Home / Browse projects / Dakshina Kannada, Karnataka / SINDHU SOUPARNIKA

Registration approved No litigation declared Mixed Development project

SINDHU SOUPARNIKA

By SINDHU CORPORATION

RG-KA-50808 · RERA PRM/KA/RERA/1257/334/PR/100925/008079 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2030Possession promisedno revision filed
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 70%
59 of 71Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 133 documents Report an error

SINDHU SOUPARNIKA is a Mixed Development project by SINDHU CORPORATION in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/100925/008079 on 10 Sep 2025. Possession is promised by 31 Dec 2030. 12 of the 71 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.

At a glance

Project

  • NameSINDHU SOUPARNIKA
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/100925/008079
  • ReraGenie IDRG-KA-50808

Builder

  • NameSINDHU CORPORATION
  • Entity typePartnership Firm
  • GSTIN29ADEFS1291C1Z5
  • Authorized SignatoryPRASHANTH KUMAR
  • Other registrations2 more →

Key dates

this monthRegisteredSep 2025PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Sep 2025
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings2 building records
  • Documents filed133 files

Current status

17%12 of 71 units booked
7.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK A---04949
BLOCK B---22022

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 70%.

Building: 17% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work70%
Foundation footing work60%
Upto Plinth Level50%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)40%
Retaining wall (All types)30%
RCC or MS Framed structure20%
Masonry Construction20%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities42

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
SEWAGE TREATMENT PLANT (STP)Yes0%
ELECTRICITY SUPPLY TRANSFORMER AND SUBSTATIONYes0%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes20%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners5
LandownerVillageDistrict
SINDHU CORPORATION--
SINDHU CORPORATION--
SINDHU CORPORATION--
SINDHU CORPORATION--
SINDHU CORPORATION--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 11.07 cr
Cost incurredRs 77.47 lakh
Spent of the estimate7.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 11.07 crRs 77.47 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVENKATESH R
EngineerSURESH KUMAR P
Chartered AccountantCA SHAM BHAT K

