Home / Browse projects / Mumbai Suburban, Maharashtra / SIDDHI GARIMA
SIDDHI GARIMA
By NHA INFRAPROJECTS PRIVATE LIMITED
RG-MH-10395 · RERA P51800000706 · Last updated on MahaRERA portal: 27 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 84 months
- 6 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SIDDHI GARIMA is a Residential / Group Housing project by NHA INFRAPROJECTS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000706 on 20 Jul 2017. Possession was promised by 30 Dec 2025 and is now 10 months past that date. The completion date has moved by 84 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameSIDDHI GARIMA
- TypeResidential / Group Housing
- Location
- CHEMBUR
- Kurla
- Mumbai Suburban
- 400074
- Pincode400074
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800000706
- ReraGenie IDRG-MH-10395
Builder
- NameNHA INFRAPROJECTS PRIVATE LIMITED
- Entity typeCompany
- Managing DirectorPRAVIN MANOHARLAL TALREJA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on20 Jul 2017
- Promised completion30 Dec 2025
- Revised completionRevised to 30 Dec 2025 (originally 31 Dec 2018)
- Buildings1 building record
- Documents filed188 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SIDDHI GARIMA | NA | 24 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
SIDDHI GARIMA: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 27 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed135
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | M/s. VIVEK BHOLE ARCHITECTS PVT LTD |
| Architect | M/s. SUNIL AMBRE & ASSOCIATES. |
| Engineer | M/s. ASSOCIATED CONSULTANTS. |
| Chartered Accountant | M P KANGUTKAR & ASSOCIATES |
| Partner | Role in project |
|---|---|
| NHA INFRAPROJECTS PRIVATE LIMITED | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThat due to delay in issue of Notification by Government of Maharashtra in respect use of double TDR Policy as per the provisions of DCR 2034, the MCGM has restricted some part of Commercial Premises. That the restricted Part of Commercial Part has not been sold to anyone. The said Notification is expected to be released by the Government of Maharashtra. That we have completed all residential Flats for which already OC has been issued by MCGM and Physical Possession of all the Sold Flats has been given to the Purchasers. That in view of the above circumstances, we request you to kindly extend
Reason as filed by the promoterThat the common compound wall existing between our Project and BMC School collapsed and MCGM had issued Stop Work Notice and it took time for revocation of Stop Work Notice due to which work was delayed. The delays was also caused due to issue of Notification for implementation of DCR 2034, which delayed the approval of Plans. Therefore we are requesting for a extension of only 1 year for completion of Project. The details are mentioned in the Self Declaration and the Copy of the Stop Work Notice is attached.
Reason as filed by the promoter1. That in our Application for registration of our Project under MAHARERA, that previously we have requested for Extension and we have been granted extension till 30-12-2022. That our Project Registration serial number is P51800000706. 2. Our is a composite building of Residential and Commercial premises. The Occupation Certificate for the full Residential premises has been received and all the residential flats have been handed over to all the allotees. 3. A Notification by Government of Maharashtra in respect of use of TDR as per the provisions of DCR 2034 in relation to our Commercial Premi
Reason as filed by the promoterAwaiting Government Notification regarding TDR
Reason as filed by the promoterTo, The Maharashtra Real Estate Regulatory Authority. Respected Sir, We, M/s. NHA Infraprojects Pvt. Ltd, a company formed under the provisions of the Companies Act, 1956, having its office at A- 802, Siddhi Garima, Tapasya Apartment CHS Ltd., Collector Colony, Chembur, Mumbai - 400 074. Ours is a composite building of Residential and Commercial premises. The Occupation Certificate for the full Residential premises has been received and all the residential flats have been handed over to all the allotees. Part OC for your reference is enclosed herewith. In case of commercial premises we had rec
Reason as filed by the promoterWe, M/s. NHA Infraprojects Pvt. Ltd, a company formed under the provisions of the Companies Act, 1956, having its office at A- 802, Siddhi Garima, Tapasya Apartment CHS Ltd., Collector Colony, Chembur, Mumbai - 400 074. Our Project Registration serial number is P51800000706. Previously we have requested for Extension and we have been granted extension till 30-12-2024. Ours is a composite building of Residential and Commercial premises. The Occupation Certificate for the full Residential premises has been received and all the residential flats have been handed over to all the allotees. In case
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000078769 | Ranchandra Yadavrao | NHA Infraprojects Pvt Ltd | 06/04/2019 |
| CC006000000193282 | Kishnlal Singhvi and 3 others | NHA Infrarproject Pvt Ltd | 14/06/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Aug 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Nov 2019
Documents filed188
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 188 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 27 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 27 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory Details.pdf | 27 May 2025 |
| Certificates of CA (Form 3)File: Form3.pdf | 15 May 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 7 May 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 20 Apr 2025 |
| Certificates of CA (Form 5)File: FORM NO 5.pdf | 20 Apr 2025 |
| Declaration in FORM BFile: Form B.pdf | 26 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3 Uploaded.pdf | 26 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Updated Architect Certificate.pdf | 31 Jan 2025 |
| Declaration in FORM BFile: Affidavit Cum Declaration.pdf | 30 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 30 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 30 Jan 2025 |
