Home / Browse projects / Palghar, Maharashtra / SIDDHIVINAYAK COMPLEX

Registered Litigation declared Others project

SIDDHIVINAYAK COMPLEX

By SUGANDHI REALTORS

RG-MH-89084 · RERA P99000011924 · Last updated on MahaRERA portal: 28 Oct 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
19 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 90%
53 of 140Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

SIDDHIVINAYAK COMPLEX is a Others project by SUGANDHI REALTORS in Palghar, Maharashtra, registered with MahaRERA as P99000011924 on 1 Sep 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 87 of the 140 units on this registration are recorded sold or booked, and 19 of 33 construction stages are filed complete.

At a glance

Project

  • NameSIDDHIVINAYAK COMPLEX
  • TypeOthers
  • Location
    • PALGHAR
    • Saravali
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000011924
  • ReraGenie IDRG-MH-89084

Builder

  • NameSUGANDHI REALTORS
  • Entity typePartnership
  • PartnersDEVENDRA KHIMRAJ JAIN, PRASAD PANDURANG PAWAR

Key dates

this monthRegisteredSep 2017First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Sep 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed70 files

Current status

62%87 of 140 units booked
67.4%Work done, per cost certificate

Figures as on 28 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 4 F WING G WINGNA5439039
BUILDING NO 2 A WING B WINGNA5436036
BUILDING NO 3 C WING D WING E WINGNA5465065

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 28 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 90%.

BUILDING NO 4 F WING G WING65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
BUILDING NO 2 A WING B WING88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
BUILDING NO 3 C WING D WING E WING72%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%

Progress on shared amenities15

As on 28 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes70%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered3
BuildingClosed/CoveredTotal
BUILDING NO 4 F WING G WING11
BUILDING NO 2 A WING B WING11
BUILDING NO 3 C WING D WING E WING11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,680 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityChief Executive Office, Thane
Permissible FSI7029.59
Proposed, not sanctioned7,030 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHAKUR ARCADE NEAR RAILWAY STATION VIRAR WEST VASAI 401303
Estimated costRs 4.40 cr
Cost incurredRs 2.97 cr
Work done67.41%
BuildingWingEstimatedIncurred
BUILDING NO 4 F WING G WINGNARs 1.32 crRs 93.00 lakh
BUILDING NO 2 A WING B WINGNARs 1.32 crRs 93.00 lakh
BUILDING NO 3 C WING D WING E WINGNARs 1.32 crRs 93.00 lakh
-NARs 44.00 lakhRs 17.60 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTU SHILP
EngineerDARSH CONSULT
EngineerPradip Patil
Chartered AccountantRamesh D Lukad
PartnerRole in project
SUGANDHI REALTORS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000019606Dec 2023 → Dec 2024

Reason as filed by the promoterEXTENSION REQUIRED FOR STATUTORY COMPLIANCE COMPLETION

EXT99000027649Dec 2023 → Dec 2026

Reason as filed by the promoterThe reason for the extension of the project completion date for the Siddhivinayak Complex (Project Registration No P99000011924) is formally applied under Section 7(3) of the RERA Act. The promoters, M/s Sugandhi Realtors, have submitted the application dated 30/09/2025 to MahaRERA. The key reason for the extension request is the delay in completion schedule. The promoters have obtained consent from 64.37% of the allottees (56 out of 87 sold units) as per the prescribed circular no 07/2019 dated 8 Feb 2019, which requires at least 51% allottee consent for such extension. The construction activ

