Home / Browse projects / Palghar, Maharashtra / MITHILA COMPLEX

Registered No litigation declared Residential / Group Housing project

MITHILA COMPLEX

By NAVAL RAMBAHADUR SINGH

RG-MH-04547 · RERA P99000022165 · Last updated on MahaRERA portal: 10 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 40 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 40 months from the original
20 of 33Construction stages doneacross 3 buildings; furthest along: Basement (if any), 0%
171 of 209Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 134 documents Report an error

MITHILA COMPLEX is a Residential / Group Housing project by NAVAL RAMBAHADUR SINGH in Palghar, Maharashtra, registered with MahaRERA as P99000022165 on 4 Sep 2019. Possession is promised by 31 Dec 2028. The completion date has moved by 40 months from the original filing. 38 of the 209 units on this registration are recorded sold or booked, and 20 of 33 construction stages are filed complete.

At a glance

Project

  • NameMITHILA COMPLEX
  • TypeResidential / Group Housing
  • Location
    • THANE PADA
    • KAPASE
    • Palghar
    • 401102
  • Pincode401102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000022165
  • ReraGenie IDRG-MH-04547

Builder

  • NameNAVAL RAMBAHADUR SINGH
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2019First promiseAug 2025Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Sep 2019
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 20 Aug 2025)
  • Buildings3 building records
  • Documents filed134 files

Current status

18%38 of 209 units booked
80.1%Work done, per cost certificate

Figures as on 10 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIVAM SHUBHAMNA10589089
AROHINA10560060
VIBHANA10560060

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 10 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 0%.

SHIVAM SHUBHAM82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
AROHI82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
VIBHA18%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Closed/Covered5
Open Space45
BuildingClosed/CoveredOpen SpaceTotal
SHIVAM SHUBHAM31518
AROHI11516
VIBHA11516

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,310 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
NAVAL SINGH KapasePalghar

Approvals and building plan

Sanctioning authorityDistrict Collector Office Palghar
Permissible FSI7066.9
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIRA ROAD
Estimated costRs 14.72 cr
Cost incurredRs 11.79 cr
Work done80.13%
BuildingWingEstimatedIncurred
SHIVAM SHUBHAMNARs 5.21 crRs 5.21 cr
AROHINARs 3.58 crRs 3.58 cr
VIBHANARs 3.58 crRs 1.08 cr
-NARs 2.34 crRs 1.92 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRoshan Rajendra Patil
EngineerMahesh Kumar
EngineerFAROOQ NAGORRI
Chartered AccountantASHOK JHA & ASSOCIATES
Chartered AccountantR P S K AND ASSOCIATES
Chartered AccountantDNYANESHWAR BALU HASE
PartnerRole in project
NAVAL RAMBAHADUR SINGH-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA26082502450Aug 2025 → Dec 2028

Reason as filed by the promoterDELAYED IN PERMISSION FROM PLANNING AUTHORITY

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Aug 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Aug 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed134

