Registered No litigation declared Residential / Group Housing project

Skyi Manas Lake Phase IX

By Enerrgia Skyi Ventures LLP

RG-MH-23546 · RERA P52100078857 · Last updated on MahaRERA portal: 14 Feb 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 70%
2 of 79Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

Skyi Manas Lake Phase IX is a Residential / Group Housing project by Enerrgia Skyi Ventures LLP in Pune, Maharashtra, registered with MahaRERA as P52100078857 on 15 Jan 2025. Possession is promised by 31 Dec 2027. 77 of the 79 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSkyi Manas Lake Phase IX
  • TypeResidential / Group Housing
  • Location
    • Gat No 215 (P)
    • 217
    • 218
    • 219
    • 220
    • 221
    • 222
    • 223
    • 224 (P)
    • 293
    • 294 (P)
    • Bhukum
    • Pune
    • Bhukum
    • Mulshi
    • 412115
  • Pincode412115
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100078857
  • ReraGenie IDRG-MH-23546

Builder

  • NameEnerrgia Skyi Ventures LLP
  • Entity typePartnership
  • PartnersSushant Mohan Jadhav, Amit Anil Jagtap
  • Other registrations8 more →
  • Completed5 of 9
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredJan 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jan 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed82 files

Current status

97%77 of 79 units booked
59.3%Work done, per cost certificate

Figures as on 14 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building - 12NA121079079

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.

Building - 12: 47% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises47%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes5%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed157

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots157
Closed/Covered39
Open Space118

