Home / Browse projects / Mumbai Suburban, Maharashtra / SHREE KRISHNA RESIDENCY

Completed No litigation declared Others project

SHREE KRISHNA RESIDENCY

By SHREE KRISHNA DEVELOPERS

RG-MH-46615 · RERA P51800018508 · Last updated on MahaRERA portal: 19 Jan 2023

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 11 other registrations.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Internal walls, 90%
0Complaints at MahaRERAon this registration
Jump to the 109 documents Report an error

SHREE KRISHNA RESIDENCY is a Others project by SHREE KRISHNA DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800018508 on 12 Nov 2018. The registration is recorded completed; possession was promised by 1 Jun 2022.

At a glance

Project

  • NameSHREE KRISHNA RESIDENCY
  • TypeOthers
  • Location
    • JAMNADAS ADUKIA ROAD
    • KANDIVALI WEST MUMBAI
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • RERA no.P51800018508
  • ReraGenie IDRG-MH-46615

Builder

  • NameSHREE KRISHNA DEVELOPERS
  • Entity typePartnership
  • PartnerKRISHNA PRATAP VED
  • Other registrations11 more →
  • Completed7 of 12
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2018PromisedJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on12 Nov 2018
  • Promised completion1 Jun 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed109 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE KRISHNA RESIDENCYNA790000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

SHREE KRISHNA RESIDENCY: 85% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 19 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,027 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3023.96
Proposed, not sanctioned1,615 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchP B NO 7080 POISAR S V ROAD MTNL BUILDING KANDIVALI WEST P O MUMBAI 400067

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectASHWIN R MEHTA
EngineerRAJESH N SHAH
PartnerRole in project
SHREE KRISHNA DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Jun 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 May 2022

