune
Balu alias Balasaheb ChoudhariBhugaonPune
Suvarna Balasaheb ChoudhariBhugaonPune
Prathmesh Balasaheb ChoudhariBhugaonPune
Hrishikesh Balasaheb ChoudhariBhugaonPune
Kunda Dnyanoba ChoudhariBhugaonPune
Ganesh Dnyanoba ChoudhariBhugaonPune
Megha Ganesh ChoudhariBhugaonPune
Vedant Ganesh ChoudhariBhugaonPune
Vishal Dnyanoba ChoudhariBhugaonPune
Namdev Tukaram MazireBhugaonPune
Nivrutti Tukaram MazireBhugaonPune
Mahadev Tukaram MazireBhugaonPune
Vijay Pandurang MazireBhugaonPune
Pallavi Vikram WaniBhugaonPune
Aatish Jayprakash SalunkeBhugaonPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI8077.44
Proposed, not sanctioned7,540 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAUKIK APARTMENT SGROUND FLOOR,PLOT NO 3, CTS NO 870 BHANDARKAR ROAD PUNE MAHARASHTRA 411004
Estimated costRs 29.64 cr
Cost incurredRs 3.44 cr
Work done11.59%
BuildingWingEstimatedIncurred
Building - ANARs 27.46 crRs 1.35 cr
-NARs 2.18 crRs 2.09 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDhananjay S. Deshmukh
ArchitectPGS and Associates
EngineerSandip Rangdal & Asso Structural Consultant
Chartered AccountantA S Jinturkar & Co
Chartered AccountantSPCM & Associates
PartnerRole in project
Enerrgia Skyi Ventures-

Litigation declared1

CaseCourtStatus
1757/2021Civil Court Senior DivisionWS and Say

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
SM12500254Ram GawaliEnerrgia Skyi Ventures29/12/2025
SM12600362Ram GawaliEnerrgia Skyi Ventures26/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 May 2029

