Home / Browse projects / Nagpur, Maharashtra / SHREE MANSION
SHREE MANSION
RG-MH-07904 · RERA P50500014642 · Last updated on MahaRERA portal: 11 Apr 2023
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 3 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 6 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREE MANSION is a Residential / Group Housing project by SACHIN ASHOK KHARE in Nagpur, Maharashtra, registered with MahaRERA as P50500014642 on 20 Dec 2017. The registration is recorded completed; possession was promised by 30 Jun 2018.
At a glance
Project
- NameSHREE MANSION
- TypeResidential / Group Housing
- Location
- LAXMI NAGAR
- AJNI
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440022
- Pincode440022
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500014642
- ReraGenie IDRG-MH-07904
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on20 Dec 2017
- Promised completion30 Jun 2018
- Revised completionNone
- Buildings1 building record
- Documents filed25 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREE MANSION | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SHREE MANSION: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 11 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAURABH JAGDALE |
| Engineer | AAJ ENGINEERS |
| Partner | Role in project |
|---|---|
| SACHIN ASHOK KHARE | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Nov 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Nov 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Aug 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Nov 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Jan 2020
Documents filed25
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: DocScanner Apr 11, 2023 5-01 PM (1).pdf | 11 Apr 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: SHREE MANSION-converted_Compressed.pdf | 2 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: shree mansion.pdf | 16 Mar 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECT CERTIFICATE- R9.pdf | 29 Jan 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: parwani oc letter.pdf | 27 Jan 2020 |
| Building plan approvalFile: scan422 (1).pdf | 7 Aug 2018 |
| Building plan approvalFile: scan421 (1).pdf | 7 Aug 2018 |
| Building Plan Approval (IOD)File: scan422 (1).pdf | 7 Aug 2018 |
| Building Plan Approval (IOD)File: scan421 (1).pdf | 7 Aug 2018 |
| Building plan approvalFile: Sanction Plan.pdf | 11 Dec 2017 |
| Details of encumbrancesFile: SEARCH REPORT SACHINKHARE R-9.pdf | 11 Dec 2017 |
| Building Plan Approval (IOD)File: Sanction Plan.pdf | 11 Dec 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Ongoing Project.pdf | 11 Dec 2017 |
| OtherFile: Allotment Letter_.pdf | 11 Dec 2017 |
| OtherFile: Sanction Plans.pdf | 11 Dec 2017 |
| OtherFile: correction Deed for Khasara NO 346.pdf | 11 Dec 2017 |
| OtherFile: FLATS DETAILS BY ARCHITECT12122017.pdf | 11 Dec 2017 |
| Layout approvalFile: declaration for not having layout11122017.pdf | 25 Nov 2017 |
| PAN CardFile: sachin khare.pdf | 25 Nov 2017 |
| Copy of Layout Approval (in case of layout)File: declaration for not having layout11122017.pdf | 25 Nov 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Comencement Cert.pdf | 25 Nov 2017 |
| Declaration in FORM BFile: form B declaration07122017.pdf | 25 Nov 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE25112017.pdf | 25 Nov 2017 |
| Proforma of Allotment letterFile: AGREEMENT-RERA-SHRI MANSION--STD.pdf | 25 Nov 2017 |
| Copy of the legal title reportFile: SEARCH REPORT SHREE CONSTRUCTION.pdf | 24 Nov 2017 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHREE MANSION | R-9 LAXMI NAGAR NAGPUR | 18 | Completed | Jun 2018 | Jun 2018 |
| SHREE RESIDENCY | LAXMI NAGAR | 12 | Completed | Feb 2017 | Feb 2017 |
| SHREEE RESIDENCY 1 | SONEGAON | 6 | Completed | Oct 2012 | Oct 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 25 filed documents as one ZIP, foldered, with a manifest
Keep SHREE MANSION on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AJNI2,800+ in Nagpur
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
VEDANT BERYL
NANIS BUILDCON PRIVATE LIMITED
SHRILA APARTMENTS
MAXX BUILDER AND DEVELOPERS
USHA DEEPAK THOOL
USHA DEEPAK THOOL
SHREEKRISHNA HEMPRABHA
SHREE KRISHNA INFRAVENTURES
PIONEER ORION
PIONEER INFRASTRUCTURES COMPANY PRIVATE LI
SAPHALYA
DELTA DEVELOPERS
See every Nagpur project, with the district possession charts
Builder: SACHIN ASHOK KHARE
SACHIN ASHOK KHARE has 7 registrations on MahaRERA, including SHREE MANSION and SHREE CHANDRIKA MANSION. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if SHREE MANSION is delayed beyond 30 Jun 2018?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREE MANSION?
The registered promoter entity is SACHIN ASHOK KHARE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREE MANSION?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREE MANSION?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREE MANSION?
The professionals named in the filing: Architect: SAURABH JAGDALE; Engineer: AAJ ENGINEERS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE MANSION?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback