Home / Browse projects / Nagpur, Maharashtra / Silver Paradise
Silver Paradise
By Raghukul Constructions Private Limited
RG-MH-80909 · RERA P50500023454 · Last updated on MahaRERA portal: 18 Nov 2024
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Silver Paradise is a Residential / Group Housing project by Raghukul Constructions Private Limited in Nagpur, Maharashtra, registered with MahaRERA as P50500023454 on 16 Dec 2019. The registration is recorded completed; possession was promised by 30 Dec 2026.
At a glance
Project
- NameSilver Paradise
- TypeResidential / Group Housing
- Location
- 24 Mtr DP Road
- Somalwada
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440015
- Pincode440015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500023454
- ReraGenie IDRG-MH-80909
Builder
- NameRaghukul Constructions Private Limited
- Entity typeCompany
- CINU45202MH2009PTC197303
- GSTIN27AAECR5597C1Z5
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorMrs Maithili Dilip Bharade
- Other registrations8 more →
- Completed6 of 9
- Declared earlier projects14 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on16 Dec 2019
- Promised completion30 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed137 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Silver Paradise | NA | 12 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.
Silver Paradise: 76% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 5% |
Progress on shared amenities24
As on 18 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
| Basement Parking | Yes | 1% |
| CC TV surveillance | Yes | 2% |
| Compound Gate | Yes | 2% |
| Elevators | Yes | 4% |
| Fire Escape Staircase | Yes | 1% |
| Staircase | Yes | 3% |
| Ground water sump | Yes | 1% |
| Overhead Tank | Yes | 2% |
| Peripheral compound wall | Yes | 1% |
Parking filed46
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | karan Nashine |
| Engineer | Deveshkumar singh |
| Engineer | Sandeep Shelgaonkar |
| Chartered Accountant | SK Panigrahi & Associates |
| Partner | Role in project |
|---|---|
| Raghukul Constructions Private Limited | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Nov 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 15 Aug 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 17 Feb 2024
Documents filed137
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 137 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Status of ConveyanceFile: Conveyance _SP.pdf | 18 Nov 2024 |
| Status of ConveyanceFile: Conveyance _SP.pdf | 18 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SP Occupancy 18-01-2024.pdf | 17 Feb 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Silver Paradise Form 4.pdf | 17 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA SP_compressed.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP ARCHITECT .pdf | 19 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: sp engineering certificate .pdf | 19 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SP QUALITY .pdf | 19 Jan 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200293825944_For_Asset_Based_Search_17_01_2024_20_24_20_050.pdf | 19 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: SP sold unsold.pdf | 19 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SILVER PARADISE _compressed.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Silver Paradise Engineering .pdf | 19 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP ARCHITECT.pdf | 17 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SP QUALITY .pdf | 17 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SP SOLD UNSOLD .pdf | 17 Oct 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200283821372_For_Asset_Based_Search_17_10_2023_19_50_25_183.pdf | 17 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - SILVER PARADISE .pdf | 27 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP ARCHITECT.pdf | 20 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SP ENGINEER.pdf | 20 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SP QUALITY .pdf | 20 Jul 2023 |
| CERSAI detailsFile: SP_CERSAI.pdf | 20 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: SP SOLD UNSOLD.pdf | 20 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA SILVER PARADISE _compressed.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP ARCHITECT'S CERTIFICATE.pdf | 20 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SP ENGINEER CERTIFICATE .pdf | 20 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SP ENGINEER'S CERTIFICATE FORM 2 A.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: SP DISCLOSURE OF SOLDBOOKED INVENTORY.pdf | 20 Apr 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200266645322_For_Asset_Based_Search_20_04_2023_18_16_10_951.pdf | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Document 20_compressed.pdf | 20 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 22 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 sp.pdf | 13 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sp Architect Certificate.pdf | 20 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sp- Enginners certificate.pdf | 20 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: sp quality cert rera (1).pdf | 20 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: sp sold unsold inventory.pdf | 20 Jan 2023 |
| CERSAI detailsFile: cersai silver paradise.pdf | 20 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Silver paradise _compressed.pdf | 20 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Silver Paradise Architect.pdf | 19 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SP-Engineer Certificate .pdf | 19 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SP-QUALITY.pdf | 19 Oct 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200250209635_For_Asset_Based_Search_19_10_2022_17_02_16_082.pdf | 19 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: SP-SOLD UNSOLD.pdf | 19 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SP-CA_compressed.pdf | 19 Oct 2022 |