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1-Skyi Park Phase I-A-31-03-26.pdf24 Jun 2026
Withdrawal Update Form 2File: Form 2-Skyi Park Phase I-A-31-03-26.pdf24 Jun 2026
Withdrawal Update Form 3File: Form 3-Skyi Park Phase I-A-31-03-26.pdf24 Jun 2026
Withdrawal Update Form 1File: Form 1 Skyi Park Phase I A.pdf14 Feb 2026
Withdrawal Update Form 2File: Form 2 Skyi Park Phase I A.pdf14 Feb 2026
Withdrawal Update Form 3File: Form 3 Skyi Park Phase I A.pdf14 Feb 2026
Withdrawal Update Form 1File: Form 1-Skyi Park Phase I.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2-Skyi Park Phase I-A.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3-Skyi Park Phase I-A.pdf13 Feb 2026
Withdrawal Update Form 1File: Form 1-Skyi Park Phase I.pdf26 Dec 2025
Withdrawal Update Form 2File: Form 2-Skyi Park Phase I-A.pdf26 Dec 2025
Withdrawal Update Form 3File: Form 3-Skyi Park Phase I-A.pdf26 Dec 2025
Form 5 (FY 2024-2025)File: Form 5-Skyi Park Phase I-FY 2024-25.pdf26 Dec 2025
Disclosure of sold/ booked inventoryFile: Skyi Park Phase I.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Skyi Park Phase I.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Skyi Park Phase I.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Skyi Park Phase I.pdf21 Apr 2025
Other - LegalFile: Declaration for clarification on Varsha.pdf13 Mar 2025
Other - LegalFile: Will-2021_11zon.pdf13 Mar 2025
Layout approvalFile: 2-12-Layout.pdf6 Mar 2025
Building plan approvalFile: 1-12-Amalgamation.pdf6 Mar 2025
Building plan approvalFile: 2-12-Layout.pdf6 Mar 2025
Building plan approvalFile: 3-12-Parking.pdf6 Mar 2025
Building plan approvalFile: 4-12-TowerA-Floor Plan.pdf6 Mar 2025
Building plan approvalFile: 5-12-Tower A-Floor Plan.pdf6 Mar 2025
Building plan approvalFile: 6-12-Tower A-Floor Plan.pdf6 Mar 2025
Building plan approvalFile: 7-12-Tower A-Section.pdf6 Mar 2025
PAN CardFile: PAN_ESV.PDF6 Mar 2025
Copy of the legal title reportFile: 1 Copy of the legal title report (1).pdf6 Mar 2025
Details of encumbrances concerned to FinanceFile: 2 a Details of encumbrances concerned to Finance.pdf6 Mar 2025
Details of encumbrances concerned to FinanceFile: 1 a Details of encumbrances concerned to Finance.pdf6 Mar 2025
Copy of Layout Approval (in case of layout)File: 2-12-Layout.pdf6 Mar 2025
Proforma of Allotment letterFile: AL_Skyi Park Phase I_Ms Enerrgia Skyi Ventures 05022025.pdf6 Mar 2025
Declaration in FORM BFile: Form B - Promoter.pdf6 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Skyi Park_Form 3-Revised.pdf6 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Letter-27-02-2025.pdf6 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC Verification Mail-Skyi Park Phase I.pdf6 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 1-12-Amalgamation.pdf6 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 7-12-Tower A-Section.pdf6 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 6-12-Tower A-Floor Plan.pdf6 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 5-12-Tower A-Floor Plan.pdf6 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 4-12-TowerA-Floor Plan.pdf6 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 3-12-Parking.pdf6 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2-12-Layout.pdf6 Mar 2025
Declaration about Commencement CertificateFile: Format D - Declaration of Commencement Certificate.pdf6 Mar 2025
CERSAI detailsFile: Declaration of Cersai.pdf6 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - All RERA Designated Bank Accounts.pdf6 Mar 2025
Deviation Report with respect to Allotment letterFile: Deviation Report-Allotment Letter.pdf6 Mar 2025
Details of encumbrances concerned to LegalFile: 1 a Details of encumbrances concerned to Finance.pdf6 Mar 2025
Details of encumbrances concerned to LegalFile: 2 a Details of encumbrances concerned to Finance.pdf6 Mar 2025
Other - FinanceFile: POA-Pallavi Wani-ESV-28888-23-12-2024.pdf6 Mar 2025
Other - FinanceFile: POA-Tukaram Choudhari-ESV-289-23-01-2014.pdf6 Mar 2025
Other - FinanceFile: POA-Sudha Patil- ESV-28854-23-12-2024.pdf6 Mar 2025
Other - FinanceFile: POA-Skyline Realty-ESV-29462-30-12-2024.pdf6 Mar 2025
Other - FinanceFile: POA-Namdev Mazire-ESV-11808-5-05-2024-131to155.pdf6 Mar 2025
Other - FinanceFile: POA-Namdev Mazire-ESV-11808-5-05-2024-91to130.pdf6 Mar 2025
Other - FinanceFile: POA-Namdev Mazire-ESV-11808-5-05-2024-46to90.pdf6 Mar 2025
Other - FinanceFile: POA-Namdev Mazire-ESV-11808-5-05-2024-1to45.pdf6 Mar 2025
Other - FinanceFile: POA-KM Realty-ESV-28898-23-12-2024.pdf6 Mar 2025
Other - FinanceFile: POA-Aatish Salunke-ESV-28873-23-12-2024.pdf6 Mar 2025
Other - FinanceFile: Revised Declaration - Exemption of bank account for landowner.pdf6 Mar 2025
Other - TechnicalFile: Annexure A - Order No 50.pdf6 Mar 2025
Other - TechnicalFile: Plot Area Declaration.pdf6 Mar 2025
Other - TechnicalFile: CC Verification Mail-Skyi Park Phase I.pdf6 Mar 2025
Deviation Report with respect to model copy of AgreementFile: Deviation Report-Agreement for sale.pdf6 Mar 2025
Proforma of Agreement for saleFile: AFS_Skyi Park Phase I_Ms Enerrgia Skyi Ventures 05022025.pdf6 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Disclosure of Interest in other organisations.pdf6 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B - Declaration from the bank.pdf6 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured and unsecured finance availed for the project.pdf6 Mar 2025

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Skyi Star Towers Phase IIGat No 229 and others Village Bhukum Taluka Mulshi Dist Pune256CompletedFeb 2021Jan 2021
Skyi Star Towers Phase IGat No 229 and others Village Bhukum Taluka Mulshi Pune233CompletedAug 2019Jan 2019

How this compares with Pune

62%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Skyi Park Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhukum, Pune13,700+ in Pune

2 kmSkyi Park Phase ICompleted 11Lapsed / revoked 5Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: Enerrgia Skyi Ventures

Enerrgia Skyi Ventures has 6 registrations on MahaRERA, including Skyi Star Towers Phase I and Skyi Star Towers Phase II. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Skyi Park Phase I is delayed beyond 31 May 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Skyi Park Phase I?

The registered promoter entity is Enerrgia Skyi Ventures, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Skyi Park Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Skyi Park Phase I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Skyi Park Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Skyi Park Phase I?

The professionals named in the filing: Architect: Dhananjay S. Deshmukh; Architect: PGS and Associates; Engineer: Sandip Rangdal & Asso Structural Consultant; Chartered Accountant: A S Jinturkar & Co; Chartered Accountant: SPCM & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Skyi Park Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Skyi Park Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Skyi Park Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.