Home / Browse projects / Raigarh, Maharashtra / SHRI HIMGIRI

Completed No litigation declared Others project

SHRI HIMGIRI

By PYRAMID DEVELOPERS

RG-MH-73865 · RERA P52000012130 · Last updated on MahaRERA portal: 10 May 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 52 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Sep 2024Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Internal walls, 95%
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

SHRI HIMGIRI is a Others project by PYRAMID DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000012130 on 1 Sep 2017. The registration is recorded completed; possession was promised by 30 Sep 2024. The completion date has moved by 52 months from the original filing.

At a glance

Project

  • NameSHRI HIMGIRI
  • TypeOthers
  • Location
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000012130
  • ReraGenie IDRG-MH-73865

Builder

  • NamePYRAMID DEVELOPERS
  • Entity typePartnership
  • PartnersPRAKASH PARKAR, PRANAB PANGAM
  • Other registrations6 more →
  • Completed4 of 7
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1

Key dates

this monthRegisteredSep 2017First promiseMay 2020Revised toSep 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Sep 2017
  • Promised completion30 Sep 2024
  • Revised completionRevised to 30 Sep 2024 (originally 30 May 2020)
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRI HIMGIRINA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

SHRI HIMGIRI: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 10 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes95%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered1
Open Space3

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area535 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHRI HIMGIRI CO OP HOUSING SOCIETY LIMITEDPanvelRaigarh

Approvals and building plan

Permissible FSI662.0
Proposed, not sanctioned662 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch9TH FLOOR NEHRU CENTRE DISCOVERY OF INDIA BUILDING DR ANNIE BESANT ROAD WORLI MUMBAI 400018

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMADHURA BHISE
Chartered AccountantRutuja Narsingh & Associates
PartnerRole in project
PYRAMID DEVELOPERS-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000012521May 2020 → May 2023

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 62.5 % allottees for purpose of extension of RERA registration period of the said project.

EXT52000009360May 2020 → Nov 2021

Reason as filed by the promoterDue to covid and delay in the implementations of UDCPR, the project have got delayed. Since, we have to register the agreement for sale before 31st March 2021 to enable the buyers to get the benefit of stamp duty reduction, we urge you to kindly accept our application and extend the project till 30th November 2021 as soon as possible.

EXT52000001879May 2020 → May 2020

Reason as filed by the promoterThis application is in regards to the requirement for the extension of the above mentioned project for the period of 12 months (One Year). The work has got delayed majorly because of the delay of the MMR region DCPR for the Panvel Municipal Corporation. Such delay in the government policies have resulted in the delay in the further permission of the project. The project has been completed 90% throughout. We would also like to add up that, there is only 1 inventory been allotted and the allottee is aware about the problem being faced by us due to the delay in the government policy. Also, we her

EXT52000017298May 2020 → Oct 2023

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 61.54% allottees for purpose of extension of RERA registration period of the said project.

EXT52000019724May 2020 → Sep 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 80% allottees for purpose of extension of RERA registration period of the said project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: rera copy final (1).pdf10 May 2024
Disclosure of sold/ booked inventoryFile: rera copy final (1) (1).pdf10 May 2024
Declaration about Commencement CertificateFile: Format D.pdf3 May 2024
Declaration in FORM BFile: Shri Himgiri -Form B (1).pdf3 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate for Himgiri Extension.pdf3 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: A2DB9274-8960-4E62-A1C8-2F4659AEA46B_11zon.pdf3 May 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf3 May 2024
CERSAI detailsFile: Declaration of CERSAI.pdf3 May 2024
Certificates of CA (Form 3)File: himgiri ca certification_11zon.pdf3 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf3 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf3 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Himgiri (2022-2023).pdf25 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022-23.pdf24 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect’s Certificate.pdf22 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A 21-22.pdf19 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23 (2).pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate March 2018_4_11zon.pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate March 2019_5_11zon.pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate March 2020_6_11zon.pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate March 2021_7_11zon.pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate Dec 2021_1_11zon.pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate March 2022_8_11zon.pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate June 2022_3_11zon.pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate Sept 2022_10_11zon.pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate Dec 2022_2_11zon.pdf19 Aug 2023
Certificates of CA (Form 3)File: CA Certificate March 2023_9_11zon.pdf19 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (31-3-2018).pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (31-3-2019)_compressed.pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (31-3-2020).pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (31-3-2021).pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (31-12-2021).pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (31-3-2022).pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (30-6-2022).pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (30-9-2022).pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 ( 31-12-2022)_compressed.pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 (31-3-2023).pdf18 Aug 2023
Annual Audit Report of Statutory CA (Form 5)File: Form 5 (2017-2018).pdf18 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 (2018-2019).pdf18 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 (2019-2020).pdf18 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 (2020-2021).pdf18 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (2021-2022).pdf18 Aug 2023
Disclosure of sold/ booked inventoryFile: Pyramid Developers form 29 (Himgiri).pdf5 Aug 2023
Declaration in FORM BFile: Form B_11zon.pdf3 Aug 2023
Declaration about Commencement CertificateFile: Format D.pdf16 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-2020.pdf16 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf16 Sep 2022
Disclosure of sold/ booked inventoryFile: 29 Himgiri.pdf16 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 18 19 Shri Himgiri.pdf16 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 19 20 Shri Himgiri.pdf16 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20 21 Shri Himgiri.pdf16 Sep 2022
Annual Audit Report of Statutory CA (Form 5)File: Form 5 Pyramid Developers.pdf21 Oct 2019
Building plan approvalFile: imagetopdf (10).pdf31 Jul 2017
Layout approvalFile: imagetopdf (10).pdf31 Jul 2017
PAN CardFile: imagetopdf.pdf31 Jul 2017
Copy of the legal title reportFile: NO.pdf31 Jul 2017
Details of encumbrancesFile: NO.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: imagetopdf (10).pdf31 Jul 2017
Building Plan Approval (IOD)File: imagetopdf (10).pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: imagetopdf (4).pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: imagetopdf (5).pdf31 Jul 2017
Declaration in FORM BFile: form b declaration.pdf31 Jul 2017
Declaration in FORM BFile: form b declaration1.pdf31 Jul 2017
Declaration in FORM BFile: form b declaration2.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: imagetopdf (1).pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: imagetopdf (2).pdf31 Jul 2017
Certificates of CA (Form 3)File: imagetopdf (6).pdf31 Jul 2017
Certificates of CA (Form 3)File: imagetopdf (9).pdf31 Jul 2017
Proforma of Allotment letterFile: imagetopdf (16).pdf31 Jul 2017
Proforma of Allotment letterFile: imagetopdf (17).pdf31 Jul 2017
Certificates of Architect (Form 4)File: imagetopdf (1).pdf31 Jul 2017

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 52 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHRI HIMGIRI on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Panvel5,900+ in Raigarh

2 kmSHRI HIMGIRICompleted 211Lapsed / revoked 57Other 134Dot size: filed unitsN

Filed coordinates, straight-line distance. 402 registered projects within 2 km.

Builder: PYRAMID DEVELOPERS

Pyramid Developers has 7 registrations on MahaRERA, including The Nook Phase 1 and 81 AUREATE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if SHRI HIMGIRI is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRI HIMGIRI?

The registered promoter entity is PYRAMID DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRI HIMGIRI?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRI HIMGIRI?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRI HIMGIRI?

The professionals named in the filing: Architect: MADHURA BHISE; Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRI HIMGIRI?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRI HIMGIRI. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRI HIMGIRI to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.