Home / Browse projects / Palghar, Maharashtra / Shriyan Gold
Shriyan Gold
RG-MH-29350 · RERA P99000028370 · Last updated on MahaRERA portal: 13 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shriyan Gold is a Residential / Group Housing project by Shriyan Engineering in Palghar, Maharashtra, registered with MahaRERA as P99000028370 on 22 Feb 2021. Possession was promised by 30 Jun 2025 and is now 16 months past that date.
At a glance
Project
- NameShriyan Gold
- TypeResidential / Group Housing
- Location
- Central Park
- Pandit Pada
- Makane
- Palghar
- 401102
- Pincode401102
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000028370
- ReraGenie IDRG-MH-29350
Builder
- NameShriyan Engineering
- Entity typePartnership
- PartnersPRASHANT SHRINIWAS KALANTRI, DHARMENDRA HASMUKHLAL MODI
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Feb 2021
- Promised completion30 Jun 2025
- Revised completionNone
- Buildings1 building record
- Documents filed29 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Shiryan Gold | NA | 5 | 5 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 13 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
Shiryan Gold: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Roshan Ravindra Patil |
| Engineer | Akshay Patil |
| Chartered Accountant | Vishwanath Pai |
| Chartered Accountant | Bhavesh Nagda |
| Partner | Role in project |
|---|---|
| Shriyan Engineering | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Feb 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Feb 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Feb 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Feb 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed29
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: WORKCOMPLETION15.pdf | 13 Apr 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: shriyangoldCHS.pdf | 13 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: UpdateAwing31032025.pdf | 13 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: updateBwing31032025.pdf | 13 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: shrreraupd31032024.pdf | 4 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: shriyanrera211023.pdf | 21 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1comprssed.pdf | 5 May 2023 |
| Disclosure of sold/ booked inventoryFile: shriyanupdate31032023.pdf | 4 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ShriyanGold_Form5_Mar21.pdf | 23 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ShriyanGold_Form5_Mar22.pdf | 23 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: shriyanupdatenov22.pdf | 26 Nov 2022 |
| OtherFile: shriyanupdatenov22.pdf | 26 Nov 2022 |
| Disclosure of sold/ booked inventoryFile: Update.pdf | 26 Aug 2021 |
| OtherFile: form B co promoter_compressed.pdf | 16 Feb 2021 |
| OtherFile: Document Detail.pdf | 16 Feb 2021 |
| PAN CardFile: shriyan_pancard-converted.pdf | 13 Feb 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: central_park_cc_compressed.pdf | 13 Feb 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: central_park_cc_1.pdf | 13 Feb 2021 |
| OtherFile: POA shriyan gold_compressed (1).pdf | 13 Feb 2021 |
| OtherFile: project shriyan gold.pdf | 13 Feb 2021 |
| Declaration in FORM BFile: affidavit shriyan gold-min.pdf | 4 Feb 2021 |
| Layout approvalFile: Layout Plan Best.pdf | 3 Feb 2021 |
| Building plan approvalFile: Layout Plan Best.pdf | 3 Feb 2021 |
| Copy of the legal title reportFile: Title_certificate lower version.pdf | 3 Feb 2021 |
| Details of encumbrancesFile: encumbrance certificate.pdf | 3 Feb 2021 |
| Copy of Layout Approval (in case of layout)File: Layout Plan Best.pdf | 3 Feb 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Layout Plan Best.pdf | 3 Feb 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202101 Shriyan Engineering Form 3.pdf | 3 Feb 2021 |
| Proforma of Allotment letterFile: Final_agreement.pdf | 3 Feb 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 29 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Shriyan Gold on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pandit Pada3,200+ in Palghar
Filed coordinates, straight-line distance. 46 registered projects within 2 km.
BLOSSOM AVENUE
DILIPKUMAR AMBALAL JAIN
RAJLAXXMI PARK
SAPHALE LAND DEVELOPERS LLP
STAR VIRATHAN CITY
STAR BUILDERS & DEVELOPERS
VIDHATA EMPIRE
K.M.WORLD
MITHILA COMPLEX
NAVAL RAMBAHADUR SINGH
PARIVAR COMPLEX BUILDING NO 1 AND 3
PARIVAR HOMES
See every Palghar project, with the district possession charts
Builder: Shriyan Engineering
Shriyan Engineering has 1 registration on MahaRERA, including Shriyan Gold. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that Shriyan Gold shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Shriyan Gold is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shriyan Gold?
The registered promoter entity is Shriyan Engineering, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shriyan Gold?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Shriyan Gold?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shriyan Gold?
The professionals named in the filing: Architect: Roshan Ravindra Patil; Engineer: Akshay Patil; Chartered Accountant: Vishwanath Pai; Chartered Accountant: Bhavesh Nagda. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shriyan Gold?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback