Home / Browse projects / Mumbai City, Maharashtra / SHREEPATI SKIES
SHREEPATI SKIES
RG-MH-20042 · RERA P51900003092 · Last updated on MahaRERA portal: 22 Dec 2022
Source: official MahaRERA filing
Red flags
- De-registered
- Litigation declared, 6 cases
- 1 complaint at MahaRERA
Clear
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREEPATI SKIES is a Residential / Group Housing project by SHREEPATI SKIES in Mumbai City, Maharashtra, registered with MahaRERA as P51900003092 on 4 Aug 2017. Possession is promised by 30 Dec 2026. 1 complaint is on record with the regulator.
At a glance
Project
- NameSHREEPATI SKIES
- TypeResidential / Group Housing
- Location
- Tukaram Javji Marg
- Mumbai City
- 400007
- Pincode400007
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900003092
- ReraGenie IDRG-MH-20042
Builder
- NameSHREEPATI SKIES
- Entity typeOthers
- Named personsRAJENDRA R CHATURVEDI, TAPAS CHATURVEDI
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on4 Aug 2017
- Promised completion30 Dec 2026
- Revised completionNone
- Buildings3 building records
- Documents filed42 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 63 | 0 | 0 | 0 | 0 |
| WING B | NA | 0 | 0 | 0 | 0 | 0 |
| WING C | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 22 Dec 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.
WING A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 22 Dec 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed320
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MILIND SAMEL |
| Architect | B.N. Shah & Associates |
| Engineer | Sunil Sohani |
| Chartered Accountant | Jain Ashwani & Co. |
| Chartered Accountant | Bansal & Co. LLP |
| Chartered Accountant | Damyanti Gupta |
| Partner | Role in project |
|---|---|
| SHREEPATI SKIES | - |
Litigation declared6
| Case | Court | Status |
|---|---|---|
| 1263/2002 | HIGH COURT | DISPOSED |
| 2329/2012 | HIGH COURT | DISPOSED |
| 2348/2012 | HIGH COURT | DISPOSED |
| 2976/2014 | HIGH COURT | DISPOSED |
| 978/2018 | High Court | DISPOSED |
| 1263/2002 | high Court | Closed |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000056630 | PROZONE DEVELOPERS & REALTORS PRIVATE LIMITED | M/s Shreepati Skies | 18/10/2018 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Mar 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2026
Documents filed42
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Foreclosure of the ProjectFile: DECLARATION FORM 4.pdf | 22 Dec 2022 |
| Foreclosure of the ProjectFile: Cancellation of RERA 02-12-2022.pdf | 13 Dec 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 _Eng certificate.pdf | 13 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SUNIL SOHANI (Civil Engineer).pdf | 13 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form - 1 _Architect certificate.pdf | 4 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE _compressed.pdf | 4 Oct 2022 |
| Certificates of CA (Form 3)File: Form 3_compressed.pdf | 4 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Skies form -5.pdf | 3 May 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: skies form 5.pdf | 14 Apr 2021 |
| OtherFile: MHADA NOC upload.pdf | 18 Mar 2021 |
| OtherFile: Penalty Payment Ack.pdf | 6 Jan 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 _ Architect Certificate.pdf | 14 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 _Engineer Certificate.pdf | 14 Nov 2019 |
| Certificates of CA (Form 3)File: Form 3 Skies CA cert.pdf | 14 Nov 2019 |
| OtherFile: Shreepati Skeis _ Project Status.pdf | 28 Aug 2019 |
| Certificates of CA (Form 5)File: S SKIES FORM 5.pdf | 24 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Rera Certificate 31-03-2018.pdf | 30 Oct 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate 31-03-2018.pdf | 30 Oct 2018 |
| Certificates of CA (Form 3)File: CA CSR SKIES MARCH 2018.pdf | 29 Oct 2018 |
| Layout approvalFile: skies-lay.pdf | 26 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: skies-lay.pdf | 26 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE.pdf | 31 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE.pdf | 31 Oct 2017 |
| Certificates of CA (Form 3)File: SHREEPATI SKIES.pdf | 31 Oct 2017 |
| Layout approvalFile: Architect Certificate.pdf | 24 Jul 2017 |
| Building plan approvalFile: IOD_16-02-2008-.pdf | 24 Jul 2017 |
| PAN CardFile: PAN_Shreepati Skies.pdf | 24 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE CS NO_309.pdf | 24 Jul 2017 |
| Details of encumbrancesFile: SHREEPATI SKIES.pdf | 24 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Architect Certificate.pdf | 24 Jul 2017 |
| Building Plan Approval (IOD)File: IOD_16-02-2008-.pdf | 24 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-.pdf | 24 Jul 2017 |
| Declaration in FORM BFile: FORM B SHREEPATI SKIES.pdf | 24 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 24 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_24TH JULY 2017.pdf | 24 Jul 2017 |
| Certificates of CA (Form 3)File: Chartered Accountant Certificate.pdf | 24 Jul 2017 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf | 24 Jul 2017 |
| OtherFile: CIVIL AVIATION NOC.pdf | 24 Jul 2017 |
| OtherFile: HIGH RISE NOC.pdf | 24 Jul 2017 |
| OtherFile: MHADA NOC.pdf | 24 Jul 2017 |
| OtherFile: ENVIROMENTAL CLEARANCE.pdf | 24 Jul 2017 |
| OtherFile: CFO NOC.pdf | 24 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 42 filed documents as one ZIP, foldered, with a manifest
Keep SHREEPATI SKIES on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mumbai City780+ in Mumbai City
Filed coordinates, straight-line distance. 98 registered projects within 2 km.
AARADHYA AVAAN
SHREEPATI SKIES (R R CHATURVEDI)
The Empire Tower
Samak Constructions Pvt. Ltd
Golden Navkar
GOLDEN REALTY (BALARAM STREET)
BELFORT BAY - MUMBADEVI
SHAILENDRA REALTORS PVT. LTD.
SHUKRIYA ELITE TOWER
ELITE CASTLES PRIVATE LIMITED
NIRVAANA PEARL
Nirvaana Lifespace LLP
See every Mumbai City project, with the district possession charts
Builder: SHREEPATI SKIES
SHREEPATI SKIES has 1 registration on MahaRERA, including SHREEPATI SKIES. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What does it mean that SHREEPATI SKIES shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SHREEPATI SKIES is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREEPATI SKIES?
The registered promoter entity is SHREEPATI SKIES, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREEPATI SKIES?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHREEPATI SKIES?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHREEPATI SKIES?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREEPATI SKIES?
The professionals named in the filing: Architect: MILIND SAMEL; Architect: B.N. Shah & Associates; Engineer: Sunil Sohani; Chartered Accountant: Jain Ashwani & Co.; Chartered Accountant: Bansal & Co. LLP; Chartered Accountant: Damyanti Gupta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREEPATI SKIES?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback