Home / Browse projects / Nagpur, Maharashtra / SINGAPORE LIFE CITY

Completed No litigation declared Residential / Group Housing project

SINGAPORE LIFE CITY

By DHL INFRABULLS

RG-MH-01314 · RERA P50500002626 · Last updated on MahaRERA portal: 13 Aug 2021

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Oct 2021Possession promisedregistration recorded completed
0 of 77Construction stages doneacross 7 buildings; furthest along: Excavation, 0%
1Complaints at MahaRERAon this registration
Jump to the 165 documents Report an error

SINGAPORE LIFE CITY is a Residential / Group Housing project by DHL INFRABULLS in Nagpur, Maharashtra, registered with MahaRERA as P50500002626 on 2 Aug 2017. The registration is recorded completed; possession was promised by 30 Oct 2021. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSINGAPORE LIFE CITY
  • TypeResidential / Group Housing
  • Location
    • Gotal Panjari
    • Nagpur (Rural)
    • Nagpur
    • 441108
  • Pincode441108
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500002626
  • ReraGenie IDRG-MH-01314

Builder

  • NameDHL INFRABULLS
  • Entity typePartnership
  • PartnersSANTOSH KUMAR SHIV PRASAD SINGH, NISHIT ARUNKUMAR JAISWAL, RISHIT ARUN JAISWAL

Key dates

this monthRegisteredAug 2017First promiseOct 2019Revised toOct 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on2 Aug 2017
  • Promised completion30 Oct 2021
  • Revised completionRevised to 30 Oct 2021 (originally 31 Oct 2019)
  • Buildings7 building records
  • Documents filed165 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 01 WING A RAFFLES TOWERNA80000
BUILDING NO 02 THE FULLERTONNA40000
BUILDING NO 03 THE FULLERTONNA40000
BUILDING NO 04 THE SENTOSANA40000
BUILDING NO 05 THE SENTOSANA40000
BUILDING NO 06 THE ORCHARDNA40000
BUILDING NO 01 WING B RAFFLES TOWERNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 13 Aug 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Excavation, at 0%.

BUILDING NO 01 WING A RAFFLES TOWER0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 02 THE FULLERTON0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 03 THE FULLERTON0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 04 THE SENTOSA0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 05 THE SENTOSA0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 06 THE ORCHARD0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 01 WING B RAFFLES TOWER0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Aug 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes55%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes55%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes60%
Street LightingYes60%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes10%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered7
Open Space3
BuildingClosed/CoveredOpen SpaceTotal
BUILDING NO 01 WING A RAFFLES TOWER112
BUILDING NO 02 THE FULLERTON101
BUILDING NO 03 THE FULLERTON101
BUILDING NO 04 THE SENTOSA101
BUILDING NO 05 THE SENTOSA101
BUILDING NO 06 THE ORCHARD112
BUILDING NO 01 WING B RAFFLES TOWER112

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,458 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI12296.0
Proposed, not sanctioned12,296 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSITABULDI NAGPUR

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSKA CONSORTIUM
EngineerPATANKAR & ASSOCIATES
PartnerRole in project
DHL INFRABULLS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500002546Oct 2019 → Oct 2020

Reason as filed by the promoterSLOW DOWN IN BUSINESS

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12501324Narendra Anantrao RambhadDHL INFRABULLS21/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Oct 2020

Documents filed165

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 165 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Completion Certificate By Architect In Form 4 for Singapore Life City.pdf13 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf22 Oct 2020
Building plan approvalFile: Building_Permit_6th_floor_compressed__1_.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan1.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan2.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan3.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan4.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan6.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan6.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan7.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan8.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan9.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan10.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan11.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan12.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan13.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan15.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan16.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan17.pdf5 Mar 2020
Building plan approvalFile: Updated Sanction Plan18.pdf5 Mar 2020
Building Plan Approval (IOD)File: Building_Permit_6th_floor_compressed__1_.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan1.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan2.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan3.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan4.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan6.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan6.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan7.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan8.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan9.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan10.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan11.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan12.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan13.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan15.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan16.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan17.pdf5 Mar 2020
Building Plan Approval (IOD)File: Updated Sanction Plan18.pdf5 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Updated Sanction Plan5.pdf5 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Updated Sanction Plan14.pdf5 Mar 2020
OtherFile: Fire_NOC_2.pdf5 Mar 2020
OtherFile: Fire_NOC_2.pdf5 Mar 2020
Building plan approvalFile: scan748.pdf29 Feb 2020
Building plan approvalFile: scan749.pdf29 Feb 2020
Building plan approvalFile: scan750.pdf29 Feb 2020
Building plan approvalFile: scan750.pdf29 Feb 2020
Building plan approvalFile: scan753.pdf29 Feb 2020
Building plan approvalFile: scan756.pdf29 Feb 2020
Building plan approvalFile: scan757.pdf29 Feb 2020
Building plan approvalFile: scan758.pdf29 Feb 2020
Building plan approvalFile: scan759.pdf29 Feb 2020
Building plan approvalFile: scan759.pdf29 Feb 2020
Building plan approvalFile: scan764.pdf29 Feb 2020
Building plan approvalFile: scan765.pdf29 Feb 2020
Building plan approvalFile: scan766.pdf29 Feb 2020
Building plan approvalFile: scan767.pdf29 Feb 2020
Building plan approvalFile: scan768.pdf29 Feb 2020
Building plan approvalFile: scan769.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan748.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan749.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan750.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan750.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan753.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan756.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan757.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan758.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan759.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan759.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan764.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan765.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan766.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan767.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan768.pdf29 Feb 2020
Building Plan Approval (IOD)File: scan769.pdf29 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19(1).pdf31 Oct 2019
Certificates of CA (Form 3)File: Form 3.pdf17 Oct 2019
Annual Audit Report of Statutory CA (Form 5)File: Audit Report FOrm 5 FY 17-18.pdf17 Oct 2019
OtherFile: iMAGE1.pdf17 Oct 2019

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one moved by 24 months
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SINGAPORE LIFE CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gotal Panjari2,800+ in Nagpur

2 kmSINGAPORE LIFE CITYCompleted 2Lapsed / revoked 1Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 6 registered projects within 2 km.

Builder: DHL INFRABULLS

DHL INFRABULLS has 1 registration on MahaRERA, including SINGAPORE LIFE CITY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if SINGAPORE LIFE CITY is delayed beyond 30 Oct 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SINGAPORE LIFE CITY?

The registered promoter entity is DHL INFRABULLS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SINGAPORE LIFE CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SINGAPORE LIFE CITY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SINGAPORE LIFE CITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SINGAPORE LIFE CITY?

The professionals named in the filing: Architect: SKA CONSORTIUM; Engineer: PATANKAR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SINGAPORE LIFE CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SINGAPORE LIFE CITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SINGAPORE LIFE CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.