Home / Browse projects / Nashik, Maharashtra / Siyaram Avenues
Siyaram Avenues
RG-MH-07049 · RERA P51600056452 · Last updated on MahaRERA portal: 12 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Siyaram Avenues is a Others project by Amrut Lifespaces in Nashik, Maharashtra, registered with MahaRERA as P51600056452 on 31 May 2024. Possession is promised by 31 Dec 2026. 23 of the 102 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete.
At a glance
Project
- NameSiyaram Avenues
- TypeOthers
- Location
- Deolali Shiwar
- Nashik
- Nashik (M Corp.)
- 422101
- Pincode422101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600056452
- ReraGenie IDRG-MH-07049
Builder
- NameAmrut Lifespaces
- Entity typePartnership
- PartnersDharmesh Amrut Patel, Smeet Amrut Patel, Miheer Amrut Patel
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 May 2024
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings2 building records
- Documents filed103 files
Current status
Figures as on 12 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Siyaram Avenues Wing A | NA | 8 | 7 | 56 | 9 | 65 |
| Siyaram Avenues Wing B | NA | 8 | 7 | 28 | 9 | 37 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 12 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 75%.
Siyaram Avenues Wing A89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Siyaram Avenues Wing B68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 65% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Progress on shared amenities15
As on 12 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 75% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed358
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Siyaram Avenues Wing A | 300 | 300 |
| Siyaram Avenues Wing B | 58 | 58 |
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Dhanraj Appartment Co. Op. Housing Society Ltd. | Nashik (M Corp.) | Nashik |
| Shanti Appartment Co. Op. Housing Society Ltd. | Nashik Road | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Siyaram Avenues Wing A | NA | Rs 7.25 cr | Rs 7.25 cr |
| Siyaram Avenues Wing B | NA | Rs 6.50 cr | Rs 4.55 cr |
| - | NA | Rs 75.00 lakh | - |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Raveena and Nikhil Dhadiwal (Ar. Nikhil Ramesh Dhadiwal) |
| Architect | Raveena and Nikhil Dhadiwal Architects & Interiors |
| Engineer | Mehul Raju Bhai Patel |
| Engineer | Aadhar Engineers |
| Chartered Accountant | CA Paresh Sabadra |
| Chartered Accountant | RSPH & Associates |
| Chartered Accountant | P N Sabadra and Associates |
| Partner | Role in project |
|---|---|
| Amrut Lifespaces | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 May 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 May 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed103
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A - March 26.pdf | 12 Aug 2026 |
| Withdrawal Update Form 1File: AR - June 26.pdf | 1 Aug 2026 |
| Withdrawal Update Form 2File: ER-June 26.pdf | 1 Aug 2026 |
| Withdrawal Update Form 3File: CA-Final.pdf | 1 Aug 2026 |
| Withdrawal Update Form 1File: AR - March 26.pdf | 15 May 2026 |
| Withdrawal Update Form 2File: ER - March 26.pdf | 15 May 2026 |
| Withdrawal Update Form 3File: CA - March 26-final.pdf | 15 May 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - March 25 .pdf | 28 Feb 2026 |
| Withdrawal Update Form 1File: AR - dec 25 .pdf | 31 Jan 2026 |
| Withdrawal Update Form 2File: ER - dec 25 .pdf | 31 Jan 2026 |
| Withdrawal Update Form 3File: CA Dec 25 Final.pdf | 31 Jan 2026 |
| Form 5 (FY 2024-2025)File: RERA audit report final.pdf | 29 Dec 2025 |
| Form 1File: AR - sept 25.pdf | 6 Nov 2025 |
| Form 2File: ER - sept 25.pdf | 6 Nov 2025 |
| Form 3File: CA - sept 25 final.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - Sept 25.pdf | 6 Nov 2025 |
| Form 1File: Architect certificate jun 25.pdf | 25 Jul 2025 |
| Form 2File: ER Certificate Jun 25.pdf | 25 Jul 2025 |
| Form 3File: CA Certificate jun 25.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Jun 25.pdf | 25 Jul 2025 |
| Form 1File: form 1 Architects certificate.pdf | 9 Jun 2025 |
| Form 2File: form 2 Engineers certificate.pdf | 9 Jun 2025 |
| Form 3File: form 3 charted accountants certificate.pdf | 9 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - wing A and B - March 25.pdf | 9 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: Quarterly Progress Report.pdf | 9 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - wing A and B - March 25.pdf | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Architects certificate.pdf | 30 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3.pdf | 30 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Engineers certificate.pdf | 30 Apr 2025 |
| Building plan approvalFile: SHEET 1 Part Completion.pdf | 31 Mar 2025 |
| Building plan approvalFile: SHEET 2 Part Completion.pdf | 31 Mar 2025 |
| Building plan approvalFile: SHEET 3 Part Completion.pdf | 31 Mar 2025 |
