Home / Browse projects / Palghar, Maharashtra / Signature Residency

Registered No litigation declared Others project

Signature Residency

By MUNIR ABDULLATIF GAZI

RG-MH-24165 · RERA P99000006550 · Last updated on MahaRERA portal: 13 Jul 2026

Source: official MahaRERA filing

Red flags

  • 34 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
45 of 220Construction stages doneacross 20 buildings; furthest along: Basement (if any), 90%
34Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Signature Residency is a Others project by MUNIR ABDULLATIF GAZI in Palghar, Maharashtra, registered with MahaRERA as P99000006550 on 14 Aug 2017. Possession is promised by 30 Dec 2028. 34 complaints are on record with the regulator.

At a glance

Project

  • NameSignature Residency
  • TypeOthers
  • Location
    • Kambalgaon
    • Boisar
    • Palghar
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000006550
  • ReraGenie IDRG-MH-24165

Builder

  • NameMUNIR ABDULLATIF GAZI
  • Entity typeIndividual
  • Other registrations1 more →

Key dates

this monthRegisteredAug 2017PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Aug 2017
  • Promised completion30 Dec 2028
  • Revised completionNone
  • Buildings20 building records
  • Documents filed75 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No 1NA40000
Building No 2NA40000
Building No 3NA40000
Building No 4NA40000
Building No 5NA40000
Building No 6NA40000
Building No 7NA40000
Building No 8NA40000
Building No 9NA40000
Building No 10NA40000
Building No 11NA40000
Building No 12NA40000
Building No 13NA40000
Building No 14NA40000
Building No 15NA00000
Building No 34NA00000
Building No 35NA00000
Building No 36NA00000
Building No 37NA00000
Building No 38NA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

45 of 220 construction stages are filed complete across 20 buildings. The stage furthest along is Basement (if any), at 90%.

Building No 125%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 235%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 344%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 436%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 536%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 625%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 741%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 843%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 943%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 1043%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 1143%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 1243%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 1335%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 1437%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 150%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 340%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 350%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 360%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 370%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 380%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes20%
Landscaping & Tree PlantingYes0%
Street LightingYes5%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,570 sq m
Land owned byThe promoter, with other names on the file
Named landownersNone

Approvals and building plan

Permissible FSI19560.0
Proposed, not sanctioned9,070 sq m
Buildings approved20
Buildings sanctioned20

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBoisar west, Dist Palghar

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKetan Gopal Sawant
EngineerJai Shree Krishna Consulting Engineer
EngineerShilpLekha Associates
Chartered AccountantCA Archit Patel
PartnerRole in project
MUNIR ABDULLATIF GAZI-

Complaints filed with MahaRERA34

Case no.ComplainantRespondentFiled
CC006000000197674Shweta Ajay BarveGoldstar Realtors29/07/2021
CC006000000054608VISHALPRAKASH MUTREJAGoldstar Realtors23/05/2018
CC006000000056461Ajay Mitairam MauryaGoldstar Realtors05/10/2018
CC006000000055255Dr Munir A GaziGoldstar Realtors04/07/2018
CC006000000055389Abbasi Ibrahimbhai JhabuawalaGoldstar Realtors15/07/2018
CC006000000055405Khadija Muffaddal DohadwalaGoldstar Realtors16/07/2018
CC006000000055574Shivkumar GuptaGoldstar Realtors26/06/2021
CC006000000057121FATEMA MURTUZA MOOKHTIARGOLDSTAR REALTORS30/11/2018
CC006000000057123MUMTAZ HASANABBAS BALSANIAGOLDSTAR REALTORS30/11/2018
CC006000000078616manjula h galaPrakash rakilal masalia26/11/2019
CC006000000195867Sachit JainGoldstar Realtors04/03/2021
CC006000000196876ATISH PRABHAKAR JADKARM/s Goldstar Realtors29/05/2021
CC006000000197387REUBEN GUNASEELAN CHARLESGoldstar Realtors24/06/2021
CC006000000197217Gopal Dukhran SinghGoldstar Realtors15/06/2021
CC006000000197251UMESH YASHWANT SAWANTGoldstar Relators28/07/2021
CC006000000197430SANGEET KUMAR SINGHGoldstar Realtors10/07/2021
CC006000000197274Surendra Mithiram YadavGoldstar Realtors15/06/2021
CC006000000197309Monali Nitesh ShettyGoldstar Realtors18/06/2021
CC006000000197376MR GAURAV PRADEEP BARVEM/S GOLDSTAR REALTORS23/06/2021
CC006000000197378SATISH VIJAYAN NAIRGOLDSTAR REALTORS22/06/2021
CC006000000197381Satish Vijayan NairGoldstar Realtors22/06/2021
CC006000000197389GIRISHKUMAR VISHWAKARMAGoldstar Realtors24/06/2021
CC006000000197397Ashish Kumar SharmaAmit Masalia24/06/2021
CC006000000197726Anita Sanjeev SawantGoldstar Realtors28/07/2021
CC006000000197807Dnyanesh Anil Rao MudholkarGoldstar Realtor04/08/2021
CC006000000197975Aditi Rajesh GadgilGoldstar Realtor13/08/2021
CC006000000198205Asad Shafiq NurieGoldstar Realtor16/09/2021
CC006000000198338Amit Balvantrai MehtaGoldstar Realtor19/09/2021
CC006000000198365Amit Balvantrai MehtaGoldstar Realtor19/09/2021
CC006000000198406SANJAY MADHUKAR BORKARGoldstar Realtor21/09/2021
CC006000000198408KALYANI CAPADIAGoldstar Realtor21/09/2021
CC006000000198421BIJENDRA KUMAR SINGHGoldstar Realtor23/09/2021
CC006000000209950Vishal MutrejaGold Star Realtors08/02/2022
CC006000000396728Association of Allottees of Luxury Empire Township (Signature Residency)Asset Reconstruction Company (India) Limited18/07/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2028