| CERSAI detailsFile: CERSAI_SILVER_PARADISE.pdf | 20 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SP CA Certifiate_.pdf | 20 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Document 67.pdf | 19 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Document 68 (1)-compressed.pdf | 19 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Document 69.pdf | 19 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Document 68.pdf | 19 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Document 70_compressed.pdf | 19 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects cetificate.pdf | 6 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers cetificate form 2.pdf | 6 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: engineers quality assuarance 2A.pdf | 6 May 2022 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold inventory.pdf | 6 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf | 6 May 2022 |
| Disclosure of sold/ booked inventoryFile: sold unsold inventory-converted.pdf | 9 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's certificate.pdf | 7 Mar 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate.pdf | 7 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer's certificate for Quality assurance.pdf | 7 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 7 Mar 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200227347341_For_Asset_Based_Search_04_01_2022_18_30_53_388.pdf | 4 Jan 2022 |
| CERSAI detailsFile: acknowledgement.pdf | 4 Jan 2022 |
| Declaration about Commencement CertificateFile: circuler32 SP.pdf | 9 Dec 2021 |
| Disclosure of sold/ booked inventoryFile: Sold unsold inventry docement.pdf | 9 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SP Chartered Accountan's Certificate.pdf | 9 Dec 2021 |
| OtherFile: Format C-Circuler 28.pdf | 9 Dec 2021 |
| OtherFile: SP Chartered Accountan's Certificate.pdf | 9 Dec 2021 |
| Declaration about Commencement CertificateFile: circuler32 SP.pdf | 23 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: from no 5 20-21 CA annual report.pdf | 23 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP Architects Certificate Form 1.pdf | 7 Oct 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SP Engineer's Certificate Form 2.pdf | 7 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SP Engineer's Certificate for Quality Assurance Form 2A.pdf | 7 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SP Chartered Accountan's Certificate.pdf | 7 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: sp annual report on statement of account pdf.pdf | 1 Sep 2021 |
| Building plan approvalFile: Permit_Letter.pdf | 15 Aug 2021 |
| Building plan approvalFile: BASEMENT PLAN.pdf | 15 Aug 2021 |
| Building plan approvalFile: GF_FF_PLAN_Sheet2.pdf | 15 Aug 2021 |
| Building plan approvalFile: SF_TF_PLAN_Sheet3.pdf | 15 Aug 2021 |
| Building plan approvalFile: Fourth_Nine_PLAN_Sheet4.pdf | 15 Aug 2021 |
| Building plan approvalFile: Elevation_Sheet_5.pdf | 15 Aug 2021 |
Promoter's earlier projects13
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| DIGVIJAYAP50500047723 | Shankar Nagar, Nagpur | - | Nov 2022 | Completed | Sep 2027 | Mar 2025 |
| SRI BALAJIP50500034108 | SHIVAJI NAGAR NAGPUR, Nagpur | - | Mar 2022 | Completed | Jan 2026 | Jun 2024 |
| KANCHAN GEETP50500018334 | SHIVAJI NAGAR, Nagpur | - | Oct 2018 | Completed | Dec 2024 | Jul 2021 |
| Amrit SaritaP50500001628 | Nagpur (M Corp.), Nagpur | - | Jul 2017 | Completed | Dec 2019 | Dec 2019 |
| Amrit KalashP50500001929 | Nagpur (M Corp.), Nagpur | - | Jul 2017 | Completed | Mar 2019 | Jan 2019 |
| Silver Meadows Apartments | Plot No 1 Near Navnath Society Mouza Somalwada Nagpur | 16 | - | Completed | Feb 2017 | Late, Mar 2017 |
| Smruti Apartments | Plot no 59 Dharampeth extension Shivaji Nagar Nagpur | 24 | - | Completed | Oct 2016 | Late, Nov 2016 |
| Samarpan Apartments | Plot No 80A B Dharampeth Extension Shivaji Nagar Nagpur | 10 | - | Completed | Oct 2015 | Late, Dec 2015 |
| Silver Heights | Plot No 2 Near Navnath Society Mouza- Somalwada Nagpur | 32 | - | Completed | Oct 2015 | Late, Nov 2015 |
| Shree Mohini Raj Apartments | Mouza Lendra Khare Town Dharampeth Nagpur | 26 | - | Completed | Mar 2014 | Late, Jul 2014 |
| Harikrupa Apartments | Plot No E 3 Mouza Ambazari Buty Layout Dharampeth Extension Nagpur | 8 | - | Completed | Mar 2014 | Late, Apr 2014 |
| Krushna Kunj Apartments | Plot no. 152 Mouza Ambazari Dharampeth Extension Nagpur | 12 | - | Completed | Jan 2014 | Late, Feb 2014 |
| Silver Glory Apartments | plot no 3 Near Navnath Society Mouza Somalwada Nagpur | 28 | - | Completed | Oct 2012 | Late, Dec 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 137 filed documents as one ZIP, foldered, with a manifest
Keep Silver Paradise on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Somalwada2,800+ in Nagpur
Filed coordinates, straight-line distance. 112 registered projects within 2 km.
STRAWBERRY FARM
MEGHA AMOL WALKE
OFFICERS ENCLAVE
R SANDESH INFRASTRUCTURES PRIVATE LIMITED
WHITE TIGER AND WILD FLOWER
MILINDKUMAR BHAURAO MESHRAM
PALAZZO ROYAL
INTERCONTINENTAL OASIS INFRA LLP
gokul
surendra mangaldas chadda
Sai Villa 5
Earth Infra Venture
See every Nagpur project, with the district possession charts
Builder: Raghukul Constructions Private Limited
Raghukul Constructions Private Limited has 9 registrations on MahaRERA, including Amrit Kalash and Amrit Sarita. Its filings disclose 14 earlier MahaRERA projects: declares 6 of 14 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if Silver Paradise is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Silver Paradise?
The registered promoter entity is Raghukul Constructions Private Limited, a company as per the filing. Its CIN U45202MH2009PTC197303 and GSTIN 27AAECR5597C1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Silver Paradise?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Silver Paradise?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Silver Paradise?
The professionals named in the filing: Architect: karan Nashine; Engineer: Deveshkumar singh; Engineer: Sandeep Shelgaonkar; Chartered Accountant: SK Panigrahi & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Silver Paradise?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.