Home / Browse projects / Nagpur, Maharashtra / SHREE RESIDENCY
SHREE RESIDENCY
RG-MH-03906 · RERA P50500032454 · Last updated on MahaRERA portal: 21 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREE RESIDENCY is a Plotted project by WAINGANGA ASSOCIATE in Nagpur, Maharashtra, registered with MahaRERA as P50500032454 on 4 Jan 2022. Possession is promised by 1 Dec 2026. 19 of the 37 units on this registration are recorded sold or booked.
At a glance
Project
- NameSHREE RESIDENCY
- TypePlotted
- Location
- SHANKARPUR
- GRAMPANCHAYAT SHANKARPUR
- Nagpur (Rural)
- Nagpur
- 441108
- Pincode441108
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500032454
- ReraGenie IDRG-MH-03906
Builder
- NameWAINGANGA ASSOCIATE
- Entity typePartnership
- PartnersSHRIHARI JIYALAL CHAUDHARI, PRASHANT HARIBHAU KANOJE
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Jan 2022
- Promised completion1 Dec 2026
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed39 files
Current status
Figures as on 21 Feb 2025, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 21 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ASPECT DESIGN |
| Engineer | B P GOHAR |
| Chartered Accountant | CA SAROJ VIDHANI |
| Partner | Role in project |
|---|---|
| WAINGANGA ASSOCIATE | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Dec 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Dec 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 1 Dec 2026
Documents filed39
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: Disclosure.pdf | 21 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: shree residency form 1.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: shree residency form 2.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: shree residency form 1.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: shree residency form 2.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CRTIFICATE1.pdf | 31 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERTIFICATE1.pdf | 31 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: signed Shree Residency Form 3.pdf | 24 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHREE RESIDENCY MARCH 2023.pdf | 29 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fORM 1 SHREE RESIDENCY JUNE 2023.pdf | 29 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: fORM 1 SHREE RESIDENCY SEPT 2023.pdf | 29 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHREE RESIDENCY MARCH 2023.pdf | 29 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUNE SHREE RESIDENCY 2023.pdf | 29 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHREE RESIDENCY SEPT 2023.pdf | 29 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure .pdf | 29 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Shree Residency March_compressed.pdf | 29 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Shree Residency June _compressed.pdf | 29 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Shree Residency Sept.pdf | 29 Nov 2023 |
| Building plan approval or NA orderFile: Shree residency final map (3).pdf | 18 Dec 2021 |
| Details of encumbrancesFile: Encumburance Certificate (2).pdf | 18 Dec 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Shree residency final map (3).pdf | 18 Dec 2021 |
| Declaration about Commencement CertificateFile: Format D New (2).pdf | 18 Dec 2021 |
| CERSAI detailsFile: DEBTORS BASED SERCHED REPORT.pdf | 18 Dec 2021 |
| CERSAI detailsFile: CERSAI_Search_Report_200226086453_For_Asset_Based_Search_18_12_2021_12_02_37_739.pdf | 18 Dec 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form No 1_compressed.pdf | 9 Dec 2021 |
| Layout approvalFile: Parishist B_compressed.pdf | 6 Dec 2021 |
| PAN CardFile: FIRM PAN_compressed.pdf | 6 Dec 2021 |
| Copy of the legal title reportFile: Formate A- LEGAL TITEL REPORT_compressed.pdf | 6 Dec 2021 |
| Copy of the legal title reportFile: 7-12 Copy in the name of Wainganga Associates_compressed.pdf | 6 Dec 2021 |
| Details of encumbrancesFile: No Encumburance Certificate_compressed.pdf | 6 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: Parishist B_compressed.pdf | 6 Dec 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Parishist B_compressed.pdf | 6 Dec 2021 |
| Declaration in FORM BFile: form B.pdf | 6 Dec 2021 |
| CERSAI detailsFile: CERSAI UNDERTAKING.pdf | 6 Dec 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 6 Dec 2021 |
| Proforma of Allotment letterFile: allotment_leter DRAFT.pdf | 6 Dec 2021 |
| Proforma of Allotment letterFile: AGREEMENT FORMATE.pdf | 6 Dec 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 39 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SHREE RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GRAMPANCHAYAT SHANKARPUR2,800+ in Nagpur
Filed coordinates, straight-line distance. 50 registered projects within 2 km.
Kanher Nagri Developers
KANHER NAGRI DEVELOPERS
MAHALAXMI NAGAR 6
MAHALAXMI ESTATE
MAHALAXMI NAGAR 4
PADMALAXMI DEVELOPERS
Moreshwar park 4
PRASANNA PLANNERS
PRIME PLATINUM
UMAKANT VITTHAL MENDHE
MAULI NAGAR 8
MAULI INFRATECH
See every Nagpur project, with the district possession charts
Builder: WAINGANGA ASSOCIATE
WAINGANGA ASSOCIATE has 2 registrations on MahaRERA, including SHREE RESIDENCY and Kalash Vatika. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if SHREE RESIDENCY is delayed beyond 1 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREE RESIDENCY?
The registered promoter entity is WAINGANGA ASSOCIATE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREE RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREE RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREE RESIDENCY?
The professionals named in the filing: Architect: ASPECT DESIGN; Engineer: B P GOHAR; Chartered Accountant: CA SAROJ VIDHANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.