Documents filed109

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 109 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrances concerned to FinanceFile: DETAILS OF ENCUMBRANCES.pdf19 Jan 2023
Details of encumbrances concerned to LegalFile: DETAILS OF ENCUMBRANCES.pdf19 Jan 2023
CERSAI detailsFile: CERSAI details.pdf19 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf19 Jan 2023
Proforma of Agreement for saleFile: RERA DRAFT ALLOTTMENT AND MODEL AGREEMENT FOR SALE.pdf19 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: There is no separate bank account hence no details needed to provide including there is no19 Jan 2023
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf19 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to model copy of Agreement.pdf19 Jan 2023
Architect’s Certificate on Completion of Project (Form 4)File: FINAL ALKA FORM 4.pdf31 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL.pdf30 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL.pdf30 May 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FINAL OCCUPANTION CERTIFICATE AND BUILDING COMPLETION CERTIFCIATE 2313282_OC_signed.pdf30 May 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: REGISTRATION OF SOCIETY.pdf30 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL.pdf28 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL.pdf28 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL.pdf28 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL.pdf28 May 2022
Building plan approvalFile: Drawing amenment PAGE 1_compressed.pdf26 May 2022
Building plan approvalFile: Drawing amenment PAGE 2_compressed.pdf26 May 2022
Building plan approvalFile: Drawing amenment PAGE 3_compressed.pdf26 May 2022
Building plan approvalFile: Drawing amenment PAGE 4_compressed.pdf26 May 2022
Building plan approvalFile: Drawing amenment PAGE 5_compressed.pdf26 May 2022
Building plan approvalFile: Drawing amenment PAGE 6_compressed.pdf26 May 2022
Building plan approvalFile: Drawing amenment PAGE 7_compressed.pdf26 May 2022
Building plan approvalFile: Drawing amenment PAGE 8_compressed.pdf26 May 2022
Building Plan Approval (IOD)File: Drawing amenment PAGE 1_compressed.pdf26 May 2022
Building Plan Approval (IOD)File: Drawing amenment PAGE 2_compressed.pdf26 May 2022
Building Plan Approval (IOD)File: Drawing amenment PAGE 3_compressed.pdf26 May 2022
Building Plan Approval (IOD)File: Drawing amenment PAGE 4_compressed.pdf26 May 2022
Building Plan Approval (IOD)File: Drawing amenment PAGE 5_compressed.pdf26 May 2022
Building Plan Approval (IOD)File: Drawing amenment PAGE 6_compressed.pdf26 May 2022
Building Plan Approval (IOD)File: Drawing amenment PAGE 7_compressed.pdf26 May 2022
Building Plan Approval (IOD)File: Drawing amenment PAGE 8_compressed.pdf26 May 2022
Commencement Certificates / NA Order for plotted developmentFile: final Commencement Certificate.pdf26 May 2022
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf26 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM NO 1.pdf18 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Binder1.pdf18 Jan 2022
Certificates of CA (Form 3)File: Binder1.pdf18 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL.pdf9 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL.pdf9 Aug 2021
Certificates of CA (Form 3)File: FINAL.pdf9 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL Binder1.pdf5 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL.pdf5 Apr 2021
Certificates of CA (Form 3)File: FINAL.pdf5 Apr 2021
Building plan approvalFile: 1.pdf16 Jun 2020
Building plan approvalFile: 2.pdf16 Jun 2020
Building plan approvalFile: 3.pdf16 Jun 2020
Building plan approvalFile: 4.pdf16 Jun 2020
Building plan approvalFile: 5-6.pdf16 Jun 2020
Building plan approvalFile: 7.pdf16 Jun 2020
Building Plan Approval (IOD)File: 1.pdf16 Jun 2020
Building Plan Approval (IOD)File: 2.pdf16 Jun 2020
Building Plan Approval (IOD)File: 3.pdf16 Jun 2020
Building Plan Approval (IOD)File: 4.pdf16 Jun 2020
Building Plan Approval (IOD)File: 5-6.pdf16 Jun 2020
Building Plan Approval (IOD)File: 7.pdf16 Jun 2020
Commencement Certificates / NA Order for plotted developmentFile: 2241484Amendletter_signed 24-03-2020 by EE.pdf16 Jun 2020
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FINAL.pdf6 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL.pdf5 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL.pdf5 Mar 2020
Certificates of CA (Form 3)File: FINAL.pdf5 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL.pdf19 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL.pdf19 Dec 2019
Certificates of CA (Form 3)File: FINAL 1.pdf19 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: FINAL.pdf1 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL.pdf23 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL.pdf23 Aug 2019
Certificates of CA (Form 3)File: FINAL.pdf23 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FINAL Binder1.pdf23 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FINAL Binder1.pdf23 Jul 2019
Certificates of CA (Form 3)File: FINAL.pdf23 Jul 2019
Building plan approvalFile: PAGE 1 ALKA LAST APPROVED PLAN DWG (3).pdf1 Mar 2019
Building plan approvalFile: PAGE 2 ALKA FURTHER 16FLR APPROVED PLAN DWG (2).pdf1 Mar 2019
Building plan approvalFile: PAGE 3 ALKA FURTHER 16FLR APPROVED PLAN DWG (2).pdf1 Mar 2019
Building plan approvalFile: PAGE 4 ALKA FURTHER 16FLR APPROVED PLAN DWG (3).pdf1 Mar 2019
Building plan approvalFile: PAGE 5 ALKA FURTHER 16FLR APPROVED PLAN DWG (2).pdf1 Mar 2019
Building Plan Approval (IOD)File: PAGE 1 ALKA LAST APPROVED PLAN DWG (3).pdf1 Mar 2019
Building Plan Approval (IOD)File: PAGE 2 ALKA FURTHER 16FLR APPROVED PLAN DWG (2).pdf1 Mar 2019
Building Plan Approval (IOD)File: PAGE 3 ALKA FURTHER 16FLR APPROVED PLAN DWG (2).pdf1 Mar 2019
Building Plan Approval (IOD)File: PAGE 4 ALKA FURTHER 16FLR APPROVED PLAN DWG (3).pdf1 Mar 2019

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE KRISHNA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANDIVALI WEST MUMBAI6,700+ in Mumbai Suburban

Builder: SHREE KRISHNA DEVELOPERS

SHREE KRISHNA DEVELOPERS has 12 registrations on MahaRERA, including SHREE KRISHNA HEIGHTS and SUNFLOWER. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHREE KRISHNA RESIDENCY is delayed beyond 1 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE KRISHNA RESIDENCY?

The registered promoter entity is SHREE KRISHNA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE KRISHNA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE KRISHNA RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE KRISHNA RESIDENCY?

The professionals named in the filing: Architect: ASHWIN R MEHTA; Engineer: RAJESH N SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE KRISHNA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE KRISHNA RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE KRISHNA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.