ReraGenieLog inGet a buyer report

Home / Browse projects / Kolhapur, Maharashtra / Shree Yash Chintamani

Completed No litigation declared Residential / Group Housing project

Shree Yash Chintamani

By Powar Associates

RG-MH-13174 · RERA P53000022387 · Last updated on MahaRERA portal: 6 Oct 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Internal walls, 60%
0Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

Shree Yash Chintamani is a Residential / Group Housing project by Powar Associates in Kolhapur, Maharashtra, registered with MahaRERA as P53000022387 on 19 Sep 2019. The registration is recorded completed; possession was promised by 30 Dec 2025.

At a glance

Project

  • NameShree Yash Chintamani
  • TypeResidential / Group Housing
  • Location
    • Mohite Park Rankala
    • Kasaba Karveer
    • Kolhapur (M Corp.)
    • Karvir
    • Kolhapur
    • 416012
  • Pincode416012
  • RERA no.P53000022387
  • ReraGenie IDRG-MH-13174

Builder

  • NamePowar Associates
  • Entity typePartnership
  • PartnerPrakash Narayan Powar
  • Other registrations2 more →
  • Completed3 of 3
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2019PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on19 Sep 2019
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed65 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shree Yash ChintamaniNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 60%.

Shree Yash Chintamani: 63% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Closed/Covered9

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area638 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1965.0
Proposed, not sanctioned1,965 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch10/4 A ward Khari Corner Kolhapur

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSambhaji Patil
EngineerArun S Mohite
Chartered AccountantTripti C Pimpalkar and Associates
PartnerRole in project
Powar Associates-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Sep 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Mar 2023

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022-2023 Powar Associates10052023.pdf6 Oct 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Deed of Declaration Index10062023.pdf6 Oct 2023
Status of ConveyanceFile: Sale Deed Index10062023.pdf6 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Sachin Powar.pdf3 Mar 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Sachin Powar.pdf3 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (21-22).pdf21 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA-3 Compress.pdf14 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf8 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Engineer's Certificate.pdf8 Jul 2022
Disclosure of sold/ booked inventoryFile: Discolsure of sold booked inventory.pdf8 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountant's Certificate.pdf8 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf17 Jan 2022
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED.pdf17 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf17 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf17 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate-compressed.pdf6 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate (2)-compressed.pdf6 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A -compressed.pdf6 Oct 2021
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory (1).pdf6 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate.pdf6 Oct 2021
Declaration about Commencement CertificateFile: Format D.pdf10 Aug 2021
Building plan approvalFile: Section Plan (2)_compressed.pdf9 Aug 2021
Building plan approvalFile: Section Plan (3)-compressed.pdf9 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: Section Plan (2)_compressed.pdf9 Aug 2021
Building Plan Approval / NA Order for plotted developmentFile: Section Plan (3)-compressed.pdf9 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aechitect Certificate FORM 1_compressed.pdf9 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_compressed.pdf9 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate Final.pdf9 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: C A Certificate Final.pdf9 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A)File: Sachin Powar Form-2A (Q 4 20-21) compressed.pdf1 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Sachin Powar Form-2A (Q-3 - 20-21)_compressed.pdf1 Jun 2021
Disclosure of sold/ booked inventoryFile: Powar Associates Sold Unsold Inventory.pdf1 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A june.pdf5 Nov 2020
Engineers Certificate on Quality Assurance (Form 2A)File: form 2A sep.pdf5 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 511052020.pdf5 Nov 2020
Building plan approvalFile: Plan A- 21-9-2020.pdf28 Sep 2020
Building plan approvalFile: Plan B- 21-9-2020 powar.pdf28 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan A- 21-9-2020.pdf28 Sep 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan B- 21-9-2020 powar.pdf28 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: commencement.pdf28 Sep 2020
Engineers Certificate on Quality Assurance (Form 2A)File: combinepdf-min.pdf31 Dec 2019
Building plan approvalFile: Scan (1).pdf18 Dec 2019
Building plan approvalFile: Scan0001.pdf18 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: Scan (1).pdf18 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: Scan0001.pdf18 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: img-Z11041934-0001 Sachin Powar-converted.pdf18 Dec 2019
Declaration in FORM BFile: Form B_0001.pdf13 Sep 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf13 Sep 2019
PAN CardFile: PAN powar associates.pdf11 Sep 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf11 Sep 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf11 Sep 2019
Layout approvalFile: Layout Plan.pdf3 Sep 2019
Building plan approvalFile: Sanctioned Plan 1.pdf3 Sep 2019
Building plan approvalFile: Sanctined Plan 2.pdf3 Sep 2019
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf3 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Plan 1.pdf3 Sep 2019
Building Plan Approval / NA Order for plotted developmentFile: Sanctined Plan 2.pdf3 Sep 2019
Proforma of Allotment letterFile: Agreement To Sale.pdf3 Sep 2019
Proforma of Allotment letterFile: Allotement letter.pdf3 Sep 2019
Copy of the legal title reportFile: Search Report Plot No 19.pdf31 Aug 2019
Copy of the legal title reportFile: Search Report Plot No 20.pdf31 Aug 2019
Details of encumbrancesFile: Encumbrances.pdf31 Aug 2019
Commencement Certificates / NA Order for plotted developmentFile: Commecement Certificate.pdf31 Aug 2019
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A.pdf31 Aug 2019

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Abasaheb RecidencyC S No 2371-5 Kasaba Bawada Kolhapur11CompletedJul 2015Jul 2015
Shree Yash AmayR.S.No. 75 Plot No.34 A Ward Kolhapur12CompletedAug 2013Aug 2013

How this compares with Kolhapur

17%of Kolhapur projects moved their completion datethis one has not
25%of Kolhapur registrations have lapsed or been cancelledthis one is completed

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep Shree Yash Chintamani on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kasaba Karveer880+ in Kolhapur

Builder: Powar Associates

Powar Associates has 3 registrations on MahaRERA, including Shree Yash Varad and Shree Yash Chintamani. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if Shree Yash Chintamani is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Yash Chintamani?

The registered promoter entity is Powar Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Yash Chintamani?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shree Yash Chintamani?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Yash Chintamani?

The professionals named in the filing: Architect: Sambhaji Patil; Engineer: Arun S Mohite; Chartered Accountant: Tripti C Pimpalkar and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Yash Chintamani?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Yash Chintamani. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Yash Chintamani to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.