| Certificates of CA (Form 5)File: Form - 5.pdf | 30 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 30 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 30 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf | 30 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Audit Report and Financials FY 2023-2024.pdf | 24 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 6 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 6 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2 A.pdf | 6 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Booked_Sold Inventory Details.pdf | 6 Feb 2024 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 6 Feb 2024 |
| Certificates of CA (Form 5)File: FORM 5.pdf | 6 Feb 2024 |
| Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf | 19 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory.pdf | 19 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate.pdf | 28 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate.pdf | 28 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: NHA_Signed Financials FY 2021-22.pdf | 28 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: NHA Financials FY 2022-23.pdf | 28 Dec 2023 |
| Home Buyer /Allottee Grievance Redressal CellFile: Home Buyer_Allottee Grievance Redressal Cell.pdf | 28 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory.pdf | 20 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Org.pdf | 20 Dec 2023 |
| Proforma of Agreement for saleFile: Proforma of Agreement for sale.pdf | 14 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Flats.pdf | 14 Dec 2022 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory.pdf | 22 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account.pdf | 22 Aug 2022 |
| Foreclosure of the ProjectFile: Forecloure.pdf | 22 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf | 22 Aug 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement.pdf | 22 Aug 2022 |
| Other - FinanceFile: Other Technical.pdf | 22 Aug 2022 |
| Other - TechnicalFile: Other Technical.pdf | 22 Aug 2022 |
| Details of encumbrances concerned to LegalFile: declaration of encumbrance.pdf | 17 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank account and Details of encumbrance.pdf | 17 Aug 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate'.pdf | 22 Mar 2022 |
| Status of ConveyanceFile: Society Registration Certificate'.pdf | 22 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: Sold and Unsold Inventory.pdf | 5 Mar 2022 |
| CERSAI detailsFile: CERSAI.pdf | 5 Mar 2022 |
| Certificates of CA (Form 3)File: Final Form 3 CA Signed_compressed.pdf | 5 Mar 2022 |
| Building plan approvalFile: Drawing 6 ammendment-1.pdf | 3 Mar 2022 |
| Building plan approvalFile: Drawing 6 ammendment-2_compressed.pdf | 3 Mar 2022 |
| Building plan approvalFile: Drawing 6 ammendment-3_compressed.pdf | 3 Mar 2022 |
| Building plan approvalFile: Drawing 6 ammendment-4_compressed.pdf | 3 Mar 2022 |
| Building plan approvalFile: Drawing 6 ammendment-5.pdf | 3 Mar 2022 |
| Building plan approvalFile: Drawing 6 ammendment-6.pdf | 3 Mar 2022 |
| Building plan approvalFile: Drawing 6 ammendment-7_compressed.pdf | 3 Mar 2022 |
| Building plan approvalFile: Drawing 6 ammendment-8.pdf | 3 Mar 2022 |
| Building plan approvalFile: Drawing 6 ammendment-9.pdf | 3 Mar 2022 |
| Details of encumbrancesFile: Details_of_Encumbrance.pdf | 3 Mar 2022 |
| Building Plan Approval (IOD)File: Drawing 6 ammendment-1.pdf | 3 Mar 2022 |
| Building Plan Approval (IOD)File: Drawing 6 ammendment-2_compressed.pdf | 3 Mar 2022 |
| Building Plan Approval (IOD)File: Drawing 6 ammendment-3_compressed.pdf | 3 Mar 2022 |
| Building Plan Approval (IOD)File: Drawing 6 ammendment-4_compressed.pdf | 3 Mar 2022 |
| Building Plan Approval (IOD)File: Drawing 6 ammendment-5.pdf | 3 Mar 2022 |
| Building Plan Approval (IOD)File: Drawing 6 ammendment-6.pdf | 3 Mar 2022 |
| Building Plan Approval (IOD)File: Drawing 6 ammendment-7_compressed.pdf | 3 Mar 2022 |
| Building Plan Approval (IOD)File: Drawing 6 ammendment-8.pdf | 3 Mar 2022 |
| Building Plan Approval (IOD)File: Drawing 6 ammendment-9.pdf | 3 Mar 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_compressed.pdf | 3 Mar 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_compressed.pdf | 3 Mar 2022 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Signed.pdf | 3 Mar 2022 |
| Certificates of CA (Form 5)File: Form 5 Annual Report Signed.pdf | 3 Mar 2022 |
| OtherFile: FurtherCC_.pdf | 3 Mar 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Flats_compressed.pdf | 8 Nov 2021 |
| Details of encumbrancesFile: Changes in Encumbrances Report.pdf | 2 Nov 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf | 2 Nov 2021 |
| Certificates of CA (Form 5)File: Form 5 Annual Report on Accounts.pdf | 2 Nov 2021 |
| Details of encumbrancesFile: Changes in Encumbrances Report.pdf | 21 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Certificates of Engineer.pdf | 21 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf | 21 Aug 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 188 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SIDDHI GARIMA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHEMBUR6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 297 registered projects within 2 km.
Chandak Highscape City 1A
CHANDAK REALTORS PRIVATE LIMITED
CHANDAK HIGHSCAPE CITY 1B
CHANDAK REALTORS PRIVATE LIMITED
RUNWAL WOODS
Evie Holdings Private Limited and Adishakt
SKY ANNEX
Stans Buildtech Homes Private Limited
Raya
F. A. Builders & Developers LLP
Raya - Verdue
F. A. Builders & Developers LLP
See every Mumbai Suburban project, with the district possession charts
Builder: NHA INFRAPROJECTS PRIVATE LIMITED
NHA INFRAPROJECTS PRIVATE LIMITED has 1 registration on MahaRERA, including SIDDHI GARIMA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that SIDDHI GARIMA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SIDDHI GARIMA is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SIDDHI GARIMA?
The registered promoter entity is NHA INFRAPROJECTS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SIDDHI GARIMA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SIDDHI GARIMA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SIDDHI GARIMA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SIDDHI GARIMA?
The professionals named in the filing: Architect: M/s. VIVEK BHOLE ARCHITECTS PVT LTD; Architect: M/s. SUNIL AMBRE & ASSOCIATES.; Engineer: M/s. ASSOCIATED CONSULTANTS.; Chartered Accountant: M P KANGUTKAR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SIDDHI GARIMA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback