Home / Browse projects / Mumbai Suburban, Maharashtra / SHREE VALLABH

Registered No litigation declared Others project

SHREE VALLABH

By MAMTORA ENTERPRISE

RG-MH-68310 · RERA P51800047875 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
4 of 11Construction stages donefurthest along: External plumbing and external plaster, 95%
58 of 64Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 117 documents Report an error

SHREE VALLABH is a Others project by MAMTORA ENTERPRISE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800047875 on 1 Dec 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 12 months from the original filing. 6 of the 64 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSHREE VALLABH
  • TypeOthers
  • Location
    • MATHURADAS ROAD
    • KANDIVALI WEST
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800047875
  • ReraGenie IDRG-MH-68310

Builder

  • NameMAMTORA ENTERPRISE
  • Entity typePartnership
  • PartnersHITESH JIVANDAS LAL, MITESH ASHOK LAL, NATWARLAL MATHURADAS LAL
  • PartnersBHARAT LAXMIDAS LAL, NIYANT NATWARLAL LAL, PRATIK HITESH LAL
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects2 →

Key dates

1 months past promisethis monthRegisteredDec 2022First promiseSep 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Dec 2022
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Sep 2025)
  • Buildings1 building record
  • Documents filed117 files

Current status

9%6 of 64 units booked
79.7%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE VALLABHNA1514491564

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 95%.

SHREE VALLABH: 70% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises81%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks81%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.29%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed43

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots43
Closed/Covered43

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,750 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Jul 2025
LandownerVillageDistrict
M/S. KANDIVLI SAMIR CO-OP HOUSING SOCIETYBorivaliMumbai Suburban
MR. SAMIR DHIRENDRA TANNABorivaliMumbai Suburban
SMT. SHOBHA TANNABorivaliMumbai Suburban
MR. VILESH TANNABorivaliMumbai Suburban
MRS. VEENA SHAHBorivaliMumbai Suburban
MISS. FALGUNI TANNABorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI3601.92
Proposed, not sanctioned1,801 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKANDIVALI WEST
Estimated costRs 14.50 cr
Cost incurredRs 11.55 cr
Work done79.68%
BuildingWingEstimatedIncurred
SHREE VALLABHNARs 14.21 crRs 11.39 cr
-NARs 29.00 lakhRs 16.25 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCHIRAG S RAYANI
EngineerCSE CONSULTANT RAJESH SHAH
Chartered AccountantVAYEDA AND ASSOCIATES
Chartered AccountantHEM KETAN DAVE
PartnerRole in project
MAMTORA ENTERPRISE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA29092517981Sep 2025 → Sep 2026

Reason as filed by the promoterTHE CONSTRUCTION OF THE PROJECT UNDER REFERENCE IS DELAY DUE TO DELAY IN PROCESS FOR OBTAINED FURTHER APPROVAL FROM CONCERNED AUTHORITY,

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12603030Samir TannaMAMTORA ENTERPRISE22/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Nov 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed117