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,118 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Aug 2025
LandownerVillageDistrict
Sandip Shridhar WalimbeBhugaonPune
Milind Laxman KulkarniBhugaonPune
M/s. Enerrgia Skyi VenturesBhugaonPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI7548.82
Proposed, not sanctioned5,049 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLOHIA JAIN AVENUE 1ST FLOOR SHOWROOM SR NO 150 PAUD ROAD CHANDANI CHOWK PUNE MAHARASHTRA 411038
Estimated costRs 21.76 cr
Cost incurredRs 12.90 cr
Work done59.27%
BuildingWingEstimatedIncurred
Building - 12NARs 18.51 crRs 10.25 cr
-NARs 3.25 crRs 2.65 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA.B.S. Architects & Associates
ArchitectDhananjay S. Deshmukh
ArchitectDhananjay Deshmukh
EngineerSandip Rangdal & Associates
Chartered AccountantA S Jinturkar & Co
PartnerRole in project
Enerrgia Skyi Ventures LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jan 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Manas Lake Phase IX Bldg 12.pdf14 Feb 2026
Form 2File: Form 2 Manas Lake Phase IX Bldg 12.pdf14 Feb 2026
Form 3File: Form 3 Manas Lake Phase IX Bldg 12.pdf14 Feb 2026
Disclosure of Sold and Booked InventoryFile: Skyi Manas Lake Phase IX SOLD UNSOLD.pdf14 Feb 2026
Withdrawal Update Form 1File: Form 1-Manas Lake Phase IX-Bldg 12.pdf13 Feb 2026
Withdrawal Update Form 1File: Form 1 Manas Lake Phase IX Bldg 12.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2 Manas Lake Phase IX Bldg 12.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2 Manas Lake Phase IX Bldg 12.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3 Manas Lake Phase IX Bldg 12.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3 Manas Lake Phase IX Bldg 12.pdf13 Feb 2026
Form 5 (FY 2024-2025)File: From 5-Manas Lake Phase IX-FY 2024-25.pdf6 Dec 2025
Withdrawal Update Form 1File: Form 1-Manas Lake Phase IX-Bldg 12.pdf18 Aug 2025
Withdrawal Update Form 2File: Form 2-Manas Lake Phase IX-Bldg 12.pdf18 Aug 2025
Withdrawal Update Form 3File: Form 3 - Mar 2025.pdf18 Aug 2025
Form 1File: Form 1-Manas Lake Phase IX-Bldg 12.pdf20 Jul 2025
Form 2File: Form 2-Manas Lake Phase IX-Bldg 12.pdf20 Jul 2025
Form 3File: Form 3-Manas Lake Phase IX-Bldg 12.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: 12.pdf20 Jul 2025
Disclosure of sold/ booked inventoryFile: Skyi Manas Lake Phase IX.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Manas Lake Phase IX-Bldg 12.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Manas Lake Phase IX-Bldg 12.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Manas Lake Phase IX-Bldg 12.pdf21 Apr 2025
Proforma of Agreement for saleFile: Agreement Draft-ML-12.pdf22 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Manas Lake Phase IX-Bldg 12.pdf12 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Manas Lake Phase IX-Bldg 12.pdf12 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Manas Lake Phase IX-Bldg 12.pdf12 Mar 2025
Layout approvalFile: 1-17 - Layout-1_11zon (1)_11zon.pdf8 Jan 2025
Copy of Layout Approval (in case of layout)File: 1-17 - Layout-1_11zon (1)_11zon.pdf8 Jan 2025
Other - LegalFile: 10-294_Narayan Mazire_Sigma_6323-2008.pdf8 Jan 2025
Other - LegalFile: 1-218_Sandip Ingawale_Sigma_6653_2007.pdf8 Jan 2025
Other - LegalFile: 2-218_Sigma_Pandharinath Mazire_4404_2008.pdf8 Jan 2025
Other - LegalFile: 3-219-Avinash Batra and others_Sigma_7145_2008.pdf8 Jan 2025
Other - LegalFile: 4-221_Dattatrey Kadam_Sigma_1928_2008.pdf8 Jan 2025
Other - LegalFile: 5-222_Shrikant Mahale_ESVLLP_4940_2013.pdf8 Jan 2025
Other - LegalFile: 6-223_Nakul Deshpande_ESVLLP_4933_2013.pdf8 Jan 2025
Other - LegalFile: 7-224_Nakul Deshpande_ ESVLLP_4933_2013.pdf8 Jan 2025
Other - LegalFile: 9-294_Mahdev Mazire_Sigma_6322_2008.pdf8 Jan 2025
Other - LegalFile: 11-294-Deepa Bafana-ESVLLP_12069_2023-1to34.pdf8 Jan 2025
Other - LegalFile: 11-294-Deepa Bafana-ESVLLP_12069_2023-35to68.pdf8 Jan 2025
Building plan approvalFile: 14-17 - Elevation.pdf7 Jan 2025
Copy of the legal title reportFile: Title Report - Pg 1- 86.pdf7 Jan 2025
Copy of the legal title reportFile: Title Report - Pg 87-173.pdf7 Jan 2025
Declaration in FORM BFile: Form - Promoter-colour.pdf7 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 14-17 - Elevation.pdf7 Jan 2025
Other - LegalFile: Incorporation Certificate_of_Conversion_ESV LLP.pdf7 Jan 2025
Other - FinanceFile: POA-ESVLLP-ESV-4118.PDF7 Jan 2025
Other - FinanceFile: Declaration-Land Cost.pdf7 Jan 2025
Other - FinanceFile: POA-ESVLLP-MILIND KULKARNI-3488.pdf7 Jan 2025
Other - FinanceFile: POA-ESVLLP-SANDEEP WALIMBE-3485.pdf7 Jan 2025
Other - FinanceFile: POA_ESVLLP and ESV_4120_26-10-2015.PDF7 Jan 2025
Other - FinanceFile: Declaration for no units and bank account - Sandeep and Milind.pdf7 Jan 2025
Other - FinanceFile: Declaration for no units and bank account - ESV.pdf7 Jan 2025
Other - FinanceFile: Incorporation Certificate_of_Conversion_ESV LLP.pdf7 Jan 2025
Other - TechnicalFile: Annexure A - Order No 50.pdf7 Jan 2025
Other - TechnicalFile: CC Verification Mail - Skyi Manas Lake Phase IX.pdf7 Jan 2025
Other - TechnicalFile: Incorporation Certificate_of_Conversion_ESV LLP.pdf7 Jan 2025
Other - TechnicalFile: Plot Area Declaration.pdf7 Jan 2025
Details of encumbrances concerned to FinanceFile: No Encumbrance Letter -Dues.pdf6 Jan 2025
Details of encumbrances concerned to FinanceFile: No Encumbrance Letter - Litigations.pdf6 Jan 2025
Proforma of Allotment letterFile: AL_Skyi Manas Lake Pahse-IX_03012025.pdf6 Jan 2025
Declaration about Commencement CertificateFile: Format D - Declaration of Commencement Certificate.pdf6 Jan 2025
CERSAI detailsFile: Declaration of Cersai.pdf6 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - All RERA Designated Bank Accounts.pdf6 Jan 2025
Deviation Report with respect to Allotment letterFile: Deviation Allotment Letter.pdf6 Jan 2025
Details of encumbrances concerned to LegalFile: No Encumbrance Letter -Dues.pdf6 Jan 2025
Details of encumbrances concerned to LegalFile: No Encumbrance Letter - Litigations.pdf6 Jan 2025
Deviation Report with respect to model copy of AgreementFile: Deviation-AFS.pdf6 Jan 2025
Proforma of Agreement for saleFile: AFS_Skyi Manas Lake Phase-IX_31122024.pdf6 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf6 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B - Declaration from the bank.pdf6 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Secured and Unsecured Loan.pdf6 Jan 2025
Building plan approvalFile: 13-17 - Terrace and Section AA.pdf4 Jan 2025
Building plan approvalFile: 12-17 - Parking and Typical Floor Plan.pdf4 Jan 2025
Building plan approvalFile: 8-17-Bldg No 11-12-Parking Floor-1.pdf4 Jan 2025
Building plan approvalFile: 1-17 - Layout-1_11zon (1)_11zon.pdf4 Jan 2025
PAN CardFile: PAN ESV LLP.pdf4 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3.pdf4 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Letter-30-12-24.pdf4 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 8-17-Bldg No 11-12-Parking Floor-1.pdf4 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 13-17 - Terrace and Section AA.pdf4 Jan 2025