Litigation declared1

CaseCourtStatus
SPECIAL SUIT NO 66/2011CIVIL JUDGE SENIOR DIVISION AT PALGHARON PRIMARY BASIS

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 6 (1).pdf28 Oct 2025
Form 2File: 6 (3).pdf28 Oct 2025
Form 3File: 6 (5).pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf28 Oct 2025
Withdrawal Update Form 1File: 6 (2).pdf28 Oct 2025
Withdrawal Update Form 2File: 6 (4).pdf28 Oct 2025
Withdrawal Update Form 3File: 7 Certificates of CA (Form 3).pdf28 Oct 2025
Form 2A (FY 2024-2025)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf28 Oct 2025
Form 5 (FY 2023-2024)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf28 Oct 2025
Form 5 (FY 2024-2025)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25).pdf28 Oct 2025
Layout approvalFile: LAYOUT.pdf24 Apr 2024
Layout approvalFile: LAYOUT-1.pdf24 Apr 2024
Building plan approvalFile: BLDG NO 2-A.pdf24 Apr 2024
Building plan approvalFile: BLDG NO 2-B.pdf24 Apr 2024
Building plan approvalFile: BLDG NO 3-A1_11zon.pdf24 Apr 2024
Building plan approvalFile: BLDG NO 3-C1_11zon.pdf24 Apr 2024
Building plan approvalFile: BLDG NO 3-D_11zon.pdf24 Apr 2024
Building plan approvalFile: BLDGNO 4-A2_11zon.pdf24 Apr 2024
Building plan approvalFile: BLDG NO 4-C_11zon.pdf24 Apr 2024
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf24 Apr 2024
Copy of Layout Approval (in case of layout)File: LAYOUT-1.pdf24 Apr 2024
Building Plan Approval (IOD)File: BLDG NO 2-A.pdf24 Apr 2024
Building Plan Approval (IOD)File: BLDG NO 2-B.pdf24 Apr 2024
Building Plan Approval (IOD)File: BLDG NO 3-A1_11zon.pdf24 Apr 2024
Building Plan Approval (IOD)File: BLDG NO 3-C1_11zon.pdf24 Apr 2024
Building Plan Approval (IOD)File: BLDG NO 3-D_11zon.pdf24 Apr 2024
Building Plan Approval (IOD)File: BLDGNO 4-A2_11zon.pdf24 Apr 2024
Building Plan Approval (IOD)File: BLDG NO 4-C_11zon.pdf24 Apr 2024
Declaration in FORM BFile: 3 Declaration in FORM B (1).pdf23 Apr 2024
Declaration in FORM BFile: 2 Declaration in FORM B.pdf22 Apr 2024
PAN CardFile: SUGANDHI-pan card.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf16 Apr 2024
Certificates of CA (Form 3)File: FORM 3 SUGANDHI.pdf16 Apr 2024
Other - TechnicalFile: ANNEXURE A DECLARATION CUM UNDERTAKING.pdf16 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: New - 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project) 1.pdf15 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 19-20.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 20-21.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21-22.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 22-23.pdf13 Apr 2024
Details of encumbrancesFile: Finance Encumbrance.pdf12 Apr 2024
Details of encumbrances concerned to FinanceFile: Legal Encumbrance.pdf12 Apr 2024
Details of encumbrances concerned to LegalFile: Legal Encumbrance.pdf12 Apr 2024
Declaration about Commencement CertificateFile: cc declaration.pdf12 Apr 2024
Declaration about Commencement CertificateFile: ANNEXURE A DISCLOSURE OF INTEREST 2.pdf12 Apr 2024
Declaration in FORM BFile: FROM B AFIDAVIT CUM DECLARATION.pdf12 Apr 2024
CERSAI detailsFile: Cersai.pdf12 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A DISCLOSURE OF INTEREST 1.pdf12 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 MARCH 18.pdf12 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 MARCH 19.pdf12 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5-19-20.pdf12 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 MARCH 21.pdf12 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 MARCH 22.pdf12 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 MARCH23.pdf12 Apr 2024
Proforma of Agreement for saleFile: AGREEMENT.pdf12 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Declaration.pdf12 Apr 2024
Deviation Report with respect to Allotment letterFile: Deviation-Allotment.pdf12 Apr 2024
Deviation Report with respect to model copy of AgreementFile: Deviatin-Agreement.pdf12 Apr 2024
Building plan approvalFile: cc.pdf8 Aug 2017
Layout approvalFile: layout.pdf8 Aug 2017
Copy of the legal title reportFile: TITLE.pdf8 Aug 2017
Details of encumbrancesFile: Authorization Letter.pdf8 Aug 2017
Copy of Layout Approval (in case of layout)File: layout.pdf8 Aug 2017
Building Plan Approval (IOD)File: cc.pdf8 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf8 Aug 2017
Declaration in FORM BFile: Form B Affidavit Cum Declaration.pdf8 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf8 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate.pdf8 Aug 2017
Certificates of CA (Form 3)File: Form 3 C A Certificate.pdf8 Aug 2017
Proforma of Allotment letterFile: DRAFT AGGREMENT.pdf8 Aug 2017

How this compares with Palghar

62%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 36 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SIDDHIVINAYAK COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PALGHAR3,200+ in Palghar

2 kmSIDDHIVINAYAK COMPLEXCompleted 9Lapsed / revoked 6Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: SUGANDHI REALTORS

SUGANDHI REALTORS has 1 registration on MahaRERA, including SIDDHIVINAYAK COMPLEX. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SIDDHIVINAYAK COMPLEX is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SIDDHIVINAYAK COMPLEX?

The registered promoter entity is SUGANDHI REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SIDDHIVINAYAK COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SIDDHIVINAYAK COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SIDDHIVINAYAK COMPLEX?

The professionals named in the filing: Architect: VASTU SHILP; Engineer: DARSH CONSULT; Engineer: Pradip Patil; Chartered Accountant: Ramesh D Lukad. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIDDHIVINAYAK COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIDDHIVINAYAK COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIDDHIVINAYAK COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.