SHRI DEVI KRIPA RESIDENCY
RG-KA-93523 · RERA PRM/KA/RERA/1257/336/PR/110823/006166 · Last updated on RERA Karnataka portal: 11 Aug 2023
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SHRI DEVI KRIPA RESIDENCY is a Residential/Group Housing project by AMARNATH SHETTY KURIYALA in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/336/PR/110823/006166 on 11 Aug 2023. Possession is promised by 31 Dec 2028.
At a glance
Project
- NameSHRI DEVI KRIPA RESIDENCY
- TypeResidential/Group Housing
- Location
- Bantwala
- Dakshina Kannada
- 574211
- Pincode574211
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/336/PR/110823/006166
- ReraGenie IDRG-KA-93523
Builder
- NameAMARNATH SHETTY KURIYALA
- Entity typeProprietorship
- GSTIN29ARMPS9313D2ZD
- Authorized SignatoryAMARNATH SHETTY KURIYALA
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on11 Aug 2023
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings1 building record
- Documents filed77 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHRI DEVI KRIPA RESIDENCY | - | - | - | 13 | 0 | 13 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 11 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 11 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| AMARNATH SHETTY KURIYALA | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 1.82 cr | - |
| Payment of taxes | Rs 5.00 lakh | - |
| On-site expenditure-Site Overhead | Rs 2.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHALINI SURESH |
| Engineer | SUDHIR SHETTY |
| Chartered Accountant | SRINIDHI RAO |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed77
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/336/PR/110823/006166 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| MR COPY BEFORE AMALGAMATIONFile: MR copy.pdf | 11 Aug 2023 |
| Registration CertificateFile: trade licence.pdf | - |
| Certificate issued by CA Form 1File: RERA FORM 1.pdf | - |
| Certificate issued by Architect Form 2File: architect certiifcate.pdf | - |
| Certificate issued by Engineer Form 3File: engineer certficate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: litigation affidavit.pdf | - |
| Certificate from Chartered AccountFile: RERA FORM 1.pdf | - |
| Balance Sheet 2021 - 2022File: BS 2023_compressed.pdf | - |
| Balance Sheet 2020 - 2021File: BS 2022.pdf | - |
| Balance Sheet 2019 - 2020File: BS 2021.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: PL 2023_compressed.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: PL 2022.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: PL 2021.pdf | - |
| Cash Flow Statement 2021 - 2022File: IS 2023.pdf | - |
| Cash Flow Statement 2020 - 2021File: IS 2022.pdf | - |
| Auditor's Report 2021 - 2022File: Schedule 2023_compressed.pdf | - |
| Auditor's Report 2020 - 2021File: Schedule 2022.pdf | - |
| Auditor's Report 2019 - 2020File: Schedule 2021.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITR AY 2023-24.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR AY 2022-23.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: ITR AY 2021-22.pdf | - |
| building licence | - |
| single layout | - |
| sanction plan_compressed | - |
| sanction plan | - |
| sanction plan | - |
| sanction plan | - |
| specification | - |
| single layout | - |
| single layout | - |
| stability certificate | - |
| search report | - |
| title deed | - |
| Concersion order_compressed | - |
| Concersion order_compressed | - |
| mother deed | - |
| proforma AOS | - |
| proforma allotment letter | - |
| brocuher | - |
| form b_compressed | - |
| affidavit 3(1) | - |
| mescom noc | - |
| water noc | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| railway noc | - |
| single layout order copy | - |
| single layout plan | - |
| Village map | - |
| estimation cost by engineer | - |
| STP-drawing | - |
| carpet area statement | - |
| guidance value | - |
| source of fund | - |
| Occupancy CertificateFile: OC.jpeg | - |
| Architect certificate for having completed the work(in format no 5)File: architect certificate -completion.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: form 4cc_compressed.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: completion affidavit.pdf | - |
| engineer certificateFile: engineer certificate-completion.pdf | - |
| completion certificateFile: completion.jpeg | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep SHRI DEVI KRIPA RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
Filed coordinates, straight-line distance. 7 registered projects within 2 km.
SAINT ANTONY COMPLEX
LANCY GERALD LOBO
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
See every Dakshina Kannada project, with the district possession charts
Builder: AMARNATH SHETTY KURIYALA
AMARNATH SHETTY KURIYALA has 1 registration on RERA Karnataka, including SHRI DEVI KRIPA RESIDENCY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if SHRI DEVI KRIPA RESIDENCY is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SHRI DEVI KRIPA RESIDENCY?
The registered promoter entity is AMARNATH SHETTY KURIYALA, a proprietorship as per the filing. Its GSTIN 29ARMPS9313D2ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SHRI DEVI KRIPA RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SHRI DEVI KRIPA RESIDENCY?
The professionals named in the filing: Architect: SHALINI SURESH; Engineer: SUDHIR SHETTY; Chartered Accountant: SRINIDHI RAO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHRI DEVI KRIPA RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.