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Skyi Manas Lake Phase IIIGat No 215 P and others Village Bhukum Mulshi Pune119CompletedFeb 2021Oct 2020
Skyi Manas Lake Phase IIGat No 215 P and others Village Bhukum Mulshi Pune220CompletedFeb 2021Oct 2020
Skyi Manas Lake Phase IGat No 215 and others Bhukum Mulshi Pune249CompletedJun 2017Late, Mar 2018

How this compares with Pune

97%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Skyi Manas Lake Phase IX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune13,700+ in Pune

2 kmSkyi Manas Lake Phase IXCompleted 6Lapsed / revoked 5Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: Enerrgia Skyi Ventures LLP

Enerrgia Skyi Ventures LLP has 9 registrations on MahaRERA, including Skyi Manas Lake Phase I and Skyi Manas Lake Phase II. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Skyi Manas Lake Phase IX is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Skyi Manas Lake Phase IX?

The registered promoter entity is Enerrgia Skyi Ventures LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Skyi Manas Lake Phase IX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Skyi Manas Lake Phase IX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Skyi Manas Lake Phase IX?

The professionals named in the filing: Architect: A.B.S. Architects & Associates; Architect: Dhananjay S. Deshmukh; Architect: Dhananjay Deshmukh; Engineer: Sandip Rangdal & Associates; Chartered Accountant: A S Jinturkar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Skyi Manas Lake Phase IX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Skyi Manas Lake Phase IX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Skyi Manas Lake Phase IX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.