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf20 Jul 2026
Commencement certificateFile: SHREE VALLABH FULL CC.pdf20 Apr 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf20 Apr 2026
Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf20 Apr 2026
Withdrawal Update Form 3File: FORM 3 C A CERTIFICATE.pdf20 Apr 2026
Withdrawal Update Form 1File: FORM-1.pdf14 Jan 2026
Withdrawal Update Form 2File: FORM-2.pdf14 Jan 2026
Withdrawal Update Form 3File: FORM- 3.pdf14 Jan 2026
Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf11 Nov 2025
Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf11 Nov 2025
Withdrawal Update Form 3File: CA CERTIFICATE.pdf11 Nov 2025
Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf20 Oct 2025
Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf20 Oct 2025
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf20 Oct 2025
Form 2A (FY 2024-2025)File: FORM 2A SITE SUPERVISOR CERTIFICATE.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5 FY 2024-25 SIGNED.pdf22 Sep 2025
Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf19 Jul 2025
Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf19 Jul 2025
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf19 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf21 Apr 2025
Building plan approvalFile: 2440358Amendletter_signed 03-01-2025.pdf19 Apr 2025
Building plan approvalFile: PLAN 03-01-2025 1-2.pdf19 Apr 2025
Building plan approvalFile: PLAN 03-01-2025 3-4.pdf19 Apr 2025
Building plan approvalFile: PLAN 03-01-2025 5-6.pdf19 Apr 2025
Building plan approvalFile: PLAN 03-01-2025 7-8.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf19 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: 2459698_FurtherCC_signed.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 2440358Amendletter_signed 03-01-2025.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 03-01-2025 1-2.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 03-01-2025 3-4.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 03-01-2025 5-6.pdf19 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 03-01-2025 7-8.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD inventory.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf21 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD INVENTORY.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Q1.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Q2.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Q1.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Q2.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Q1.pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Q2.pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 FY 2023-24 Mamtora Enterprise Signed.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 31-3-24.pdf4 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 31-3-24.pdf4 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 31-3-24.pdf4 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 31-03-2024.pdf4 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE Q3 ME.pdf19 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE Q3.pdf19 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 CA CERTIFICATE Q3 ME.pdf19 Feb 2024
Building plan approvalFile: IOD 17-07-2023 Front Page.pdf17 Feb 2024
Building plan approvalFile: IOD PLAN 13-10-2023 1.pdf17 Feb 2024
Building plan approvalFile: IOD PLAN 13-10-2023 1.pdf17 Feb 2024
Building plan approvalFile: IOD PLAN 1.pdf17 Feb 2024
Building plan approvalFile: IOD PLAN 2.pdf17 Feb 2024
Building plan approvalFile: IOD PLAN 3.pdf17 Feb 2024
Building plan approvalFile: IOD PLAN 4.pdf17 Feb 2024
Building plan approvalFile: IOD PLAN 5.pdf17 Feb 2024
Building plan approvalFile: IOD PLAN 7.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD 17-07-2023 Front Page.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD PLAN 13-10-2023 1.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD PLAN 13-10-2023 1.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD PLAN 1.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD PLAN 2.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD PLAN 3.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD PLAN 4.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD PLAN 5.pdf17 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD PLAN 7.pdf17 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: CC 25-08-2023.pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM- 1 architect CERTIFICATE 31-03-2023.pdf9 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM- 1 Architect CERTIFICATE 30-06-2023.pdf9 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM- 1 Architect CERTIFICATE 30-09-2023.pdf9 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE 31-03-2023.pdf9 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F0RM 2 ENGINEER CERTIFICATE 30-06-2023.pdf9 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 30-09-2023 Sign Copy.pdf9 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 CA CERTIFICATE 31-03-2023.pdf9 Jan 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationRegisteredStatusPromisedDelivered
PHASE 1 SHREE NIKUNJP51800005606Borivali, Mumbai SuburbanAug 2017CompletedOct 2018Registered original: Jan 2018Late, Apr 2022

How this compares with Mumbai Suburban

9%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE VALLABH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANDIVALI WEST6,700+ in Mumbai Suburban

2 kmSHREE VALLABHCompleted 149Lapsed / revoked 95Other 149Dot size: filed unitsN

Filed coordinates, straight-line distance. 393 registered projects within 2 km.

Builder: MAMTORA ENTERPRISE

MAMTORA ENTERPRISE has 3 registrations on MahaRERA, including PHASE 1 SHREE NIKUNJ and KANDIVALI JATIN VILLA CHSL. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHREE VALLABH is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE VALLABH?

The registered promoter entity is MAMTORA ENTERPRISE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE VALLABH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHREE VALLABH?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHREE VALLABH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE VALLABH?

The professionals named in the filing: Architect: CHIRAG S RAYANI; Engineer: CSE CONSULTANT RAJESH SHAH; Chartered Accountant: VAYEDA AND ASSOCIATES; Chartered Accountant: HEM KETAN DAVE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE VALLABH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE VALLABH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE VALLABH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.