Home / Browse projects / Mumbai Suburban, Maharashtra / Shree Ram Residency

Registered No litigation declared Residential / Group Housing project

Shree Ram Residency

By ELITE HOUSING LLP

RG-MH-07097 · RERA P51800054905 · Last updated on MahaRERA portal: 26 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 completed earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
9 of 11Construction stages donefurthest along: Basement (if any), 0%
9 of 16Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

Shree Ram Residency is a Residential / Group Housing project by ELITE HOUSING LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800054905 on 15 Feb 2024. Possession is promised by 31 Dec 2026. 7 of the 16 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameShree Ram Residency
  • TypeResidential / Group Housing
  • Location
    • 14th Road
    • Khar West
    • Greater Mumbai (M Corp.) (Part) (802794)
    • Mumbai
    • Mumbai Suburban
    • 400052
  • Pincode400052
  • RERA no.P51800054905
  • ReraGenie IDRG-MH-07097

Builder

  • NameELITE HOUSING LLP
  • Entity typePartnership
  • GSTIN27AAHFE2538C1ZQ
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersAmit Haresh Lala, Haresh Mohan Lala
  • Other registrations3 more →
  • Completed1 of 4
  • Declared earlier projects3 →

Key dates

this monthRegisteredFeb 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Feb 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed76 files

Current status

44%7 of 16 units booked
98.0%Work done, per cost certificate

Figures as on 26 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shree Ram ResidencyNA6616016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

Shree Ram Residency: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed21

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots21
Closed/Covered21

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area528 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jul 2025
LandownerVillageDistrict
Prem Mayaram BulchandaniGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban
Ramesh Mayaram BulchandaniGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban
Deepak Mayaram BulchandaniGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban
Mrs Bhavna Kishore BulchandaniGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban
Mohit Kishore BulchandaniGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1566.56
Proposed, not sanctioned1,567 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC Bank, Gabbana House, 15th Road, Khar West Mumbai- 400052
Estimated costRs 12.25 cr
Cost incurredRs 12.00 cr
Work done97.96%
BuildingWingEstimatedIncurred
Shree Ram ResidencyNARs 11.50 crRs 11.25 cr
-NARs 75.00 lakhRs 75.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPushkar Consultants
EngineerKrunal P Kamothi
Chartered AccountantA N J K & CO LLP
Chartered AccountantG N Mantri and Associates
PartnerRole in project
ELITE HOUSING LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 June 25.pdf26 Apr 2026
Withdrawal Update Form 1File: FORM 1 June 25.pdf26 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 25.pdf26 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 25.pdf26 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate June 25.pdf26 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate June 25.pdf26 Apr 2026
Withdrawal Update Form 1File: FORM 1 June 25.pdf10 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 25.pdf10 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate June 25.pdf10 Jan 2026
Withdrawal Update Form 1File: FORM 1 June 25.pdf6 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 25.pdf6 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate June 25.pdf6 Jan 2026
Withdrawal Update Form 1File: FORM 1 June 25.pdf27 Nov 2025
Withdrawal Update Form 1File: FORM 1 June 25.pdf27 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 25.pdf27 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 25.pdf27 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate June 25.pdf27 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate June 25.pdf27 Nov 2025
Withdrawal Update Form 1File: FORM 1 June 25.pdf26 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 25.pdf26 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate June 25.pdf26 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 FY 2024-25 - Signed.pdf24 Oct 2025
Withdrawal Update Form 1File: FORM 1 June 25.pdf18 Jul 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 25.pdf18 Jul 2025
Withdrawal Update Form 3File: Form 3 CA Certificate June 25.pdf18 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Final.pdf2 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate - Signed.pdf2 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - March 2025.pdf2 May 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf2 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate - Signed.pdf30 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - SRH-Signed_Compressed.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer certificate.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory_Signed.pdf20 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5_SRH_FY 2023-24_Signed.pdf18 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5_SRH_FY 2023-24_Signed.pdf18 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate SRH- sign.pdf24 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer certificate.pdf24 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory SRH.pdf24 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf16 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of inventory SRH.pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certficate SRH - Sign_11zon.pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf28 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf28 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A SRH.pdf28 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf28 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Form-3_Elite Housing LLP_compressed.pdf28 May 2024
Layout approvalFile: Drawing.pdf18 Mar 2024
Building plan approvalFile: Drawing.pdf18 Mar 2024
Copy of Layout Approval (in case of layout)File: Drawing.pdf18 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: Drawing.pdf18 Mar 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report final.pdf2 Feb 2024
Proforma of Agreement for saleFile: FSA with Deviation.pdf18 Jan 2024
Copy of the legal title reportFile: FINAL TITLE CERTIFICATE.pdf7 Dec 2023
Layout approvalFile: SRH -1.pdf10 Nov 2023
Building plan approvalFile: SRH-2.pdf10 Nov 2023
PAN CardFile: Elite Hsg LLP - PAN.pdf10 Nov 2023
Details of encumbrances concerned to FinanceFile: Encumbrance certificate with Finance and Legal.pdf10 Nov 2023
Details of encumbrances concerned to LegalFile: Encumbrance certificate with Finance and Legal.pdf10 Nov 2023
Copy of Layout Approval (in case of layout)File: SRH -1.pdf10 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: SRH-2.pdf10 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf10 Nov 2023
Declaration about Commencement CertificateFile: CC Declaration.pdf10 Nov 2023
Declaration in FORM BFile: Form B Declaration by Promoter with Authority Letter.pdf10 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate.pdf10 Nov 2023
CERSAI detailsFile: Cersai Asset Based Report_11zon.pdf10 Nov 2023
CERSAI detailsFile: Cersai Declaration.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate SRH.pdf10 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest Mr Amit Lala.pdf10 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest Mr Haresh Lala.pdf10 Nov 2023
Proforma of Allotment letterFile: Proforma of Allotment letter.pdf10 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration on Seperate bank account.pdf10 Nov 2023
Deviation Report with respect to Allotment letterFile: Deviation in Allotment letter.pdf10 Nov 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SPECTRUMPR1180002502121KHAR WEST, Mumbai Suburban29Jan 2026OngoingDec 2030Not due yet
VistaP51800046797BANDRA WEST, Mumbai Suburban-Sep 2022CompletedDec 2025Apr 2024

How this compares with Mumbai Suburban

44%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shree Ram Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khar West6,700+ in Mumbai Suburban

Builder: ELITE HOUSING LLP

ELITE HOUSING LLP has 4 registrations on MahaRERA, including Vista and Shree Ram Residency. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Shree Ram Residency is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Ram Residency?

The registered promoter entity is ELITE HOUSING LLP, a partnership as per the filing. Its GSTIN 27AAHFE2538C1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Ram Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shree Ram Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Ram Residency?

The professionals named in the filing: Architect: Pushkar Consultants; Engineer: Krunal P Kamothi; Chartered Accountant: A N J K & CO LLP; Chartered Accountant: G N Mantri and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Ram Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Ram Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Ram Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.