Home / Browse projects / Raigarh, Maharashtra / Shree Vastu Symphony

Registered No litigation declared Residential / Group Housing project

Shree Vastu Symphony

By Shree Vastupurti Associates

RG-MH-14380 · RERA P52000022687 · Last updated on MahaRERA portal: 20 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 45 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 45 months from the original
6 of 22Construction stages doneacross 2 buildings; furthest along: Stilt Floor, 70%
12 of 38Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 115 documents Report an error

Shree Vastu Symphony is a Residential / Group Housing project by Shree Vastupurti Associates in Raigarh, Maharashtra, registered with MahaRERA as P52000022687 on 12 Oct 2019. Possession is promised by 30 Jun 2027. The completion date has moved by 45 months from the original filing. 26 of the 38 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameShree Vastu Symphony
  • TypeResidential / Group Housing
  • Location
    • Village Road
    • Vihighar
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000022687
  • ReraGenie IDRG-MH-14380

Builder

  • NameShree Vastupurti Associates
  • Entity typePartnership
  • PartnerAsif Patel

Key dates

this monthRegisteredOct 2019First promiseSep 2023Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Oct 2019
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Sep 2023)
  • Buildings2 building records
  • Documents filed115 files

Current status

68%26 of 38 units booked
61.2%Work done, per cost certificate

Figures as on 20 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-WingNA5416016
B-WingNA5422022

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 70%.

A-Wing46%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor70%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-Wing46%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor70%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered14
BuildingClosed/CoveredTotal
A-Wing77
B-Wing77

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,606 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Mar 2026

Approvals and building plan

Sanctioning authorityCIDCO Navi Mumbai Airport Influence Notified Area (NAINA)
Permissible FSI1605.77
Proposed, not sanctioned1,600 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNeel Avenue, Sector 19 New Panvel 410206
Estimated costRs 4.23 cr
Cost incurredRs 2.59 cr
Work done61.19%
BuildingWingEstimatedIncurred
B-WingNARs 1.93 crRs 1.40 cr
A-WingNARs 1.64 crRs 1.19 cr
-NARs 66.02 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Neha Jain
EngineerNilesh Samant
EngineerDU Consultant
Chartered AccountantMukund Thale
Chartered AccountantSwapnil Mane & Associates
PartnerRole in project
Shree Vastupurti Associates-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000017621Sep 2023 → Dec 2024

Reason as filed by the promoterSir, The Covid crises and the resultant restriction by Government resulted into migration of labour on a large scale. The pandemic also affected the availability of construction material which resulted in completed stoppage of work. Further, since our project is located away from urban area, it took us long time to restart the work and therefore need a period of another 10-12 months for work completion and 2-3 months for getting Occupation Certificate. In view of the above, we request this Hon’ble Authority to allow extension to the Project completion date as applied for u/s 7 (3) of Real Esta

EXT52000027832Sep 2023 → Dec 2025

Reason as filed by the promoterThe work of structure, blockwork for external and internal walls as well as railings have been completed. Work is in progress plaster and elevation work. Also work for other internal finishes is in progress. The balance work shall be carried out as per the CPM chart enclosed with this application. We are hopeful of completing the balance work as per the schedule given in CPM Chart. In view of the above, we request this Hon’ble Authority to allow extension to the Project completion date as applied for u/s 7 (3) of Real Estate (Regulation and Development) Act,2016.

EA16062621391Sep 2023 → Jun 2027

Reason as filed by the promoterThe said extension is necessitated due to changes in the planning of the project as additional FSI has become available following the implementation of UDCPR across the state of Maharashtra. Therefore, the project timeline for completion has increased as detailed in the CPM chart enclosed with this Application. We are also in the process of applying for correction in the project details by filing appropriate application under section 14(2) of Real Estate (Regulation & Development) Act, 2016 soon after the extension of project registration validity is approved by this Hon’ble Authority. In view

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Sep 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Sep 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Sep 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed115

