ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / SAPHALYA

Registration lapsed No litigation declared Residential / Group Housing project

SAPHALYA

By DELTA DEVELOPERS

RG-MH-21901 · RERA P50500047154 · Last updated on MahaRERA portal: 3 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
9 of 11Construction stages donefurthest along: Basement (if any), 0%
12 of 32Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

SAPHALYA is a Residential / Group Housing project by DELTA DEVELOPERS in Nagpur, Maharashtra, registered with MahaRERA as P50500047154 on 10 Oct 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 20 of the 32 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSAPHALYA
  • TypeResidential / Group Housing
  • Location
    • the Scientific Co-Op Housing Society Limited
    • Laxmi Nagar
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440022
  • Pincode440022
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500047154
  • ReraGenie IDRG-MH-21901

Builder

  • NameDELTA DEVELOPERS
  • Entity typePartnership
  • PartnerCHAITALI NARENDRA SATPUTE
  • Other registrations5 more →
  • Completed3 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

10 months past promisethis monthRegisteredOct 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Oct 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed85 files

Current status

62%20 of 32 units booked
60.6%Work done, per cost certificate

Figures as on 3 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAPHALYANA9832032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

SAPHALYA: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 3 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed117

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots117
Closed/Covered104
Open Space13

Land and ownership18

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,195 sq m
Land owned byThe promoter, with other names on the file
Named landowners18
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Oct 2025
LandownerVillageDistrict
ROHINI SUDHAKAR KALENagpur (M Corp.)Nagpur
VINEET VINAYAK KHERNagpur (M Corp.)Nagpur
RAJESHWAR GOPAL BHAKEYNagpur (M Corp.)Nagpur
GIRIJA JITENDRA JOSHINagpur (M Corp.)Nagpur
USHA PRABHAKAR JAVKHEDKARNagpur (M Corp.)Nagpur
MANGESH PRABHAKAR JAVKHEDKARNagpur (M Corp.)Nagpur
SUNITA DATTATRAYA KULKARNINagpur (M Corp.)Nagpur
AMITABH DATTATRAYA KULKARNINagpur (M Corp.)Nagpur
ASHUTOSH DATTATRAYA KULKARNINagpur (M Corp.)Nagpur
ABHIJEET DATTATRAYA KULKARNINagpur (M Corp.)Nagpur
CHANDRIKA PRANSHANKAR JOSHINagpur (M Corp.)Nagpur
JIGNESH PRANSHANKAR JOSHINagpur (M Corp.)Nagpur
DEEPAK DATTATRAYA BHAVENagpur (M Corp.)Nagpur
SANDHYA KRISHNARAO PALSODKARNagpur (M Corp.)Nagpur
RAJIV VINAYAK RAOLENagpur (M Corp.)Nagpur
PRASAD RAMESH KOTESHWARNagpur (M Corp.)Nagpur
BASANTKUMAR ANANTLAL TIWARINagpur (M Corp.)Nagpur
NITIN DAMODAR LABHENagpur (M Corp.)Nagpur

