SIDDHIVINAYAK RESIDENCY II

By SUYASH SAHAKAR BUILDERS AND DEVELOPERS

RG-MH-18849 · RERA P52000077666 · Last updated on MahaRERA portal: 24 Sep 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 50%
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

SIDDHIVINAYAK RESIDENCY II is a Others project by SUYASH SAHAKAR BUILDERS AND DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000077666 on 21 Oct 2024. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameSIDDHIVINAYAK RESIDENCY II
  • TypeOthers
  • Location
    • SECTOR 25 A
    • PUSHPAK
    • Ulawe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000077666
  • ReraGenie IDRG-MH-18849

Builder

  • NameSUYASH SAHAKAR BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersAMIT ASHOK JADHAV, ANANDA SHRIPATI SUTAR, DARSHAN PREMCHAND SINGH, HARIBHAU GULABRAO TAWARE
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

13 months past promisethis monthRegisteredOct 2024First promiseDec 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Oct 2024
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIDDHIVINAYAK RESIDENCY IINA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.

SIDDHIVINAYAK RESIDENCY II: 59% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered1
Open Space4

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area270 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
MRS NIRABAI ASHOK KOLIUlaweRaigarh
MR ASHOK CHANDAR KOLIUlaweRaigarh

Approvals and building plan

Permissible FSI404.5
Proposed, not sanctioned404 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch GALA NO J21 MASALA MARKET SECTOR 19 VASHI NAVI MUMBAI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJENDRA TAYWADE
EngineerBAHUBALI T DHAMANE
Chartered AccountantHITESH K CHANDRA
PartnerRole in project
SUYASH SAHAKAR BUILDERS AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000025448Dec 2024 → Sep 2025

Reason as filed by the promoterTo, The Maharashtra Real Estate Regulatory Authority (MahaRERA) Mumbai Subject: Request for Extension of Project Completion Date for SIDDHIVINAYAK RESIDENCY II (Maha RERA Registration No. P52000077666) Dear Sir/Madam, I, Mr. Darshan Singh Partner of Suyash Sahakar Builders and Developers is writing this letter regarding the project of SIDDHIVINAYAK RESIDENCY II registered under Maha RERA with Registration No. P5200007766 Located in Pushpak Node, Ulwe, Maharashtra. The project is located in Pushpak Node, Ulwe and our land layout is 270 sq. mtrs which had a proposal of Ground+4 Building and Comm

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 30th June 2025.pdf24 Sep 2025
Form 1File: Form 1 QTR 1 2025-26.pdf24 Sep 2025
Form 2File: Form 2 QTR 1 2025-26.pdf24 Sep 2025
Form 3File: Form 3 QTR 1 2025-26.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 31st March 2025.pdf24 Sep 2025
Form 1File: Form 1 QTR 4 2024-25.pdf24 Sep 2025
Form 2File: Form 2 QTR 4 2024-25.pdf24 Sep 2025
Form 3File: Form 3 QTR 4 2024-25.pdf24 Sep 2025
Form 1File: Form 1 QTR 3 2024-25.pdf9 Sep 2025
Form 2File: Form 2 QTR 3 2024-25.pdf9 Sep 2025
Form 3File: Form 3 QTR 3 2024-25.pdf9 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory 31st December 2024.pdf9 Sep 2025
Proforma of Agreement for saleFile: Agreement for Sale Final.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Updated.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 138.pdf17 Aug 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: fORMAT a.pdf5 Aug 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Letter.pdf18 Jul 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report.pdf16 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about separate Bank details.pdf28 Feb 2024
Details of encumbrances concerned to FinanceFile: Encumbrance declaration.pdf27 Feb 2024
CERSAI detailsFile: Cersai undertaking.pdf27 Feb 2024
Details of encumbrances concerned to LegalFile: Encumbrance declaration.pdf27 Feb 2024
Other - TechnicalFile: Declaration -cum- undertaking Annexure A.pdf24 Feb 2024
Declaration in FORM BFile: Form -B partner.pdf22 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Architect certificate.pdf22 Feb 2024
Declaration about Commencement CertificateFile: Declaration about CC.pdf22 Feb 2024
Building plan approvalFile: CC Plot no 81 20 Mar 2020 Approved Plan.pdf21 Feb 2024
Layout approvalFile: CC Plot no 81 20 Mar 2020 Approved Plan.pdf21 Feb 2024
Copy of Layout Approval (in case of layout)File: CC Plot no 81 20 Mar 2020 Approved Plan.pdf21 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Plot no 81 sec 25 A Plinth certificate.pdf21 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: CC Plot no 81 20 Mar 2020 Approved Plan.pdf21 Feb 2024
Copy of the legal title reportFile: title 81.pdf15 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure- Haribhau Taware.pdf15 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure - Aanda Sutar.pdf15 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure - Amit Jadhav.pdf15 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure - Darshan singh.pdf15 Feb 2024
Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf29 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Agreement.pdf29 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Engineers Certificate.pdf4 Jan 2024
Proforma of Allotment letterFile: Allotment Type update.pdf23 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: CC Plot no 81 20 Mar 2020.pdf23 Dec 2023
Disclosure of sold/ booked inventoryFile: Discolsure of sold inventory.pdf23 Dec 2023
PAN CardFile: PAN CARD.pdf18 Nov 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SIDDHIVINAYAK RESIDENCYP52000022815PUSHPAK VAHAL ULWE, Raigarh16Oct 2019CompletedMay 2022Late, Mar 2023
SIDDHIVINAYAK RESIDENCYP52000022815PUSHPAK VAHAL ULWE, Raigarh16Oct 2019CompletedMay 2022Late, Mar 2023

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 9 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SIDDHIVINAYAK RESIDENCY II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUSHPAK5,900+ in Raigarh

2 kmSIDDHIVINAYAK RESIDENCY Completed 80Lapsed / revoked 27Other 106Dot size: filed unitsN

Filed coordinates, straight-line distance. 213 registered projects within 2 km.

Builder: SUYASH SAHAKAR BUILDERS AND DEVELOPERS

SUYASH SAHAKAR BUILDERS AND DEVELOPERS has 2 registrations on MahaRERA, including SIDDHIVINAYAK RESIDENCY and SIDDHIVINAYAK RESIDENCY II. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that SIDDHIVINAYAK RESIDENCY II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SIDDHIVINAYAK RESIDENCY II is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SIDDHIVINAYAK RESIDENCY II?

The registered promoter entity is SUYASH SAHAKAR BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SIDDHIVINAYAK RESIDENCY II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SIDDHIVINAYAK RESIDENCY II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SIDDHIVINAYAK RESIDENCY II?

The professionals named in the filing: Architect: RAJENDRA TAYWADE; Engineer: BAHUBALI T DHAMANE; Chartered Accountant: HITESH K CHANDRA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIDDHIVINAYAK RESIDENCY II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIDDHIVINAYAK RESIDENCY II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIDDHIVINAYAK RESIDENCY II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.