Home / Browse projects / Nashik, Maharashtra / THE CHOUPAAL

Registered No litigation declared Commercial project

THE CHOUPAAL

By KALANTRI AND BANG PROPERTIES

RG-MH-15081 · RERA P51600034715 · Last updated on MahaRERA portal: 22 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 22.00 crore secured on the land, in favour of THE SARASWAT CO OP BANK LTD

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 12 months from the original
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 90%
114 of 185Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 141 documents Report an error

THE CHOUPAAL is a Commercial project by KALANTRI AND BANG PROPERTIES in Nashik, Maharashtra, registered with MahaRERA as P51600034715 on 20 Apr 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 12 months from the original filing. 71 of the 185 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameTHE CHOUPAAL
  • TypeCommercial
  • Location
    • AHILYABAI HOLKAR MARG
    • TIDKE COLONY
    • NASHIK
    • Nashik
    • 422002
  • Pincode422002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600034715
  • ReraGenie IDRG-MH-15081

Builder

  • NameKALANTRI AND BANG PROPERTIES
  • Entity typePartnership
  • PartnersASHOK BANKATLAL BANG, RAMESHWAR BADRINARAYAN KALANTRI, RAMESHWAR BADRINARAYAN KALANTRI HUF, ARATI ASHOK BANG, MANGALA RAMESHWAR KALANTRI

Key dates

this monthRegisteredApr 2022First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Apr 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed141 files

Current status

38%71 of 185 units booked
65.4%Work done, per cost certificate

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CHOUPAULNA1080185185

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.

CHOUPAUL: 80% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1065

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,065
Closed/Covered1,065

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,140 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofTHE SARASWAT CO OP BANK LTD
Secured amountRs 22.00 crore
CERSAI search filedYes
Declared on4 Aug 2025

Approvals and building plan

Sanctioning authorityNASHIK MUNICIPAL CORPORTATION
Permissible FSI21531.18
Proposed, not sanctioned21,531 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHARANPUR ROAD
Estimated costRs 70.00 cr
Cost incurredRs 45.80 cr
Work done65.43%
BuildingWingEstimatedIncurred
CHOUPAULNARs 68.55 crRs 45.00 cr
-NARs 1.45 crRs 80.00 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR SANJAY M PATIL
EngineerJagruti Divakar Patil
EngineerSanjay Sitaram Patil
EngineerRAJENDRA BELE
Chartered AccountantAPURVA SANKET KASLIWAL
Chartered AccountantVINOD HIRALAL JAJOO
PartnerRole in project
KALANTRI AND BANG PROPERTIES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA28012619611Mar 2026 → Mar 2027

Reason as filed by the promoterDuring the relevant construction period, the project site experienced an abnormally early onset of monsoon commencing from April/May 2025, followed by prolonged and intense rainfall. Such unusual weather conditions severely affected construction activities, particularly excavation, RCC works, masonry, plastering and other external and weather-dependent works, which could not be carried out safely or efficiently. The early and prolonged monsoon conditions resulted in a significant shortage of labour, as frequent and continuous rainfall caused irregular attendance and reduced availability of the

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Jan 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed141

