ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Raya - Verdue

Registered No litigation declared Residential / Group Housing project

Raya - Verdue

By F. A. Builders & Developers LLP

RG-MH-64200 · RERA PR1181012502128 · Last updated on MahaRERA portal: 25 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 26 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedmoved 26 months from the original
0 of 9Construction stages donefurthest along: Excavation, 0%
83 of 83Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 14 documents Report an error

Raya - Verdue is a Residential / Group Housing project by F. A. Builders & Developers LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as PR1181012502128 on 20 Jan 2026. Possession is promised by 31 Dec 2029. The completion date has moved by 26 months from the original filing. 0 of the 83 units on this registration are recorded sold or booked, and 0 of 9 construction stages are filed complete.

At a glance

Project

  • NameRaya - Verdue
  • TypeResidential / Group Housing
  • Location
    • R C Marg
    • Chembur East
    • Wadhavali
    • Kurla
    • Mumbai Suburban
    • 400074
  • Pincode400074
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1181012502128
  • ReraGenie IDRG-MH-64200

Builder

  • NameF. A. Builders & Developers LLP
  • Entity typeLimited Liability Partnership
  • LLPINABZ-9138
  • GSTIN27AABFF1795Q1ZT
  • PartnersDivakar Baliram Parab, Roswalt Realty Private Limited
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2026First promiseOct 2027Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Jan 2026
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 10 Oct 2027)
  • Buildings1 building record
  • Documents filed14 files

Current status

0%0 of 83 units booked
0.0%Work done, per cost certificate

Figures as on 25 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sale Building. Wing - D NA232381283

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 9 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Sale Building. Wing - D: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed79

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots79
Closed/Covered79

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,933 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Jan 2026

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI8133.06
Proposed, not sanctioned8,133 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPBB GOREGAON WEST,SHOP NO.11,BHOOMI CLASSIC CHS LTD,LINK RD,MALAD WEST,DIST.MUMBAI.MH 400064
Estimated costRs 50.64 cr
Work done0.0%
BuildingWingEstimatedIncurred
Sale Building. Wing - DNARs 49.62 cr-
-NARs 1.01 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRe Form Consultants
EngineerAbhijit V Phatarpekar
EngineerMohammed Mistry
Chartered AccountantN P Shetty & Co
PartnerRole in project
F. A. Builders & Developers LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA22042620687Oct 2027 → Dec 2029

Reason as filed by the promoterThe project was originally planned for a longer duration. The initially recorded end date was based on preliminary project planning and was inadvertently entered incorrectly during documentation. Upon review of the approved project schedule and timelines, it has been identified that the correct project duration extends up to 31-12-2029 Given the circumstances, we kindly request an extension until 31-12-2029, to complete the project and fulfil all regulatory requirements

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jan 2026
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed14

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Raya Verdue For FY 2025-26.pdf25 Jun 2026
Withdrawal Update Form 1File: Form 1 March 26.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1 March 26.pdf21 Apr 2026
Withdrawal Update Form 2File: Form 2 - Raya Verdue as on March 2026.pdf21 Apr 2026
Withdrawal Update Form 2File: Form 2 - Raya Verdue as on March 2026.pdf21 Apr 2026
Withdrawal Update Form 3File: Form 3 March 26.pdf21 Apr 2026
Withdrawal Update Form 3File: Form 3 March 26.pdf21 Apr 2026
Declaration and undertaking (Annexure A)File: Annexure A -Order 50.pdf16 Jan 2026
Layout approvalFile: Layout Plan Page - 1_ F A Builders.pdf16 Jan 2026
Building plan approvalFile: Building Plan Approval -Page 2.pdf15 Jan 2026
Building plan approvalFile: Buiding Plan Approval -Page 3_.pdf15 Jan 2026
Building plan approvalFile: Buiding Plan Approval Wing D -Page 10.pdf15 Jan 2026
Building plan approvalFile: Building Plan Approval Wing D -Page 11.pdf15 Jan 2026
Building plan approvalFile: Building Plan Approval -Section -Page 12.pdf15 Jan 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
RayaP51800079114Vadhavli, Chembur, Mumbai Suburban248Feb 2025OngoingDec 2029Not due yet

How this compares with Mumbai Suburban

0%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 26 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Raya - Verdue on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur East6,700+ in Mumbai Suburban

2 kmRaya - VerdueCompleted 72Lapsed / revoked 43Other 72Dot size: filed unitsN

Filed coordinates, straight-line distance. 187 registered projects within 2 km.

Builder: F. A. Builders & Developers LLP

F. A. Builders & Developers LLP has 2 registrations on MahaRERA, including Raya and Raya - Verdue. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Raya - Verdue is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Raya - Verdue?

The registered promoter entity is F. A. Builders & Developers LLP, a limited liability partnership as per the filing. Its LLPIN ABZ-9138 and GSTIN 27AABFF1795Q1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Raya - Verdue?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Raya - Verdue?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Raya - Verdue?

The professionals named in the filing: Architect: Re Form Consultants; Engineer: Abhijit V Phatarpekar; Engineer: Mohammed Mistry; Chartered Accountant: N P Shetty & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Raya - Verdue?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Raya - Verdue. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Raya - Verdue to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.