| Building plan approvalFile: SHEET 4 Part Completion.pdf | 31 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: SHEET 1 Part Completion.pdf | 31 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: SHEET 2 Part Completion.pdf | 31 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: SHEET 3 Part Completion.pdf | 31 Mar 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: SHEET 4 Part Completion.pdf | 31 Mar 2025 |
| Declaration about Commencement CertificateFile: Format D.pdf | 31 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Disclosure Wing A.pdf | 1 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure wing B.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR CRTE 24.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ar.pdf | 27 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA.pdf | 27 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: er.pdf | 27 Jan 2025 |
| Details of encumbrances concerned to FinanceFile: Index 2 Mortgage Deed.pdf | 21 Jan 2025 |
| Details of encumbrances concerned to LegalFile: Index 2 Mortgage Deed.pdf | 21 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY.pdf | 16 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR CRTE 24.pdf | 12 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE FORM 3 Final.pdf | 12 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER CERT 24.pdf | 12 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY WING A.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY WING B.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE FORM-1.pdf | 17 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert signed copy.pdf | 17 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE FORM-2.pdf | 17 Oct 2024 |
| Copy of the legal title reportFile: AMRUT LIFESPACE TITLE REPORT.pdf | 9 May 2024 |
| Copy of the legal title reportFile: Development Agreement-1-30.pdf | 9 May 2024 |
| Copy of the legal title reportFile: Development Agreement-31-60.pdf | 9 May 2024 |
| Copy of the legal title reportFile: Development Agreement-61-90.pdf | 9 May 2024 |
| Copy of the legal title reportFile: Development Agreement-91-133 - converted.pdf | 9 May 2024 |
| Copy of the legal title reportFile: ALS GPA-1-20.pdf | 9 May 2024 |
| Copy of the legal title reportFile: ALS GPA-21-40.pdf | 9 May 2024 |
| Copy of the legal title reportFile: ALS GPA-41-61.pdf | 9 May 2024 |
| Details of encumbrances concerned to FinanceFile: EC - Finance.pdf | 9 May 2024 |
| Details of encumbrances concerned to FinanceFile: EC - Legal.pdf | 9 May 2024 |
| Details of encumbrances concerned to LegalFile: EC - Finance.pdf | 9 May 2024 |
| Details of encumbrances concerned to LegalFile: EC - Legal.pdf | 9 May 2024 |
| Declaration about Commencement CertificateFile: Form D.pdf | 9 May 2024 |
| Declaration in FORM BFile: Form B of Developers.pdf | 9 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 9 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 9 May 2024 |
| CERSAI detailsFile: Declaration of Cersai.pdf | 9 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Initial Final.pdf | 9 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Other Real Estate.pdf | 9 May 2024 |
| Proforma of Agreement for saleFile: Agreement for sale- Amrut Lifespace.pdf | 9 May 2024 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 9 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank.pdf | 9 May 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation AL.pdf | 9 May 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report - Agreement.pdf | 9 May 2024 |
| Other - LegalFile: One Plot One Registration.pdf | 9 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 103 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Siyaram Avenues on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nashik4,100+ in Nashik
Filed coordinates, straight-line distance. 84 registered projects within 2 km.
The Exchange
Viraj Estates Pvt. Ltd. & Others
HARI SANSKRUTI PHASE II
KBC GLOBAL LIMITED
ARRPAN HOUSING
A C JAIN BUILDERS AND DEVELOPERS LLP
Shilpa Madhuvan
Shilpa Estate
STAR PLUS B
DEEPAK KALYANJI CHANDE
SKY ONE
OM SAI OM BUILDERS
See every Nashik project, with the district possession charts
Builder: Amrut Lifespaces
Amrut Lifespaces has 1 registration on MahaRERA, including Siyaram Avenues. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Siyaram Avenues is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Siyaram Avenues?
The registered promoter entity is Amrut Lifespaces, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Siyaram Avenues?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Siyaram Avenues?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Siyaram Avenues?
The professionals named in the filing: Architect: Raveena and Nikhil Dhadiwal (Ar. Nikhil Ramesh Dhadiwal); Architect: Raveena and Nikhil Dhadiwal Architects & Interiors; Engineer: Mehul Raju Bhai Patel; Engineer: Aadhar Engineers; Chartered Accountant: CA Paresh Sabadra; Chartered Accountant: RSPH & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Siyaram Avenues?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback