SHREERAM SHIVALAY EAST
RG-MH-81706 · RERA P52100048271 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
- Rs 18.00 crore secured on the land, in favour of DEVELOPMENT CREDIT BANK
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREERAM SHIVALAY EAST is a Others project by Rohit Skylines in Pune, Maharashtra, registered with MahaRERA as P52100048271 on 22 Dec 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 12 months from the original filing. 61 of the 160 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete.
At a glance
Project
- NameSHREERAM SHIVALAY EAST
- TypeOthers
- Location
- Wadgaon Shinde Road
- Lohegaon
- LOHGAON
- Haveli
- Pune
- 411047
- Pincode411047
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100048271
- ReraGenie IDRG-MH-81706
Builder
- NameRohit Skylines
- Entity typePartnership
- PartnerRajendra Ramchandra Agarwal
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Dec 2022
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
- Buildings2 building records
- Documents filed79 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 10 | 9 | 56 | 20 | 76 |
| B | NA | 10 | 9 | 55 | 29 | 84 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed118
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A | 59 | 59 |
| B | 59 | 59 |
Land and ownership18
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Bapu Rangnath Moze | Pune (M Corp.) | Pune |
| Somnath Rangnath Moze | Pune (M Corp.) | Pune |
| Anand Aka Anna Gangaram Moze | Pune (M Corp.) | Pune |
| Rajaram Gangaram Moze | Pune (M Corp.) | Pune |
| Dnyanoba Gangaram Moze | Pune (M Corp.) | Pune |
| Bolhu Rangnath Moze | Pune (M Corp.) | Pune |
| Yashwant Ranghunath Moze | Pune (M Corp.) | Pune |
| Bayadabai Sunil Moze | Pune (M Corp.) | Pune |
| Sunil Vishnu Moze | Pune (M Corp.) | Pune |
| Balasaheb Ramchandra Moze | Pune (M Corp.) | Pune |
| Deepak Vishnu Moze | Pune (M Corp.) | Pune |
| Anjana Vishnu Moze | Pune (M Corp.) | Pune |
| Ujwala Vishnu Moze | Pune (M Corp.) | Pune |
| Yashwant Raghunath Moze | Pune (M Corp.) | Pune |
| Dipak Vishnu Moze | Pune (M Corp.) | Pune |
| Vikas Bapusaheb Moze | Pune (M Corp.) | Pune |
| Sunil Moze | Pune (M Corp.) | Pune |
| Sainath Bapu Moze | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A | NA | Rs 12.91 cr | Rs 10.87 cr |
| B | NA | Rs 12.91 cr | Rs 10.87 cr |
| - | NA | Rs 1.36 cr | Rs 1.02 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Somnath Kerur and Associates |
| Engineer | SK Consultants & Engineers |
| Chartered Accountant | NB Sayed & Associates |
| Chartered Accountant | Vikas Abhang & Associates |
| Partner | Role in project |
|---|---|
| Rohit Skylines | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have received the Occupancy Certificate (OC) for our project Shreeram Shivalay East from the Pune Municipal Corporation (PMC), dated 05/05/2025. However, below mentioned units have been kept on hold by PMC. Are; • Office Nos.: 20, 21, 22, 23, 24 • Flat Nos.: B-104, B-203, B-204 As per the PMC’s communication, this hold has been placed due to the presence of a stormwater line passing through a plot located two plots away from our project site. The concerned authority has held back the clearance for these specific units until the related matter is resolved.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 Oct 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Apr 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Apr 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed79
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Shreeram Shivalay East as on June 2026.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 - Shreeram Shivalay East as on June 2026.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - Shreeram Shivalay East as on June 2026.pdf | 20 Jul 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - Shreeram Shivalay East FY 2024-25.pdf | 5 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Shreeram Shivalay East as on March 2026.pdf | 18 May 2026 |
| Withdrawal Update Form 2File: Form 2 - Shreeram Shivalay East as on March 2026.pdf | 18 May 2026 |
| Withdrawal Update Form 3File: Form 3 - Shreeram Shivalay East as on March 2026.pdf | 18 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Shreeram Shivlalya East as on Dec 2025.pdf | 1 May 2026 |
| Withdrawal Update Form 2File: Form 2- Shreeram Shivalay East- 31-12-2025.pdf | 1 May 2026 |
| Withdrawal Update Form 3File: Form 3- Shreeram Shivalay East- 31-12-2025.pdf | 1 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Shreeram Shivalay East as on Sep 2025.pdf | 4 Nov 2025 |
| Withdrawal Update Form 2File: Form 2- Shreeram Shivalay East as on Sept 2025.pdf | 4 Nov 2025 |
| Withdrawal Update Form 3File: Form 3- Shreeram Shivalay East as on Sept 2025.pdf | 4 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 - Shreeram Shivalay East as on March 2024.pdf | 22 Sep 2025 |
| Withdrawal Update Form 2File: Form 2- Shreeram Shivalay East as on June 2024.pdf | 22 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 June 2025 Signed_compressed (1).pdf | 22 Sep 2025 |
| Layout approvalFile: 1.pdf | 21 Apr 2025 |
| Building plan approvalFile: 2_11zon.pdf | 21 Apr 2025 |
| Building plan approvalFile: 3_11zon.pdf | 21 Apr 2025 |
| Building plan approvalFile: 4_11zon.pdf | 21 Apr 2025 |
| Building plan approvalFile: 5_11zon.pdf | 21 Apr 2025 |
| Building plan approvalFile: 6_11zon.pdf | 21 Apr 2025 |
