Home / Browse projects / Mumbai Suburban, Maharashtra / Shri Parrsssva Eleganza

Registration lapsed No litigation declared Residential / Group Housing project

Shri Parrsssva Eleganza

By Sanghvi Constructions

RG-MH-25891 · RERA P51800009496 · Last updated on MahaRERA portal: 26 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 67 months past the filed date
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2021Possession promised67 months past this date
7 of 11Construction stages donefurthest along: Internal walls, 98%
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

Shri Parrsssva Eleganza is a Residential / Group Housing project by Sanghvi Constructions in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009496 on 22 Aug 2017. Possession was promised by 30 Mar 2021 and is now 67 months past that date. The completion date has moved by 30 months from the original filing.

At a glance

Project

  • NameShri Parrsssva Eleganza
  • TypeResidential / Group Housing
  • Location
    • Jivdaya Lane
    • Ghatkopker West
    • Kurla
    • Mumbai Suburban
    • 400086
  • Pincode400086
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009496
  • ReraGenie IDRG-MH-25891

Builder

  • NameSanghvi Constructions
  • Entity typePartnership
  • PartnerRamesh S Sanghvi
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

67 months past promisethis monthRegisteredAug 2017First promiseSep 2018Revised toMar 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion30 Mar 2021
  • Revised completionRevised to 30 Mar 2021 (originally 30 Sep 2018)
  • Buildings1 building record
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shri Parrsssva EleganzaNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 98%.

Shri Parrsssva Eleganza: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.98%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed85

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots85
Closed/Covered85

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,269 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5504.2
Proposed, not sanctioned5,199 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchManekji Wadia Bldg, Ground Floor, Nanik Motwani Marg, Fort, Mumbai, Maharashtra

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSaachi Associates
EngineerShantilal Jain
PartnerRole in project
Sanghvi Constructions-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800000827Sep 2018 → Sep 2020

Reason as filed by the promoterWe are proposing amendment in plan for 10th floor, hence for the purpose of obtaining approval and to commence work we require further time extension.

EXT51800005638Sep 2018 → Sep 2020

Reason as filed by the promoterThe project is having further proposed FSI to be consumed, so the firm intend to build further units in the project. Due to final formalities with BMC, we need further extension of time to finish remaining one upper floor and hence a further extension is sought. We require a further 12 months period to complete the project

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Eleganza 31-03-2024.pdf26 Feb 2025
Disclosure of sold/ booked inventoryFile: Eleganza 31-12-2024.pdf26 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form -1.pdf9 Jan 2025
Certificates of CA (Form 3)File: Form-3.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf9 Jan 2025
CERSAI detailsFile: Declaration Cersai.pdf9 Jan 2025
Deviation Report with respect to Allotment letterFile: No Deviation Report allotment letter.pdf9 Jan 2025
Deviation Report with respect to model copy of AgreementFile: No Deviation Report Agreement for Sale.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22.pdf9 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure - A.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf9 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5 2022-23.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf9 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 2023-24.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory(Eleganza).pdf5 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A-.pdf3 Apr 2023
Details of encumbrances concerned to FinanceFile: Legal Encumbrances.pdf27 Mar 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf27 Mar 2023
Declaration about Commencement CertificateFile: Declaration CC.pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5(2019).pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 (2020).pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 (2021).pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (2022).pdf27 Mar 2023
Certificates of CA (Form 5)File: Sanghvi Counstruction- Form 5.pdf19 Nov 2018
OtherFile: OC 1st TO 4th.pdf25 Oct 2018
OtherFile: Approval_Letter_19_9_18.pdf25 Oct 2018
OtherFile: Approved plan_19_9_18 3.pdf25 Oct 2018
PAN CardFile: pan.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineer SC.pdf29 Jul 2017
Certificates of CA (Form 3)File: Form-3 SC CA.pdf29 Jul 2017
Building plan approvalFile: IOD0003.pdf28 Jul 2017
Layout approvalFile: Ground Floor Plan.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate0001.pdf28 Jul 2017
Details of encumbrancesFile: Index-IIEncumbrance.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: Ground Floor Plan.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD0003.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC0001.pdf28 Jul 2017
Declaration in FORM BFile: FORM B (Eleganza).pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Architect Certificate - ghatkopar.pdf28 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT AND AGREEMENT FOR SALE- SHRI PARRSSSVA ELEGANZA- PDF.pdf28 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 30 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shri Parrsssva Eleganza on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghatkopker West6,700+ in Mumbai Suburban

2 kmShri Parrsssva EleganzaCompleted 115Lapsed / revoked 65Other 112Dot size: filed unitsN

Filed coordinates, straight-line distance. 292 registered projects within 2 km.

Builder: Sanghvi Constructions

Sanghvi Constructions has 2 registrations on MahaRERA, including Shri Parrsssva Eleganza and Sanghvi Parsssva Jivdaya. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Shri Parrsssva Eleganza shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shri Parrsssva Eleganza is delayed beyond 30 Mar 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shri Parrsssva Eleganza?

The registered promoter entity is Sanghvi Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shri Parrsssva Eleganza?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shri Parrsssva Eleganza?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shri Parrsssva Eleganza?

The professionals named in the filing: Architect: Saachi Associates; Engineer: Shantilal Jain. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shri Parrsssva Eleganza?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shri Parrsssva Eleganza. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shri Parrsssva Eleganza to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.