Home / Browse projects / Sangli, Maharashtra / Shree Spaces
Shree Spaces
RG-MH-16829 · RERA P53100027868 · Last updated on MahaRERA portal: 13 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 15 months past the filed date
- Completion date moved by 12 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shree Spaces is a Others project by Prasad Associates in Sangli, Maharashtra, registered with MahaRERA as P53100027868 on 10 Jan 2021. Possession was promised by 9 Jul 2025 and is now 15 months past that date. The completion date has moved by 12 months from the original filing. 38 of the 72 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameShree Spaces
- TypeOthers
- Location
- Mangalwar Bazar Road
- Sayadhari Nagar
- Sangli Miraj Kupwad (M Corp.)
- Miraj
- Sangli
- 416416
- Pincode416416
- MapView location on Google Maps (as filed on RERA)
- RERA no.P53100027868
- ReraGenie IDRG-MH-16829
Builder
- NamePrasad Associates
- Entity typePartnership
- PartnersBharat Ramdas Rachh, Muralidhar Balappa Sutar, Mahesh Dharamsinh Chandarana
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Jan 2021
- Promised completion9 Jul 2025
- Revised completionRevised to 9 Jul 2025 (originally 31 Jul 2024)
- Buildings1 building record
- Documents filed76 files
Current status
Figures as on 13 May 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Shree Spaces | NA | 10 | 0 | 48 | 24 | 72 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 13 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.
Shree Spaces: 76% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 85% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 13 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed54
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Kiran Baburao Chavan | Sangli Miraj Kupwad (M Corp.) | Sangli |
| Pravin Baburao Chavan | Sangli Miraj Kupwad (M Corp.) | Sangli |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Shree Spaces | NA | Rs 10.50 cr | Rs 10.55 cr |
| - | NA | Rs 30.00 lakh | Rs 30.00 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sachin Kanoje |
| Engineer | Mahesh Chandarana |
| Chartered Accountant | Shajmal Firoz Mullik |
| Chartered Accountant | Shivam Sancheti |
| Partner | Role in project |
|---|---|
| Prasad Associates | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRevised sanction has been obtained from Sangli, Miraj & Kupwad Corporation, Sangli ( sanctioning authority )
Reason as filed by the promoterFull OC is obtained after date of completion of project
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Nov 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Nov 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Jul 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed76
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's certificate form 3.pdf | 13 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate form 3.pdf | 13 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate form 2.pdf | 13 May 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of solf inventory.pdf | 13 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quatity Assurance certificate.pdf | 13 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-.pdf | 21 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers certificate.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 5 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate .pdf | 5 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf | 5 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5_page-0001-compressed.pdf | 3 Jul 2024 |
| Declaration in FORM BFile: Land owner declaration.pdf | 2 Jul 2024 |
| Declaration in FORM BFile: Developer Declaration.pdf | 2 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: GetUserDocumentFileContent_page-0001.pdf | 2 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Annexure B Form 2.pdf | 2 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold,booked inventory.pdf | 2 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA Certificate.pdf | 2 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 arch cert upto dec 2023.pdf | 15 Apr 2024 |
| Declaration in FORM BFile: FORM B 2024 PRASAD PARTNERS.pdf | 12 Apr 2024 |
| Declaration in FORM BFile: FORM B 2024 LAND OWNER.pdf | 11 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022 -23.pdf | 8 Mar 2024 |
| Other - LegalFile: aggr 1171-2024 ss compressed.pdf | 5 Mar 2024 |
| Other - LegalFile: aggr 1172-2024 ss compressed.pdf | 5 Mar 2024 |
| Other - LegalFile: aggr 1173-2024 ss compressed.pdf | 5 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a quality ass 22-23.pdf | 4 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch cert form1.pdf | 29 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch cert form1.pdf | 29 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY JUNE 23.pdf | 29 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg cert form 2.pdf | 28 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca form 3.pdf | 28 Sep 2023 |
| Building plan approvalFile: 3_compressed.pdf | 21 Jul 2023 |
| Building plan approvalFile: 1_compressed (1).pdf | 21 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 3_compressed.pdf | 21 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1_compressed (1).pdf | 21 Jul 2023 |
