Registered No litigation declared Residential / Group Housing project

SHRI URJA NEST

By ASHAPURA INFRA

RG-MH-77392 · RERA P51600056483 · Last updated on MahaRERA portal: 12 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Internal walls, 50%
15 of 24Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

SHRI URJA NEST is a Residential / Group Housing project by ASHAPURA INFRA in Nashik, Maharashtra, registered with MahaRERA as P51600056483 on 5 Jun 2024. Possession is promised by 31 Mar 2027. 9 of the 24 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHRI URJA NEST
  • TypeResidential / Group Housing
  • Location
    • JATRA NANDUR LINK ROAD
    • ICHHAMANI NAGAR BEHIND GARDEN COUNTY
    • Nashik (M Corp.)
    • Nashik
    • 422002
  • Pincode422002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600056483
  • ReraGenie IDRG-MH-77392

Builder

  • NameASHAPURA INFRA
  • Entity typePartnership
  • PartnersHARESH SHANTILAL RAMANI, GIRISH NARSIH MAWANI, KALPESH NARSIH MAWANI, RONAK JAYANTILAL MAVANI
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJun 2024PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Jun 2024
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed54 files

Current status

38%9 of 24 units booked
13.9%Work done, per cost certificate

Figures as on 12 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRI URJA NESTNA6624024

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.

SHRI URJA NEST: 45% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 12 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed74

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots74
Closed/Covered74

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area700 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Jul 2025

Approvals and building plan

Sanctioning authorityNASHIK MUNICIPAL CORPORATION
Permissible FSI2225.16
Proposed, not sanctioned2,225 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK LTD, SHOP NO 1AND2, PRITAM COMPLEX, PLOT NO 09, ADGAON RD, MUMBAI AGRA ROAD, NASHIK 422003
Estimated costRs 4.96 cr
Cost incurredRs 69.17 lakh
Work done13.94%
BuildingWingEstimatedIncurred
SHRI URJA NESTNARs 4.82 crRs 69.17 lakh
-NARs 13.82 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSURESH N PATEL
EngineerSUNIL PATEL
EngineerHITESH JAYANTILAL MAVANI
Chartered AccountantSACHIN PATEL
Chartered AccountantDILIP SHANTILAL PATEL
PartnerRole in project
ASHAPURA INFRA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf12 Jul 2026
Withdrawal Update Form 2File: FORM 2.pdf12 Jul 2026
Withdrawal Update Form 3File: SELF CLARIFICATION Q1 FY 24-25.pdf12 Jul 2026
Withdrawal Update Form 1File: FORM 1.pdf18 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf18 Apr 2026
Withdrawal Update Form 3File: SELF CLARIFICATION Q1 FY 24-25.pdf18 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A (1).pdf18 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf16 Jan 2026
Withdrawal Update Form 2File: FORM 2.pdf16 Jan 2026
Withdrawal Update Form 3File: SELF CLARIFICATION Q1 FY 24-25.pdf16 Jan 2026
Withdrawal Update Form 1File: FORM 1.pdf15 Oct 2025
Withdrawal Update Form 2File: FORM 2.pdf15 Oct 2025
Withdrawal Update Form 3File: SELF CLARIFICATION Q1 FY 24-25.pdf15 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5 ASHAPURA INFRA FY 24-25.pdf23 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SELF CLARIFICATION Q4 FY 24-25.pdf8 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSER OF INVENTORY MARCH 25.pdf8 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SELF CLARIFICATION Q3 FY 24-25.pdf25 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSER OF INVENTORY DEC 24.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SELF CLARIFICATION Q2 FY 24-25.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSER OF INVENTORY SEP 24.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSER OF INVENTORY JUNE 24.pdf9 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SELF CLARIFICATION Q1 FY 24-25.pdf9 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: Application_form_42313_419_165658_3_TLoF3Sign (1).pdf28 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Plinth Intimation Report-2352024.pdf28 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC VALIDATION.pdf28 May 2024
Declaration about Commencement CertificateFile: FORMAT D RERA - DONE.pdf21 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: UNDERTAKING OF SEPERATE BANK AC - DONE.pdf21 May 2024
Building plan approvalFile: BUILDING PLAN NEW.pdf29 Apr 2024
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATE FINANCE - DONE.pdf29 Apr 2024
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATE LEGAL.pdf29 Apr 2024
Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATE FINANCE - DONE.pdf29 Apr 2024
Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATE LEGAL.pdf29 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN NEW.pdf29 Apr 2024
Declaration in FORM BFile: FORM B.pdf29 Apr 2024
CERSAI detailsFile: CERSAI.pdf29 Apr 2024
CERSAI detailsFile: CERSAI_Search_Report_200305139205_For_Asset_Based_Search_29_04_2024_12_31_58_922.pdf29 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.PDF29 Apr 2024
Deviation Report with respect to Allotment letterFile: UNDERTAKING ALLOTMENT LETTER - DONE.pdf29 Apr 2024
Deviation Report with respect to model copy of AgreementFile: UNDERTAKING AGREEMENT TO SALE - DONE.pdf29 Apr 2024
Home Buyer /Allottee Grievance Redressal CellFile: GRIEVENCE REDRESSAL - DONE.pdf29 Apr 2024
Other - TechnicalFile: ORDER NO 50 - DONE.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf27 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 GIRISH M.pdf27 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 HARESH R.pdf27 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 KALPESH M.pdf27 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Order No 39 RONAK M.pdf27 Apr 2024
Layout approvalFile: LAY OUT.pdf25 Apr 2024
Copy of Layout Approval (in case of layout)File: LAY OUT.pdf25 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf25 Apr 2024
PAN CardFile: ashapura infra pan card.PDF29 Jan 2024
Copy of the legal title reportFile: Title search report_compressed.pdf29 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf29 Jan 2024
Proforma of Agreement for saleFile: Draft-Agreement to Sale.pdf29 Jan 2024
Proforma of Allotment letterFile: Shri Urja Nest-Allotment Letter.pdf29 Jan 2024

How this compares with Nashik

38%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHRI URJA NEST on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ICHHAMANI NAGAR BEHIND GARDEN COUNTY4,100+ in Nashik

2 kmSHRI URJA NESTCompleted 9Lapsed / revoked 3Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: ASHAPURA INFRA

ASHAPURA INFRA has 2 registrations on MahaRERA, including SHREE URJA and SHRI URJA NEST. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SHRI URJA NEST is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRI URJA NEST?

The registered promoter entity is ASHAPURA INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRI URJA NEST?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRI URJA NEST?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRI URJA NEST?

The professionals named in the filing: Architect: SURESH N PATEL; Engineer: SUNIL PATEL; Engineer: HITESH JAYANTILAL MAVANI; Chartered Accountant: SACHIN PATEL; Chartered Accountant: DILIP SHANTILAL PATEL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRI URJA NEST?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRI URJA NEST. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRI URJA NEST to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.