ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / SIDDHIVINAYAK PARK

Registration lapsed No litigation declared Others project

SIDDHIVINAYAK PARK

By SIDDHIVINAYAK CONSTRUCTIONS

RG-MH-15557 · RERA P51600046181 · Last updated on MahaRERA portal: 25 Aug 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
18 of 58Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 19 documents Report an error

SIDDHIVINAYAK PARK is a Others project by SIDDHIVINAYAK CONSTRUCTIONS in Nashik, Maharashtra, registered with MahaRERA as P51600046181 on 20 Jun 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 40 of the 58 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSIDDHIVINAYAK PARK
  • TypeOthers
  • Location
    • NASHIK SHIWAR
    • RASBIHARI ROAD
    • Nashik (M Corp.)
    • Nashik
    • 422003
  • Pincode422003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600046181
  • ReraGenie IDRG-MH-15557

Builder

  • NameSIDDHIVINAYAK CONSTRUCTIONS
  • Entity typePartnership
  • PartnersPRATIK ABASAHEB DEORE, MAHENDRA MALJI DEORE, TEJAS ASHOK PATIL, ASHOK CHINDHU PATIL
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredJun 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Jun 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed19 files

Current status

69%40 of 58 units booked
78.9%Work done, per cost certificate

Figures as on 25 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIDDHIVINAYAK PARKNA9854458

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

SIDDHIVINAYAK PARK: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 25 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed164

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots164
Closed/Covered79
Open Space85

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,258 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on22 Aug 2025

Approvals and building plan

Sanctioning authorityEXECUTIVE ENGINEER NASHIK MUCIPLE CORPORATION
Permissible FSI4146.79
Proposed, not sanctioned4,147 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPANCHAVATI NASHIK
Estimated costRs 6.75 cr
Cost incurredRs 5.33 cr
Work done78.92%
BuildingWingEstimatedIncurred
SIDDHIVINAYAK PARKNARs 6.50 crRs 5.20 cr
-NARs 25.00 lakhRs 12.73 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNAVNATH PATIL PATIL
EngineerAKASH JADHAV JADHAV
Chartered AccountantS BRAMHECHA AND COMPANY
PartnerRole in project
SIDDHIVINAYAK CONSTRUCTIONS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed19

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Scan 25 Aug 2025.pdf25 Aug 2025
Withdrawal Update Form 2File: Scan 25 Aug 2025 (1).pdf25 Aug 2025
Withdrawal Update Form 3File: Scan 25 Aug 2025 (2).pdf25 Aug 2025
Building plan approvalFile: PLAN.PDF16 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN.PDF16 Jun 2022
Declaration about Commencement CertificateFile: DECLARATION OF COMMECMENT.pdf16 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_11zon.pdf16 Jun 2022
Layout approvalFile: LAYOUT COPY.pdf6 Jun 2022
Building plan approvalFile: Scan 6 Jun 2022 (8).pdf6 Jun 2022
PAN CardFile: PAN CARD_11zon (1).pdf6 Jun 2022
Copy of the legal title reportFile: LEGAL REPORT_11zon.pdf6 Jun 2022
Details of encumbrancesFile: DECLARATION OF ENCUMBARANCE.pdf6 Jun 2022
Copy of Layout Approval (in case of layout)File: LAYOUT COPY.pdf6 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Scan 6 Jun 2022 (8).pdf6 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMECMENT CERTIFICATE_11zon (2).pdf6 Jun 2022
Declaration in FORM BFile: FORM B_11zon (2).pdf6 Jun 2022
CERSAI detailsFile: CERSAI_Search_Report_200238908704_For_Asset_Based_Search_06_06_2022_10_50_29_990.pdf6 Jun 2022
Proforma of Allotment letterFile: SiddhivinayakPark agreement for sale.pdf6 Jun 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf6 Jun 2022

How this compares with Nashik

69%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SIDDHIVINAYAK PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RASBIHARI ROAD4,100+ in Nashik

2 kmSIDDHIVINAYAK PARKCompleted 55Lapsed / revoked 14Other 52Dot size: filed unitsN

Filed coordinates, straight-line distance. 121 registered projects within 2 km.

Builder: SIDDHIVINAYAK CONSTRUCTIONS

SIDDHIVINAYAK CONSTRUCTIONS has 2 registrations on MahaRERA, including SIDDHIVINAYAK RESIDENCY and SIDDHIVINAYAK PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that SIDDHIVINAYAK PARK shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SIDDHIVINAYAK PARK is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SIDDHIVINAYAK PARK?

The registered promoter entity is SIDDHIVINAYAK CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SIDDHIVINAYAK PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SIDDHIVINAYAK PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SIDDHIVINAYAK PARK?

The professionals named in the filing: Architect: NAVNATH PATIL PATIL; Engineer: AKASH JADHAV JADHAV; Chartered Accountant: S BRAMHECHA AND COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIDDHIVINAYAK PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIDDHIVINAYAK PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIDDHIVINAYAK PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.