| Building plan approvalFile: 7.pdf | 21 Apr 2025 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 21 Apr 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 21 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 2_11zon.pdf | 21 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 3_11zon.pdf | 21 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 4_11zon.pdf | 21 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 5_11zon.pdf | 21 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 6_11zon.pdf | 21 Apr 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 21 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Shreeeram Shivalay East- 31st March 2025.pdf | 18 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shreeram Shivalay East as on March 2025.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Shreeram Shivalay East as on March 2025.pdf | 15 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Shivalay East.pdf | 7 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Shreeeram Shivalay East- 31st December 2024.pdf | 15 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shreeram Shivalay East as on Dec 2024.pdf | 15 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Shreeram Shivalay East as on Sep 2024.pdf | 19 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Shreeram Shivalay East.pdf | 5 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Shreeeram Shivalay East- 30th Sep 2024.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Shreeram Shivalay East as on June 2024.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Shreeram Shivalay East as on June 2024.pdf | 17 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Shreeeram Shivalay East- 30th June 2024.pdf | 17 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Shreeram Shivalay East as on March 2024.pdf | 17 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Shreeeram Shivalay East- 31st March 2024.pdf | 17 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Shreeram Shivalay East as on March 2024.pdf | 15 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Circular 29 - Shreeram Shivalay East as on Dec 2023.pdf | 15 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Shreeram Shivalay East as on Dec 2023.pdf | 28 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Shreeram Shivalay East as on Dec 2023.pdf | 16 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Shreeeram Shivalay East- Dec 2023.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Shreeram Shivalay East as on 20-10-2023.pdf | 25 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Shreeram Shivalay East as on September 2023.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Shreeeram Shivalay East as on 30th Sep 2023.pdf | 17 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 as on 19-08-2023.pdf | 5 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Shreeram Shivalay East as on 2022-23.pdf | 2 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Shreeram Shivalay East as on March 2023.pdf | 28 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Shreeram Shivalay East as on June 2023.pdf | 28 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Shreeram Shivalay East as on 31-03-2023.pdf | 28 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Shreeram Shivalay East as on 30-06-2023.pdf | 28 Jul 2023 |
| Other - LegalFile: AL 10122022.pdf | 10 Dec 2022 |
| Other - LegalFile: Deviation report AL 06122022.pdf | 10 Dec 2022 |
| Declaration in FORM BFile: rohit skylines affidavit_compressed.pdf | 14 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 17 Oct 2022 |
| Proforma of Agreement for saleFile: AFS 10122022.pdf | 17 Oct 2022 |
| Proforma of Allotment letterFile: Model Allotment Letter_compressed.pdf | 17 Oct 2022 |
| Deviation Report with respect to Allotment letterFile: Allotment Deviation.pdf | 17 Oct 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation report AFS 06122022_compressed.pdf | 17 Oct 2022 |
| Layout approvalFile: Copy Of Layout.pdf | 15 Oct 2022 |
| Building plan approvalFile: 1 Building Plan Approval NA Order for plotted development_compressed.pdf | 15 Oct 2022 |
| PAN CardFile: pan card.pdf | 15 Oct 2022 |
| Copy of the legal title reportFile: search and title 275-8_compressed.pdf | 15 Oct 2022 |
| Details of encumbrances concerned to FinanceFile: 1 a Details of encumbrances concerned to Finance .pdf | 15 Oct 2022 |
| Details of encumbrances concerned to LegalFile: 1 b Details of encumbrances concerned to Legal.pdf | 15 Oct 2022 |
| Copy of Layout Approval (in case of layout)File: Copy Of Layout.pdf | 15 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval NA Order for plotted development_compressed.pdf | 15 Oct 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf | 15 Oct 2022 |
| Declaration about Commencement CertificateFile: 1 Declaration CC.pdf | 15 Oct 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200246370758_For_Asset_Based_Search_05_09_2022_12_49_00_248.pdf | 15 Oct 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 'A' Format.pdf | 15 Oct 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 79 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHREERAM SHIVALAY EAST on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Lohegaon13,700+ in Pune
Filed coordinates, straight-line distance. 131 registered projects within 2 km.
NESTERRA - PHASE 1
Triaa Skyscrapers LLP
Divine Garden Phase II
SHRIRAM ASSOCIATES
Divine Garden Phase 1
SHRIRAM ASSOCIATES
Solitaire Business Hub Viman Nagar Phase 1
Classic Promoters and Builders Private Lim
Krishna Lake Town
Krishna Housing
NIVASA ENCHANTE - PHASE I
NIVASA ASSOCIATES
Builder: Rohit Skylines
Rohit Skylines has 1 registration on MahaRERA, including SHREERAM SHIVALAY EAST. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that SHREERAM SHIVALAY EAST shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHREERAM SHIVALAY EAST is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREERAM SHIVALAY EAST?
The registered promoter entity is Rohit Skylines, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREERAM SHIVALAY EAST?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREERAM SHIVALAY EAST?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREERAM SHIVALAY EAST?
The professionals named in the filing: Architect: Somnath Kerur and Associates; Engineer: SK Consultants & Engineers; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Vikas Abhang & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREERAM SHIVALAY EAST?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.