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form1.pdf13 Jul 2026
Form 2File: Form2.pdf13 Jul 2026
Form 3File: form3.pdf13 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold.pdf13 Jul 2026
Form 1File: Form 1 - Rera Certificates Signed.pdf6 May 2026
Form 2File: Form 2 - Rera Certificates Signed.pdf6 May 2026
Form 3File: Form 3 CA With Annex 31032026 Signed.pdf6 May 2026
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD 31-03-2026.pdf6 May 2026
Form 1File: Form 1 Dec2025.pdf19 Jan 2026
Form 3File: Form 3 Dec 2025.pdf19 Jan 2026
Form 2File: FORM 2.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of SOld Unsold.pdf19 Jan 2026
Form 1File: Form 1 30092025.pdf27 Nov 2025
Form 2File: Form 2 30092025.pdf27 Nov 2025
Form 3File: Form 3 with Annexure 30092025.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of SOld & Unsold.pdf27 Nov 2025
Form 1File: Form 1 30062025.pdf27 Nov 2025
Form 2File: Form - 2.pdf27 Nov 2025
Form 3File: Form - 3 wi.pdf27 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of SOld & Unsold.pdf27 Nov 2025
Form 1File: 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf24 May 2025
Form 2File: 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf24 May 2025
Form 3File: 9 Certificates of CA (Form 3).pdf24 May 2025
Form 1File: 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf24 May 2025
Disclosure of Sold and Booked InventoryFile: Form 3 Annexure Dr Gazi (1).pdf24 May 2025
Form 5 (FY 2023-2024)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf24 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2023.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2.pdf20 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2024.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 3.pdf20 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: 1.pdf20 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 (Dec 22 to March 25).pdf17 May 2025
Certificates of CA (Form 3)File: 1-16_11zon.pdf17 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf17 May 2025
Certificates of CA (Form 3)File: Form 3.pdf9 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2_11zon.pdf9 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1.pdf8 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory Details -_11zon.pdf8 Apr 2025
Certificates of CA (Form 3)File: Form 3 Annexure signed.pdf27 Jun 2024
Certificates of CA (Form 3)File: SR Form - 3 Ann compressed.pdf27 Jun 2024
Certificates of CA (Form 3)File: Signed Form 3 With Annexure-1-12.pdf20 May 2024
Certificates of CA (Form 3)File: Signed Form 3 With Annexure-13-23-1-5.pdf20 May 2024
Certificates of CA (Form 3)File: Signed Form 3 With Annexure-13-23-6-11.pdf20 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jan24Architecture Certificate .pdf17 May 2024
CERSAI detailsFile: 1CERSAI_Search_Report_Transaction_Id_Based_Search_08_01_2024_12_53_30_736.pdf17 May 2024
CERSAI detailsFile: 2CERSAI.pdf17 May 2024
CERSAI detailsFile: 3CERSAI_Search_Report_Transaction_Id_Based_Search_08_01_2024_12_53_12_473.pdf17 May 2024
CERSAI detailsFile: 4CERSAI_Search_Report_Transaction_Id_Based_Search_08_01_2024_12_52_32_518.pdf17 May 2024
Layout approvalFile: Approved Plan 2020.pdf8 Feb 2024
Copy of Layout Approval (in case of layout)File: Approved Plan 2020.pdf8 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Revised CC_compressed.pdf8 Feb 2024
Certificates of CA (Form 3)File: Updated Form 3.pdf22 Feb 2023
Declaration in FORM BFile: Form B.pdf14 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf14 Feb 2023
Layout approvalFile: Highlighted layout plan.pdf13 Feb 2023
Copy of Layout Approval (in case of layout)File: Highlighted layout plan.pdf13 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf13 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf13 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf13 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf13 Feb 2023
Layout approvalFile: Layout 45.pdf30 Jul 2017
Layout approvalFile: Proposed But Not Sanctioned Layout.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout 45.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Proposed But Not Sanctioned Layout.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Declaration E II.pdf30 Jul 2017
Certificates of CA (Form 3)File: Declaration II.pdf30 Jul 2017
OtherFile: Declaration from builder i.pdf30 Jul 2017
Building plan approvalFile: 45 CC.pdf29 Jul 2017
Details of encumbrancesFile: encumbrances certificate phase ii.pdf29 Jul 2017
Building Plan Approval (IOD)File: 45 CC.pdf29 Jul 2017
PAN CardFile: GSR PAN CARD.pdf28 Jul 2017
Copy of the legal title reportFile: Legal Report 45 46 47 53.pdf28 Jul 2017
Declaration in FORM BFile: Form B 45.pdf28 Jul 2017
Proforma of Allotment letterFile: Goldstar Realtors no 45 46 47 53.pdf28 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Signature Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Boisar3,200+ in Palghar

2 kmSignature ResidencyCompleted 6Lapsed / revoked 17Other 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 55 registered projects within 2 km.

Builder: MUNIR ABDULLATIF GAZI

MUNIR ABDULLATIF GAZI has 2 registrations on MahaRERA, including Signature Residency and Luxury Empire Township Phase III. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Signature Residency is delayed beyond 30 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Signature Residency?

The registered promoter entity is MUNIR ABDULLATIF GAZI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Signature Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Signature Residency?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Signature Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Signature Residency?

The professionals named in the filing: Architect: Ketan Gopal Sawant; Engineer: Jai Shree Krishna Consulting Engineer; Engineer: ShilpLekha Associates; Chartered Accountant: CA Archit Patel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Signature Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Signature Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Signature Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.