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 141 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf22 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf22 Jun 2026
Withdrawal Update Form 3File: Form 3_merged.pdf22 Jun 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf28 Jan 2026
Withdrawal Update Form 2File: FORM-2 ENGINEERS CERTIFICATE.pdf28 Jan 2026
Withdrawal Update Form 3File: FORM 3.pdf28 Jan 2026
Withdrawal Update Form 1File: ARCHITECTu0027S CERTIFICATE.pdf22 Nov 2025
Withdrawal Update Form 2File: Engineeru0027s Certificate 1.pdf22 Nov 2025
Withdrawal Update Form 3File: Upload Withdrawal Application Form3.pdf22 Nov 2025
Form 2A (FY 2023-2024)File: 2024.pdf30 Sep 2025
Form 2A (FY 2024-2025)File: 2025.pdf30 Sep 2025
Form 5 (FY 2023-2024)File: Form 5.pdf30 Sep 2025
Form 5 (FY 2024-2025)File: Form 5 - 2024-2025.pdf30 Sep 2025
Form 5 (FY 2022-2023)File: Form 5 (Upload) 2022-2023.pdf30 Sep 2025
Form 2A (FY 2022-2023)File: 2023.pdf31 Aug 2025
Withdrawal Update Form 1File: From 1 Architectu0027s Certificate.pdf27 Aug 2025
Withdrawal Update Form 2File: ENGINEERS CERTIFICATE.pdf27 Aug 2025
Withdrawal Update Form 3File: Form-3.pdf27 Aug 2025
Form 1File: RERA Form_1_Architect Cert.pdf6 Aug 2025
Form 2File: Engineer Certificate_Q123-24.pdf6 Aug 2025
Form 3File: Rera-3_compressed.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: UPLOAD Q1 2023-2024 SOLD BOOKED INVENTORY.pdf6 Aug 2025
Form 1File: ARCHITECTURE CERTIFICATE Upto SEPT 2023.pdf6 Aug 2025
Form 2File: ENGG CERTIFICATE UPTO SEPT 2023.pdf6 Aug 2025
Form 3File: RERA CA Certificate Upto SEPT 2023.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: UPLOAD Q2 2023- 2024 SOLD BOOKED INVENTORY.pdf6 Aug 2025
Form 1File: Form 1.pdf6 Aug 2025
Form 2File: Form 2.pdf6 Aug 2025
Form 3File: Form 3 - Chartered Accountant.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: UPLOAD Q3 2023- 2024 SOLD BOOKED INVENTORY.pdf6 Aug 2025
Form 1File: Annex-1.pdf6 Aug 2025
Form 2File: Form 2.pdf6 Aug 2025
Form 3File: Form 3.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: UPLOAD Q4 2023- 2024 SOLD BOOKED INVENTORY.pdf6 Aug 2025
Form 1File: Form 1 Architech Certificate.pdf6 Aug 2025
Form 2File: Form 2 Engineer Certificate.pdf6 Aug 2025
Form 3File: Form 3 CA Certificate.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: UPLOAD Q1 2024- 2025 SOLD BOOKED INVENTORY.pdf6 Aug 2025
Form 1File: Form 1.pdf6 Aug 2025
Form 2File: Form - 2.pdf6 Aug 2025
Form 3File: Form 3 CHARTERED ACCOUNTANTS CERTIFICATE - Q2_compressed (1).pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: UPLOAD Q2 2024- 2025 SOLD BOOKED INVENTORY.pdf6 Aug 2025
Form 1File: Architect's Certificate 14-1-25.pdf6 Aug 2025
Form 2File: Engineer Certificate 14-1-25.pdf6 Aug 2025
Form 3File: Form 3_compressed.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: UPLOAD Q3 2024- 2025 SOLD BOOKED INVENTORY.pdf6 Aug 2025
Form 1File: Annexure A Form 1.pdf6 Aug 2025
Form 2File: Form - 2.pdf6 Aug 2025
Form 3File: Form 3 -RERA_11zon.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: UPLOAD Q4 2024- 2025 SOLD BOOKED INVENTORY.pdf6 Aug 2025
Form 1File: Architect Certificate.pdf4 Aug 2025
Form 2File: RERA_ENGINEER CERTIFICATE.pdf4 Aug 2025
Form 3File: FORM 3_compressed.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: POSITION OF UNSOLD INVENTORY.pdf4 Aug 2025
Form 1File: FORM 1 Architect Certificate.pdf4 Aug 2025
Form 2File: FORM 2 RERA_ENGINEER CERTIFICATE.pdf4 Aug 2025
Form 3File: FORM 3_compressed.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: POSITION OF UNSOLD INVENTORY.pdf4 Aug 2025
Form 1File: Architect's Certificate.pdf4 Aug 2025
Form 2File: RERA_Engineer certificate.pdf4 Aug 2025
Form 3File: Form 3_compressed.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: POSITION OF UNSOLD INVENTORY.pdf4 Aug 2025
Form 1File: RERA Architect certificate.pdf4 Aug 2025
Form 2File: Engineers Cert_RERA Q4 22-23.pdf4 Aug 2025
Form 3File: CA Certificate_RERA - Upload.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: POSITION OF UNSOLD INVENTORY.pdf4 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A Form 1.pdf4 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 -RERA_11zon.pdf4 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2.pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate 14-1-25.pdf18 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf18 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 14-1-25.pdf18 Jan 2025
Copy of the legal title reportFile: Cersai_merged.pdf2 Jan 2025
Details of encumbrancesFile: E Certificate.pdf2 Jan 2025
Details of encumbrances concerned to FinanceFile: 04 Annex-04- The Saraswat Co Op Bank Ltd Loan Sanction Letter.pdf2 Jan 2025
CERSAI detailsFile: Cersai.pdf2 Jan 2025
Details of encumbrances concerned to LegalFile: 04 Annex-04- The Saraswat Co Op Bank Ltd Loan Sanction Letter.pdf2 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf15 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CHARTERED ACCOUNTANTS CERTIFICATE - Q2_compressed (1).pdf15 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2.pdf15 Nov 2024

How this compares with Nashik

38%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 12 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE CHOUPAAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TIDKE COLONY, NASHIK4,100+ in Nashik

2 kmTHE CHOUPAALCompleted 183Lapsed / revoked 40Other 105Dot size: filed unitsN

Filed coordinates, straight-line distance. 328 registered projects within 2 km.

Builder: KALANTRI AND BANG PROPERTIES

KALANTRI AND BANG PROPERTIES has 1 registration on MahaRERA, including THE CHOUPAAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if THE CHOUPAAL is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE CHOUPAAL?

The registered promoter entity is KALANTRI AND BANG PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE CHOUPAAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THE CHOUPAAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE CHOUPAAL?

The professionals named in the filing: Architect: AR SANJAY M PATIL; Engineer: Jagruti Divakar Patil; Engineer: Sanjay Sitaram Patil; Engineer: RAJENDRA BELE; Chartered Accountant: APURVA SANKET KASLIWAL; Chartered Accountant: VINOD HIRALAL JAJOO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE CHOUPAAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE CHOUPAAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE CHOUPAAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.