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed133

As listed on the registration, under the names the promoter filed them with; the newest 80 of 133 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/100925/008079 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA - SEP 26 - SOUPARNIKA.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH - SEP 26 - SOUPARNIKA.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR - SEP 26 - SOUPARNIKA.pdf14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA - JUNE 26 - SOUPARNIKA.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH - JUNE 26 - SOUPARNIKA.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR - JUNE 26 - SOUPARNIKA.pdf14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA - MAR 26 - SOUPARNIKA.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH - MAR 26 - SOUPARNIKA.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR - MAR 26 - SOUPARNIKA.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: F4 Chartered Accountant (QU) DEC 25 - SOUPARNIKA.pdf17 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH - DEC 25 - SOUPARNIKA.pdf17 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR - DEC 25 - SOUPARNIKA.pdf17 Jan 2026
AFFIDAVIT FOR NOCsFile: AFFIDAVIT FOR NOCs.pdf1 Sep 2025
ALL FLOOR WISE PLANSFile: ALL FLOOR WISE PLANS.pdf1 Sep 2025
BLOCK B 1to3rd BLOCK A 2to4thFile: BLOCK B 1to3rd BLOCK A 2to4th.pdf1 Sep 2025
BLOCK B 4th BLOCK A 5thFile: BLOCK B 4th BLOCK A 5th.pdf1 Sep 2025
BLOCK B Base & BLOCK A GthFile: BLOCK B Base & BLOCK A Gth.pdf1 Sep 2025
BLOCK B Gth BLOCK A 1stFile: BLOCK B Gth BLOCK A 1st.pdf1 Sep 2025
BLOCK B Terr BLOCK A TerrFile: BLOCK B Terr BLOCK A Terr.pdf1 Sep 2025
CDP Plan Souparnika demarcatedFile: CDP Plan Souparnika demarcated.pdf1 Sep 2025
Electrical - SouparnikaFile: Electrical - Souparnika.pdf1 Sep 2025
SITE & SECTION & BLOCK A ELEVATIONFile: SITE & SECTION & BLOCK A ELEVATION.pdf1 Sep 2025
Souparnika Revised MCC LicenseFile: Souparnika Revised MCC License.pdf1 Sep 2025
SOUPARNIKA_GOOGLE MAP demarcationFile: SOUPARNIKA_GOOGLE MAP demarcation.pdf1 Sep 2025
Ver 01_ALLOTMENT LETTER - SINDHU SOUPARNIKAFile: Ver 01_ALLOTMENT LETTER - SINDHU SOUPARNIKA.pdf1 Sep 2025
VILLAGE MAP demarcatedFile: VILLAGE MAP demarcated.pdf1 Sep 2025
Water Supply - SouparnikaFile: Water Supply - Souparnika.pdf1 Sep 2025
ADLR Sketch SouparnikaFile: ADLR Sketch souparnika.pdf9 Jul 2025
AFFIDAVIT FOR NOCsFile: AFFIDAVIT FOR NOCs.pdf9 Jul 2025
APPROVED PLAN - ALL FLOOR WISE PLANSFile: ALL FLOOR WISE PLANS.pdf9 Jul 2025
BALANCE SHEET AND SHEDULES ended March 2024File: BALANCE SHEET AND SHEDULES ended March 2024.pdf9 Jul 2025
CDP Plan Souparnika demarcatedFile: CDP Plan Souparnika demarcated.pdf9 Jul 2025
F1 CA CERTIFICATEFile: F1 CA CERTIFICATE.pdf9 Jul 2025
APPROVED PLAN - SITE & SECTION & BLOCK A ELEVATIONFile: SITE & SECTION & BLOCK A ELEVATION.pdf9 Jul 2025
SINGLE SITE LETTER & PLANFile: SINGLE SITE LETTER & PLAN.pdf9 Jul 2025
Souparnika new khathaFile: Souparnika new khatha.pdf9 Jul 2025
Souparnika Revised MCC LicenseFile: Souparnika Revised MCC License.pdf9 Jul 2025
SOUPARNIKA_GOOGLE MAP demarcationFile: SOUPARNIKA_GOOGLE MAP demarcation.pdf9 Jul 2025
Ver 01_AGREEMENT FOR SALE - SINDHU SOUPARNIKAFile: Ver 01_AGREEMENT FOR SALE - SINDHU SOUPARNIKA.pdf9 Jul 2025
Ver 01_ALLOTMENT LETTER - SINDHU SOUPARNIKAFile: Ver 01_ALLOTMENT LETTER - SINDHU SOUPARNIKA.pdf9 Jul 2025
VILLAGE MAP demarcatedFile: VILLAGE MAP demarcated.pdf9 Jul 2025
APPROVED PLAN - BLOCK B 1to3rd BLOCK A 2to4thFile: BLOCK B 1to3rd BLOCK A 2to4th.pdf9 Jul 2025
APPROVED PLAN - BLOCK B 4th BLOCK A 5thFile: BLOCK B 4th BLOCK A 5th.pdf9 Jul 2025
APPROVED PLAN - BLOCK B Base & BLOCK A GthFile: BLOCK B Base & BLOCK A Gth.pdf9 Jul 2025
APPROVED PLAN - BLOCK B Gth BLOCK A 1stFile: BLOCK B Gth BLOCK A 1st.pdf9 Jul 2025
APPROVED PLAN - BLOCK B Terr BLOCK A TerrFile: BLOCK B Terr BLOCK A Terr.pdf9 Jul 2025
RTC, survey 37/6CP1-
Mutation, survey 37/6CP1-
Encumbrance Certificate, survey 37/6CP1-
Conversion/Alienation Order, survey 37/6CP1-
Sale/Title/Gift Deed, survey 37/6CP1-
Khatha, survey 37/6CP1-
RTC, survey 35/3B1P2-
Mutation, survey 35/3B1P2-
Encumbrance Certificate, survey 35/3B1P2-
Conversion/Alienation Order, survey 35/3B1P2-
Sale/Title/Gift Deed, survey 35/3B1P2-
Khatha, survey 35/3B1P2-
RTC, survey 35/3B1P3-
Mutation, survey 35/3B1P3-
Encumbrance Certificate, survey 35/3B1P3-
Conversion/Alienation Order, survey 35/3B1P3-
Sale/Title/Gift Deed, survey 35/3B1P3-
Khatha, survey 35/3B1P3-
RTC, survey 35/3B1P4-
Mutation, survey 35/3B1P4-
Encumbrance Certificate, survey 35/3B1P4-
Conversion/Alienation Order, survey 35/3B1P4-
Sale/Title/Gift Deed, survey 35/3B1P4-
Khatha, survey 35/3B1P4-
RTC, survey 35/3B1P5-
Mutation, survey 35/3B1P5-
Encumbrance Certificate, survey 35/3B1P5-
Conversion/Alienation Order, survey 35/3B1P5-
Sale/Title/Gift Deed, survey 35/3B1P5-
Khatha, survey 35/3B1P5-
Registration CertificateFile: Firm Registration Certificate.pdf-
GST CertificateFile: GST Certificate.pdf-
Partnership DeedFile: PARTNERSHIP DEED.pdf-
Partner Details-

How this compares with Dakshina Kannada

17%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep SINDHU SOUPARNIKA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: SINDHU CORPORATION

SINDHU CORPORATION has 3 registrations on RERA Karnataka, including SINDHU SOUPARNIKA and SINDHU PHALGUNI. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if SINDHU SOUPARNIKA is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SINDHU SOUPARNIKA?

The registered promoter entity is SINDHU CORPORATION, a partnership firm as per the filing. Its GSTIN 29ADEFS1291C1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SINDHU SOUPARNIKA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SINDHU SOUPARNIKA?

The professionals named in the filing: Architect: VENKATESH R; Engineer: SURESH KUMAR P; Chartered Accountant: CA SHAM BHAT K. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SINDHU SOUPARNIKA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SINDHU SOUPARNIKA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SINDHU SOUPARNIKA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.