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 115 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: SV Symphony Form-2A FY 2025-26.pdf20 Aug 2026
Form 2A (FY 2024-2025)File: SV Symphony Form-2A FY 2024-25.pdf20 Aug 2026
Withdrawal Update Form 1File: SV Symphony Form-1 Dec 2025.pdf1 Jun 2026
Withdrawal Update Form 2File: SV Symphony Form-2 Dec 2025.pdf1 Jun 2026
Withdrawal Update Form 3File: SV Symphony Form-3 Dec 2025.pdf1 Jun 2026
Withdrawal Update Form 1File: SV Symphony Form-1 Sep 2025.pdf27 May 2026
Withdrawal Update Form 2File: SV Symphony Form-2 Sep 2025.pdf27 May 2026
Withdrawal Update Form 3File: SV Symphony Form-3 Sep 2025.pdf27 May 2026
Withdrawal Update Form 1File: SV Symphony Form-1 Jun 25.pdf23 May 2026
Withdrawal Update Form 2File: SV Symphony Form-2 June 2025.pdf23 May 2026
Withdrawal Update Form 3File: SV Symphony Form-3 June 2025.pdf23 May 2026
Form 1File: Symphony Arch Form 1 202303.pdf31 Dec 2025
Form 2File: Symphony Engr form 2 202303.pdf31 Dec 2025
Form 3File: Symphony CA Form 3 202303.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Symphony Sold disclr 202303.pdf31 Dec 2025
Form 1File: Symphony Arch Form 1 202309.pdf31 Dec 2025
Form 2File: Symphony Engr Form 2 202309.pdf31 Dec 2025
Form 3File: Symphony CA Form 3 202309.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Symphony Sold Inv disclr 202309.pdf31 Dec 2025
Form 1File: Symphony Arch Form 1 202403.pdf31 Dec 2025
Form 2File: Symphony Engr Form 2 202403.pdf31 Dec 2025
Form 3File: Symphony CA Form 3 202403.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Symphony Sold Inve Disclr 202403.pdf31 Dec 2025
Form 1File: Symphony Arch Form 1 202412.pdf31 Dec 2025
Form 2File: Symphony Engr Form 2 202412.pdf31 Dec 2025
Form 3File: Symphony CA Form 3 202412.pdf31 Dec 2025
Disclosure of Sold and Booked InventoryFile: Symphony Sold Inventory Disclr 202412.pdf31 Dec 2025
Form 5 (FY 2023-2024)File: Form-5_FY 2023-24.pdf31 Dec 2025
Form 5 (FY 2022-2023)File: Form-5_FY 2022-23.pdf31 Dec 2025
Form 5 (FY 2021-2022)File: Form-5 FY 2021-22.pdf31 Dec 2025
Declaration in FORM BFile: Form B.pdf31 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2023-24_CA_Form-5.pdf31 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 FY 2023-24 Q2 181123.pdf22 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY20425 Q1 F3 030824.pdf10 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY2425 Q2 F3 201224.pdf10 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY2425 Q3 F3 270125.pdf10 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FY202425 Q4 F3 030824.pdf10 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SV Symphony CA Certificate Form-3 FY 2023-24 Q2 181123.pdf8 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 05032025 FY202223.pdf6 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 July23 to Sep23 300923.pdf28 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 Oct23 to Dec23 020124.pdf28 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 010424.pdf28 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 010724.pdf28 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 041024.pdf28 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 090125.pdf28 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: F2A Quality Assurance Certificate Fy 23-24 100125.pdf28 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 July23 to Oct23.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Oct23 to Dec23.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F 1 July24 to Oct 24.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Jan 24 to Mar 24 01042024.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F 1 Apr24 to June24 01072024.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F 1 July24 to Oct 24 01102024.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Oct24 to Dec24 01012025.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F 1 Apr24 to June24.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SV Sym F3 FY 2023 24 Q3.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SV Sym F3 FY 202425 Q1.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SV Sym F3 FY 2023 24 Q4.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SV Sym F3 FY 2023 24 Q2.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory Sold details July23 to Sep23.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory Sold details Oct23 to Dec23.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory qtr jan to march24.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: inventory qtr Apr to June 24.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory qtr July to sep 24.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory qtr Oct to Dec24.pdf27 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5 Shree Vastu Symphony FY 2023 24.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202203_Er.pdf5 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202303_Er.pdf5 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2021-22_Form-2A.pdf5 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2022-23_Form-2A.pdf5 Oct 2023
Disclosure of sold/ booked inventoryFile: 202306_Sold.pdf5 Oct 2023
Disclosure of sold/ booked inventoryFile: 202303_Sold.pdf24 Sep 2023
Disclosure of sold/ booked inventoryFile: 202303_Sold.pdf24 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202303_CA_R.pdf24 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202206_Ar.pdf23 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202209_Ar.pdf23 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202212_Ar.pdf23 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202303_Ar.pdf23 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 202306_Ar.pdf23 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202003_Er.pdf23 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 202103_Er.pdf23 Sep 2023

How this compares with Raigarh

68%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 45 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shree Vastu Symphony on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vihighar5,900+ in Raigarh

2 kmShree Vastu SymphonyCompleted 5Lapsed / revoked 3Other 26Dot size: filed unitsN

Filed coordinates, straight-line distance. 34 registered projects within 2 km.

Builder: Shree Vastupurti Associates

Shree Vastupurti Associates has 1 registration on MahaRERA, including Shree Vastu Symphony. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Shree Vastu Symphony is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Vastu Symphony?

The registered promoter entity is Shree Vastupurti Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Vastu Symphony?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shree Vastu Symphony?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Vastu Symphony?

The professionals named in the filing: Architect: Ar Neha Jain; Engineer: Nilesh Samant; Engineer: DU Consultant; Chartered Accountant: Mukund Thale; Chartered Accountant: Swapnil Mane & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Vastu Symphony?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Vastu Symphony. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Vastu Symphony to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.