| Building plan approvalFile: 2_compressed.pdf | 19 Jul 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 2_compressed.pdf | 19 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Muncipal sanction Shree Spaces 1-7.pdf | 19 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2a - engg quality assu 2020-21.pdf | 25 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2a - engg quality assu 2021-22.pdf | 25 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold unsold.pdf | 25 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 - engg cert - feb 2023.pdf | 22 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 - ca - feb 2023_compressed.pdf | 22 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 - ca - feb 2023 (2).pdf | 22 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 arch cert feb 2023.pdf | 18 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - 1.pdf | 16 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - 2.pdf | 16 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA FORM 1 ARCH CERT AUG 2022.pdf | 24 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA ENG CERT AUG 2022.pdf | 23 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA CA FORM 3 AUG 2022.pdf | 23 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT SCANNED AUG 2022 (4).pdf | 22 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE RERA.pdf | 26 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: annexure a architect certificate kanoje scanned copy_compressed.pdf | 24 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: annexure a architect certificate kanoje scanned copy_compressed.pdf | 24 Feb 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: annexure a architect certificate kanoje scanned copy_compressed.pdf | 24 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate final scanned copy_compressed.pdf | 24 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate final scanned copy_compressed.pdf | 24 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA FORM 3.pdf | 24 Feb 2022 |
| Declaration about Commencement CertificateFile: DECLARATION COMMECEMENT CERTIF.pdf | 9 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MAHESH SIR ARCHI CERT_compressed.pdf | 9 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: MAHESH SIR ARCHI CERT_compressed.pdf | 9 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: MAHESH SIR engg certi new.pdf | 9 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Prasad_Ass_Certificate.PDF | 9 Aug 2021 |
| Copy of the legal title reportFile: mahesh (1)_compressed.pdf | 12 Nov 2020 |
| Details of encumbrancesFile: MAHESH 2.pdf | 12 Nov 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: mahesh sir cert.pdf | 6 Nov 2020 |
| Proforma of Allotment letterFile: Prasad Associates letter head-converted.pdf | 5 Nov 2020 |
| Layout approvalFile: shree spaces layout-compressed.pdf | 4 Nov 2020 |
| Building plan approvalFile: Muncipal sanction.pdf | 4 Nov 2020 |
| PAN CardFile: Prasad Associates Pan Card.pdf | 4 Nov 2020 |
| Copy of Layout Approval (in case of layout)File: shree spaces layout-compressed.pdf | 4 Nov 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: Muncipal sanction.pdf | 4 Nov 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: SHREE SPACES COMMENCEMENT CERTIFICATE.pdf | 4 Nov 2020 |
| Declaration in FORM BFile: decleration_compressed (1).pdf | 4 Nov 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shree Spaces Architect Certificate.pdf | 4 Nov 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTI-compressed.pdf | 4 Nov 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sangli
Computed across the 790+ Sangli projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 76 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Shree Spaces on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sayadhari Nagar790+ in Sangli
Filed coordinates, straight-line distance. 184 registered projects within 2 km.
SIDDHI VASTU Puram
SIDDHIVINAYAK PLATINUM
SEVEN HILLS
SHRI HARIPRIYA BUILDERS AND DEVELOPERS LLP
EVARA ESTATE
DSDB REALTY LLP
VISION CITY
VISION GROUP
NAKSHTRA
SHIV-NAKSHTRA DEVELOPERS LLP
SAHYADRISIDDHI
SAHYADRIDEVELOPERS
See every Sangli project, with the district possession charts
Builder: Prasad Associates
Prasad Associates has 1 registration on MahaRERA, including Shree Spaces. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.
Frequently asked questions
What does it mean that Shree Spaces shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Shree Spaces is delayed beyond 9 Jul 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shree Spaces?
The registered promoter entity is Prasad Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shree Spaces?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Shree Spaces?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shree Spaces?
The professionals named in the filing: Architect: Sachin Kanoje; Engineer: Mahesh Chandarana; Chartered Accountant: Shajmal Firoz Mullik; Chartered Accountant: Shivam Sancheti. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shree Spaces?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback