Home / Browse projects / Palghar, Maharashtra / Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial

Registration lapsed No litigation declared Others project

Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial

By M/s. Sairam Realtors

RG-MH-50965 · RERA P99000017104 · Last updated on MahaRERA portal: 18 Sep 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 18 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
18 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
0 of 82Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 87 documents Report an error

Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial is a Others project by M/s. Sairam Realtors in Palghar, Maharashtra, registered with MahaRERA as P99000017104 on 13 Jul 2018. Possession was promised by 13 Jun 2026 and is now 4 months past that date. The completion date has moved by 18 months from the original filing. 82 of the 82 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.

At a glance

Project

  • NameShreeram Complex Bldg No 12 A and B Wings Residential with Commercial
  • TypeOthers
  • Location
    • Tirupati Nagar
    • Virar West
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • RERA no.P99000017104
  • ReraGenie IDRG-MH-50965

Builder

  • NameM/s. Sairam Realtors
  • Entity typePartnership
  • PartnersMahesh Ratanlal Agrawal, Sandeep Kanaiyalal Mehta, Bhavana Sandeep Mehta, Pramila Mahesh Agrawal, Meeta Bhavesh Mehta, Bindu Mahesh Agrawal, Vinay Mahesh Agrawal

Key dates

4 months past promisethis monthRegisteredJul 2018First promiseDec 2024Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on13 Jul 2018
  • Promised completion13 Jun 2026
  • Revised completionRevised to 13 Jun 2026 (originally 30 Dec 2024)
  • Buildings2 building records
  • Documents filed87 files

Current status

100%82 of 82 units booked
100.0%Work done, per cost certificate

Figures as on 18 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA1515181028
Wing BNA151554054

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 18 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

Wing A82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 18 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Open Space22
BuildingOpen SpaceTotal
Wing A1010
Wing B1212

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,680 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Sep 2025
LandownerVillageDistrict
M/s. Ameya Builders And Property DevelopersVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVASAI VIRAL CITY MUNCIPAL CORARATION
Permissible FSI4946.0
Proposed, not sanctioned3,640 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFreny Arcade Samelpada Nallasopara West Palghar 401203
Estimated costRs 36.73 cr
Cost incurredRs 36.73 cr
Work done100.0%
BuildingWingEstimatedIncurred
Wing ANARs 18.30 crRs 18.30 cr
Wing BNARs 18.30 crRs 18.30 cr
-NARs 13.75 lakhRs 13.75 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhay Raut
EngineerParesh Ramniklal Unnarkar
Chartered AccountantPOKHARNA & ASSOCIATES
PartnerRole in project
M/s. Sairam Realtors-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000025492Dec 2024 → Apr 2025

Reason as filed by the promoterWe had completed the work of the aforesaid project on time but the owners of the said project M/S. Ameya Builders and Property Developers were not Appling for the Occupancy certificate even after the 100% work completion certificate from the Architect was received on 30/03/2024. Due to which the project got delayed and later after few months they got agreed to apply for Occupancy Certificate and have applied the same on 14/09/2024 in VVCMC.

EA30012619639Dec 2024 → Jun 2026

Reason as filed by the promoterOC is received we are taking extension upto oc date

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Jul 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed87