Approvals and building plan

Sanctioning authorityNagpur Municipal Corporation (NMC)
Permissible FSI4258.76
Proposed, not sanctioned4,255 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDharampeth Nagpur
Estimated costRs 10.73 cr
Cost incurredRs 6.50 cr
Work done60.6%
BuildingWingEstimatedIncurred
SAPHALYANARs 10.73 crRs 6.50 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAGRASEN ARCHITECTS
EngineerTEJASHREE GADODIA
Chartered AccountantASHISH AGARWAL
Chartered AccountantSUMIT R CHANDWANI
PartnerRole in project
DELTA DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf3 Jul 2026
Withdrawal Update Form 2File: FORM 2-Engineer Certificate.pdf3 Jul 2026
Withdrawal Update Form 3File: Form 3 CA Certificate.pdf3 Jul 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate.pdf30 Dec 2025
Withdrawal Update Form 2File: FORM 2-Engineer Certificate.pdf30 Dec 2025
Withdrawal Update Form 3File: Form 3 CA Certificate.pdf30 Dec 2025
Withdrawal Update Form 1File: FORM_1-Architect_Certificate_Saphalya.pdf10 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf10 Oct 2025
Withdrawal Update Form 3File: CA certificate June 25.pdf10 Oct 2025
Form 5 (FY 2024-2025)File: SAPHALAYA FORM 5 24-25.pdf6 Oct 2025
Form 1File: FORM 1.pdf5 Aug 2025
Form 2File: FORM 2.pdf5 Aug 2025
Form 3File: Form 3.pdf5 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory.pdf5 Aug 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate mar25.pdf4 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Architect Certificate.pdf2 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate Saphalya mar25.pdf2 May 2025
Disclosure of sold/ booked inventoryFile: Sold Book.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM_1-Architect_Certificate final.pdf5 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER DEC 24 CERT SAPHALYA SIGNED.pdf5 Mar 2025
Disclosure of sold/ booked inventoryFile: New sold book (2).pdf5 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca certificate Saphalya Dec24 signed.pdf4 Mar 2025
Disclosure of sold/ booked inventoryFile: NEW SOLD BOOK FINAL.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Saphalya June24 (1).pdf29 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Saphalya Sept24 (1).pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: saphalya june 24 sold book.pdf23 Nov 2024
Disclosure of sold/ booked inventoryFile: saphalya sold sept24.pdf23 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate June 24 saphalya signed (1).pdf22 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Sept 24 saphalya signed (1).pdf22 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch mar 24 saphalya.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch jun 24 saphalya.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch sep 24 saphalya.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SAPHALYA 23-24.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg cert saphalya mar24 (1).pdf19 Aug 2024
Disclosure of sold/ booked inventoryFile: sold book mar 24.pdf19 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Saphalaya CA Cert Mar24 STAMP.pdf19 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 5 SAPHALYA Form 5 (1).pdf19 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Saphalya (Dec 23).pdf30 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Saphalya (Dec 22).pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Saphalya (Mar 23).pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Saphalya (June 23).pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Saphalya (Sep 23).pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (Dec 2022) signed.pdf5 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (March 2023) signed.pdf5 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate (June 2023) signed.pdf5 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate (Sep 2023) signed.pdf5 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate (DEC 2023 signed.pdf5 Apr 2024
Declaration about Commencement CertificateFile: SAPHALYA FORM D DEC 22.pdf21 Mar 2024
Declaration about Commencement CertificateFile: SAPHALYA FORM D MAR 23.pdf21 Mar 2024
Declaration about Commencement CertificateFile: SAPHALYA FORM D JUNE 23.pdf21 Mar 2024
Declaration about Commencement CertificateFile: SAPHALYA FORM D JUNE 23.pdf21 Mar 2024
Declaration about Commencement CertificateFile: SAPHALYA FORM D SEP 23.pdf21 Mar 2024
Declaration about Commencement CertificateFile: SAPHALYA FORM D DEC 23.pdf21 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAPHALYA ARCH CERT DEC 22.pdf21 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAPHALYA ARCH CERT MAR 23.pdf21 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAPHALYA ARCH CERT JUN 23.pdf21 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAPHALYA ARCH CERT SEP 23.pdf21 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAPHALYA ARCH CERT DEC 23.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: SAPHALYA SOLD BOOK IN DEC 22.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: SAPHALYA SOLD BOOK IN MAR 23.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: SAPHALYA SOLD BOOK IN JUNE 23.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: SAPHALYA SOLD BOOK IN SEP 23.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: SAPHALYA SOLD BOOK IN DEC 23.pdf21 Mar 2024
Other - LegalFile: AFS.pdf27 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SAPHALYA_compressed.pdf21 Sep 2022
CERSAI detailsFile: CERSAI_Report.pdf26 Aug 2022
Layout approvalFile: Building Plan 10001.pdf23 Aug 2022
Layout approvalFile: Building Plan 20001.pdf23 Aug 2022
Building plan approvalFile: Building Plan 10001.pdf23 Aug 2022
Building plan approvalFile: Building Plan 20001.pdf23 Aug 2022
PAN CardFile: Delta pan card_compressed.pdf23 Aug 2022
Copy of the legal title reportFile: Title_Search_compressed.pdf23 Aug 2022
Details of encumbrances concerned to FinanceFile: No encumbrance_Financial.pdf23 Aug 2022
Details of encumbrances concerned to LegalFile: No encumbrance.pdf23 Aug 2022
Copy of Layout Approval (in case of layout)File: Building Plan 10001.pdf23 Aug 2022
Copy of Layout Approval (in case of layout)File: Building Plan 20001.pdf23 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 10001.pdf23 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 20001.pdf23 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf23 Aug 2022
Declaration about Commencement CertificateFile: Declaration about commencement cert.pdf23 Aug 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
VINAYAK APPTLAXMI NAGAR NAGPUR24CompletedAug 2021Aug 2021

How this compares with Nagpur

62%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is among them

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAPHALYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Laxmi Nagar2,800+ in Nagpur

2 kmSAPHALYACompleted 43Lapsed / revoked 20Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 124 registered projects within 2 km.

Builder: DELTA DEVELOPERS

DELTA DEVELOPERS has 6 registrations on MahaRERA, including KESHAO RUKHMINI APARTMENT and SHREE VINAYAK APPARTMENT. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What does it mean that SAPHALYA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SAPHALYA is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAPHALYA?

The registered promoter entity is DELTA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAPHALYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SAPHALYA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAPHALYA?

The professionals named in the filing: Architect: AGRASEN ARCHITECTS; Engineer: TEJASHREE GADODIA; Chartered Accountant: ASHISH AGARWAL; Chartered Accountant: SUMIT R CHANDWANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAPHALYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAPHALYA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAPHALYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.