ReraGenieLog inGet a buyer report

Home / Browse projects / Solapur, Maharashtra / Shree Varad Residency

Completed No litigation declared Others project

Shree Varad Residency

By Mr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty

RG-MH-26204 · RERA P52600013916 · Last updated on MahaRERA portal: 17 Jul 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

Shree Varad Residency is a Others project by Mr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty in Solapur, Maharashtra, registered with MahaRERA as P52600013916 on 2 Nov 2017. The registration is recorded completed; possession was promised by 29 Dec 2022. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameShree Varad Residency
  • TypeOthers
  • Location
    • Dahitane Road
    • Shelagi
    • Solapur (M Corp.)
    • Solapur North
    • Solapur
    • 413006
  • Pincode413006
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52600013916
  • ReraGenie IDRG-MH-26204

Builder

  • NameMr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty
  • Entity typeOthers
  • PartnerAmbavva Mallappa Shetty

Key dates

this monthRegisteredNov 2017First promiseDec 2021Revised toDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on2 Nov 2017
  • Promised completion29 Dec 2022
  • Revised completionRevised to 29 Dec 2022 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shree Varad ResidencyNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

Shree Varad Residency: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities17

As on 17 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%
Under Ground Water tankYes100%
Compound WallYes100%

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered1
Open Space4

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area501 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1151.91
Proposed, not sanctioned693 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchchoupad , navi peth , Budhwar peth, Solapur - 413001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAmit Shetty
EngineerRahul Darvekar & Associates
PartnerRole in project
Mr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52600010881Dec 2021 → Dec 2022

Reason as filed by the promoterOur Project is in small city. People are expecting ready possession flats than under construction building. we had very poor response for booking, so we had slowed down the construction activity. Now after lockdown , we have speed up the construction of the project & it is expected to finish the project by 29th Dec 2022 irrespective of Bookings.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Oct 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Jul 2024

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Cert_FO_359864_382wKdlwSign.pdf17 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Solapur Part OC.pdf27 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QA 19-20.pdf25 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QA 20-21.pdf25 Feb 2022
PAN CardFile: Pan card.pdf12 Jan 2022
Declaration about Commencement CertificateFile: Declration about CC.pdf12 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 210112 Form1 Q3 21-22.pdf12 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 5 CA CERTIFIED-4 20-21.pdf12 Jan 2022
Disclosure of sold/ booked inventoryFile: 1 Disclosure of sold Inventory.pdf12 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 CA CERTIFIED-1 17-18.pdf12 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 CA CERTIFIED-2 18-19.pdf12 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 CA CERTIFIED-3 19-20.pdf12 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 CA CERTIFIED-4 20-21.pdf12 Jan 2022
Building plan approvalFile: Sanction Plan.pdf19 Aug 2021
Building Plan Approval (IOD)File: Sanction Plan.pdf19 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf19 Aug 2021
Building plan approvalFile: Layout.pdf23 Nov 2018
Building Plan Approval (IOD)File: Layout.pdf23 Nov 2018
Building plan approvalFile: Sanctioned Layout-.pdf4 Oct 2017
Layout approvalFile: Sanctioned Layout-.pdf4 Oct 2017
Copy of the legal title reportFile: Tital search report- 1.pdf4 Oct 2017
Details of encumbrancesFile: Encurmbnces Certificate.pdf4 Oct 2017
Copy of Layout Approval (in case of layout)File: Sanctioned Layout-.pdf4 Oct 2017
Building Plan Approval (IOD)File: Sanctioned Layout-.pdf4 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf4 Oct 2017
Declaration in FORM BFile: Form B.pdf4 Oct 2017
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf4 Oct 2017
Proforma of Allotment letterFile: Model Agreement.pdf4 Oct 2017

How this compares with Solapur

15%of Solapur projects moved their completion datethis one moved by 12 months
39%of Solapur registrations have lapsed or been cancelledthis one is completed

Computed across the 550+ Solapur projects on ReraGenie, from their own filings.

Keep Shree Varad Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shelagi550+ in Solapur

2 kmShree Varad ResidencyCompleted 2Lapsed / revoked 3Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 8 registered projects within 2 km.

Builder: Mr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty

Mr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty has 1 registration on MahaRERA, including Shree Varad Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Solapur district page.

Frequently asked questions

What are my rights if Shree Varad Residency is delayed beyond 29 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Varad Residency?

The registered promoter entity is Mr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Varad Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shree Varad Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Varad Residency?

The professionals named in the filing: Architect: Amit Shetty; Engineer: Rahul Darvekar & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Varad Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Varad Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Varad Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.