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 June 2025 - SRR.pdf18 Sep 2025
Withdrawal Update Form 2File: Forn 2 June 2025 - SRR.pdf18 Sep 2025
Withdrawal Update Form 3File: form 3 NEW.pdf18 Sep 2025
Form 1File: Form 1.pdf10 Sep 2025
Form 2File: Form 2.pdf10 Sep 2025
Form 3File: Form 3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: Inventory disclosure.pdf10 Sep 2025
Declaration about Commencement CertificateFile: declaration of CC.pdf11 Dec 2024
CERSAI detailsFile: cersai.pdf11 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate - Shreeram Complex.pdf26 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate - Shreeram Complex_compressed.pdf26 Apr 2022
Building plan approvalFile: Plan 1 27821.pdf12 Mar 2022
Building plan approvalFile: Plan 2 27821.pdf12 Mar 2022
Building plan approvalFile: Plan 3 27821.pdf12 Mar 2022
Building Plan Approval (IOD)File: Plan 1 27821.pdf12 Mar 2022
Building Plan Approval (IOD)File: Plan 2 27821.pdf12 Mar 2022
Building Plan Approval (IOD)File: Plan 3 27821.pdf12 Mar 2022
Building plan approvalFile: Plan 1 - 2020.pdf10 Mar 2022
Building plan approvalFile: Plan 1 - 2021 .pdf10 Mar 2022
Building plan approvalFile: Plan 2 - 2020.pdf10 Mar 2022
Building plan approvalFile: Plan 2 - 2021 .pdf10 Mar 2022
Building plan approvalFile: Plan 3 - 2020.pdf10 Mar 2022
Building plan approvalFile: Plan 3 - 2021.pdf10 Mar 2022
Building Plan Approval (IOD)File: Plan 1 - 2020.pdf10 Mar 2022
Building Plan Approval (IOD)File: Plan 1 - 2021 .pdf10 Mar 2022
Building Plan Approval (IOD)File: Plan 2 - 2020.pdf10 Mar 2022
Building Plan Approval (IOD)File: Plan 2 - 2021 .pdf10 Mar 2022
Building Plan Approval (IOD)File: Plan 3 - 2020.pdf10 Mar 2022
Building Plan Approval (IOD)File: Plan 3 - 2021.pdf10 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: CC 04112020.pdf10 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: CC 22022021.pdf10 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: CC 27082021.pdf10 Mar 2022
OtherFile: supplementry agreement.pdf10 Mar 2022
Building plan approvalFile: Approved Floor Plan.pdf9 Jul 2018
Building plan approvalFile: Self Declaration - No IOD.pdf9 Jul 2018
Layout approvalFile: Layout Plan.pdf9 Jul 2018
Building plan approvalFile: Proposed Floor Plan -1.pdf9 Jul 2018
Building plan approvalFile: Proposed Floor Plan -2.pdf9 Jul 2018
PAN CardFile: Pancard.pdf9 Jul 2018
Copy of the legal title reportFile: Title Certificate Part 1.pdf9 Jul 2018
Copy of the legal title reportFile: Title Certificate Part 2.pdf9 Jul 2018
Copy of the legal title reportFile: Search Report Part 1.pdf9 Jul 2018
Copy of the legal title reportFile: Search Report Part 2.pdf9 Jul 2018
Copy of the legal title reportFile: Search Report Part 3.pdf9 Jul 2018
Details of encumbrancesFile: Self Declaration - No Encumbrance.pdf9 Jul 2018
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf9 Jul 2018
Building Plan Approval (IOD)File: Self Declaration - No IOD.pdf9 Jul 2018
Building Plan Approval (IOD)File: Proposed Floor Plan -1.pdf9 Jul 2018
Building Plan Approval (IOD)File: Proposed Floor Plan -2.pdf9 Jul 2018
Building Plan Approval (IOD)File: Approved Floor Plan.pdf9 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf9 Jul 2018
Declaration in FORM BFile: Form B - 1.pdf9 Jul 2018
Declaration in FORM BFile: Form B 2.pdf9 Jul 2018
Certificates of CA (Form 3)File: C A Certificate.pdf9 Jul 2018
Proforma of Allotment letterFile: Agreement for Sale as per RERA - Shreeram Complex - Final Draft- 07-07-2018.pdf9 Jul 2018
Proforma of Allotment letterFile: Allotment Letter.pdf9 Jul 2018
Proforma of Allotment letterFile: List of Amenties - Annexure E.pdf9 Jul 2018
OtherFile: 7-12 (part 1).pdf9 Jul 2018
OtherFile: 7-12 (part 2).pdf9 Jul 2018
OtherFile: Ferfar patrak.pdf9 Jul 2018
OtherFile: NA Order.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 1.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 2.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 3.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 4.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 5.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 6.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 7.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 8.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 9.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 10.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 11(CC1).pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 12(CC2).pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 13(7-12).pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 14(7-12).pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 15(POA).pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 16(POA).pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 17(POA).pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 18.pdf9 Jul 2018
OtherFile: Agreement for Sale of FSI - Part 19.pdf9 Jul 2018

How this compares with Palghar

100%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 18 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shreeram Complex Bldg No 12 A and B Wings Re on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Virar West3,200+ in Palghar

Builder: M/s. Sairam Realtors

M/s. Sairam Realtors has 1 registration on MahaRERA, including Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial is delayed beyond 13 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial?

The registered promoter entity is M/s. Sairam Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial?

The professionals named in the filing: Architect: Abhay Raut; Engineer: Paresh Ramniklal Unnarkar; Chartered Accountant: POKHARNA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shreeram Complex Bldg No 12 A and B Wings Residential with Commercial. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shreeram Complex Bldg No 12 A and B Wings Re to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.