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 134 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q4 FY 25 26.pdf10 May 2026
Withdrawal Update Form 2File: Form 2 Q4 FY 25 26.pdf10 May 2026
Withdrawal Update Form 3File: Form 3 Q4 signed.pdf10 May 2026
Withdrawal Update Form 1File: FORM 1.pdf19 Jan 2026
Withdrawal Update Form 2File: FORM 2 25.pdf19 Jan 2026
Withdrawal Update Form 3File: Mithila COMPLEX q3 form3.pdf19 Jan 2026
Form 2A (FY 2025-2026)File: Form 2A 2026.pdf29 Dec 2025
Withdrawal Update Form 1File: FORM 1.pdf16 Dec 2025
Withdrawal Update Form 2File: FORM 2 25.pdf16 Dec 2025
Withdrawal Update Form 3File: Mithila Construction Q2 FY 24-25 Form 3 Signed.pdf16 Dec 2025
Withdrawal Update Form 1File: FORM 1.pdf10 Nov 2025
Withdrawal Update Form 2File: FORM 2 25.pdf10 Nov 2025
Withdrawal Update Form 3File: Mithila Construction Q2 FY 24-25 Form 3 Signed.pdf10 Nov 2025
Form 1File: 1 Form 1 Q2 FY 2019 20.pdf20 Aug 2025
Form 2File: 2 Form 2 Q2 FY 2019 20.pdf20 Aug 2025
Form 3File: 3 Form 3 FY 2019 20 Q2.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2019-20 Q2.pdf20 Aug 2025
Form 1File: 1 Form 1 Q3 FY 2019 20.pdf20 Aug 2025
Form 2File: 2 Form 2 Q3 FY 2019 20.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2019 20 Q3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2019 20 Q3.pdf20 Aug 2025
Form 1File: 1 Form 1 Q4 FY 2019 20.pdf20 Aug 2025
Form 2File: 2 Form 2 Q4 FY 2019 20.pdf20 Aug 2025
Form 3File: 3 Form 3 FY 2019 20 Q4.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2019 20 Q4.pdf20 Aug 2025
Form 1File: 1 Form 1 Q1 FY 2020 21.pdf20 Aug 2025
Form 2File: 2 Form 2 Q1 FY 2020 21.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2020 21 Q1.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2020 21 Q1.pdf20 Aug 2025
Form 1File: 1 Form 1 Q2 FY 2020 21.pdf20 Aug 2025
Form 2File: 2 Form 2 Q2 FY 2020 21.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2020 21 Q2.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2020 21 Q2.pdf20 Aug 2025
Form 1File: 1 Form 1 Q4 FY 2020 21.pdf20 Aug 2025
Form 2File: 2 Form 2 Q4 FY 2020 21.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2020 21 Q4.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2020 21 Q4.pdf20 Aug 2025
Form 1File: 1 Form 1 Q1 FY 2021 22.pdf20 Aug 2025
Form 2File: 2 Form 2 Q1 FY 2021 22.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2021 22 Q1.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2021 22 Q1.pdf20 Aug 2025
Form 1File: 1 Form 1 Q2 FY 2021 22.pdf20 Aug 2025
Form 2File: 2 Form 2 Q2 FY 2021 22.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2021 22 Q2.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2021 22 Q2.pdf20 Aug 2025
Form 1File: 1 Form 1 Q3 FY 2021 22.pdf20 Aug 2025
Form 2File: 2 Form 2 Q3 FY 2021 22.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2021 22 Q3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2021 22 Q3.pdf20 Aug 2025
Form 1File: 1 Form 1 Q4 FY 2021 22.pdf20 Aug 2025
Form 2File: 2 Form 2 Q4 FY 2021 22.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2021 22 Q4.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2021 22 Q4.pdf20 Aug 2025
Form 1File: 1 Form 1 Q1 FY 2022 23.pdf20 Aug 2025
Form 2File: 2 Form 2 Q1 FY 2022 23.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2022 23 Q1.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2022 23 Q1.pdf20 Aug 2025
Form 1File: 1 Form 1 Q3 FY 2022 23.pdf20 Aug 2025
Form 2File: 2 Form 2 Q3 FY 2022 23.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2022 23 Q3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2022 23 Q3.pdf20 Aug 2025
Form 1File: 1 Form 1 Q4 FY 2022 23.pdf20 Aug 2025
Form 2File: 2 Form 2 Q4 FY 2022 23.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2022 23 Q4.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2022 23 Q4.pdf20 Aug 2025
Form 1File: 1 Form 1 Q1 FY 2023 24.pdf20 Aug 2025
Form 2File: 2 Form 2 Q1 FY 2023 24.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2023 24 Q1.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2023 24 Q1.pdf20 Aug 2025
Form 1File: 1 Form 1 Q2 FY 2023 24.pdf20 Aug 2025
Form 2File: 2 Form 2 Q2 FY 2023 24.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2023 24 Q2.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2023 24 Q2.pdf20 Aug 2025
Form 1File: 1 Form 1 Q3 FY 2023 24.pdf20 Aug 2025
Form 2File: 2 Form 2 Q3 FY 2023 24.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2023 24 Q3.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Disc FY 2023 24 Q3.pdf20 Aug 2025
Form 1File: 1 Form 1 Q4 FY 2023 24.pdf20 Aug 2025
Form 2File: 2 Form 2 Q4 FY 2023 24.pdf20 Aug 2025
Form 3File: 3 Form3 FY 2023 24 Q4.pdf20 Aug 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MITHILA 1 CONSTRUCTIONMITHILA DHAM OPPOSITE NINE STAR COMPLEX VILLAGE MAKANE PANDIT PADA SURVEY NO 246-2-1 SAPHALE WEST PALGHAR 4011021CompletedMar 2020Late, Mar 2021

How this compares with Palghar

18%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 40 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MITHILA COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KAPASE3,200+ in Palghar

2 kmMITHILA COMPLEXCompleted 21Lapsed / revoked 6Other 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 53 registered projects within 2 km.

Builder: NAVAL RAMBAHADUR SINGH

NAVAL RAMBAHADUR SINGH has 2 registrations on MahaRERA, including MITHILA DHAM and MITHILA COMPLEX. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if MITHILA COMPLEX is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MITHILA COMPLEX?

The registered promoter entity is NAVAL RAMBAHADUR SINGH, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MITHILA COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MITHILA COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MITHILA COMPLEX?

The professionals named in the filing: Architect: Roshan Rajendra Patil; Engineer: Mahesh Kumar; Engineer: FAROOQ NAGORRI; Chartered Accountant: ASHOK JHA & ASSOCIATES; Chartered Accountant: R P S K AND ASSOCIATES; Chartered Accountant: DNYANESHWAR BALU HASE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MITHILA COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MITHILA COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MITHILA COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.