SHREE ATHARVAPARK 2 PHASE 1

By ATHARVASHREE BUILDMAT PVT LTD

RG-MH-14170 · RERA P51600031337 · Last updated on MahaRERA portal: 22 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
12 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 95%
18 of 19Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 88 documents Report an error

SHREE ATHARVAPARK 2 PHASE 1 is a Residential / Group Housing project by ATHARVASHREE BUILDMAT PVT LTD in Nashik, Maharashtra, registered with MahaRERA as P51600031337 on 15 Oct 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 1 of the 19 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.

At a glance

Project

  • NameSHREE ATHARVAPARK 2 PHASE 1
  • TypeResidential / Group Housing
  • Location
    • MAKHMALABAD RING ROAD
    • NEAR SHARAD PAWAR APMC MARKET
    • Nashik
    • 422003
  • Pincode422003
  • RERA no.P51600031337
  • ReraGenie IDRG-MH-14170

Builder

  • NameATHARVASHREE BUILDMAT PVT LTD
  • Entity typeCompany
  • DirectorsYOGESH BEDMUTHA, SUNNY PARAKH, CHINTAN MUTHA, AJIT JAIN, PRASHANT BAGMAR, KIRTI JAIN
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2021First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Oct 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2023)
  • Buildings2 building records
  • Documents filed88 files

Current status

5%1 of 19 units booked
75.8%Work done, per cost certificate

Figures as on 22 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE ANA22909
TYPE BNA2010010

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.

TYPE A68%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
TYPE B68%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Open Space19
BuildingOpen SpaceTotal
TYPE A99
TYPE B1010

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area869 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
ANKUR SUNIL KASLIWALNandgaonNashik

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI1271.45
Proposed, not sanctioned1,271 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch51- NEEL KAMAL HOUSE, THATTE NAGAR, COLLEGE ROAD, NASHIK 422005
Estimated costRs 3.10 cr
Cost incurredRs 2.35 cr
Work done75.81%
BuildingWingEstimatedIncurred
TYPE BNARs 2.23 crRs 1.74 cr
TYPE ANARs 77.45 lakhRs 60.67 lakh
-NARs 10.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR PANKAJ JADHAV
EngineerMILIND RATHI
Chartered AccountantCA CHETAN BUMB
Chartered AccountantBhavana Loya
PartnerRole in project
ATHARVASHREE BUILDMAT PVT LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600016832Dec 2023 → Dec 2024

Reason as filed by the promoterThe project “ SHREE ATHARVAPARK 2 PHASE 1 ” has faced unexpected delays in construction due to factors like labour shortage, inclement weather or logistical challenges etc.

EXT51600027614Dec 2023 → Jun 2025

Reason as filed by the promoterThe project “ SHREE ATHARVAPARK 2 PHASE 1 ” has faced unexpected delays in construction due to factors like labour shortage, inclement weather or logistical challenges etc., therefore I hereby am correcting following data fields by filling an extention for the project

EA21112518401Dec 2023 → Dec 2026

Reason as filed by the promoter1.1. Slow Booking- Due To slow Booking and slack market we had to face shortage of funds therefore we were not able to complete the project within Specified time. 2.2. Delay for Labor Commitment :- We also had major setback, on schedule when RCC contractor couldn't provide enough manpower in slab castings, Undiscipline of work, wrong commitments, lack of working, quality etc. they has major setback in work progress overall delay in project some months.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed88

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 88 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q 2Atharvashree Buildmat (Form 1)_0002.pdf22 May 2026
Withdrawal Update Form 1File: Shree Atharvapark 2 Architect Q3.pdf22 May 2026
Withdrawal Update Form 1File: Shree Atharvapark 2 Architect Q4.pdf22 May 2026
Withdrawal Update Form 2File: Q2 tharvashree Buildmat (Form 2)_0001.pdf22 May 2026
Withdrawal Update Form 2File: Shree Atharvapark 2 Engineers Certificate Q3.pdf22 May 2026
Withdrawal Update Form 2File: Shree Atharvapark 2 Engineers Certificate Q4.pdf22 May 2026
Withdrawal Update Form 3File: Q2 Form 3 Phase 2.pdf22 May 2026
Withdrawal Update Form 3File: Atharvashree (Q3).pdf22 May 2026
Withdrawal Update Form 3File: Final Form 3 Q4.pdf22 May 2026
Form 1File: Q1 Atharvashree Buildmat (Form 1)_0001.pdf20 Nov 2025
Form 2File: Q1 Atharvashree Buildmat (Form 2)_0002.pdf20 Nov 2025
Form 3File: Q 1 Atharvashree Buildmat (Form 3)_0002.pdf20 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf20 Nov 2025
Form 5 (FY 2024-2025)File: Row house.pdf30 Sep 2025
Form 1File: The Atharvashree Buildmat Pvt ltd Architech certificate 3 P1.pdf16 Jul 2025
Form 2File: The Atharvashree Buildmat Pvt ltd Engineers Certificate 2 P1.pdf16 Jul 2025
Form 3File: Shree Atharva Park 2 PH 1 Upload.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Atharvashree Park 2 phase 1 sold unsold.pdf16 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold uploaded.pdf25 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations P1_compressed.pdf4 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Atharvashree Buildmat Pvt Ltd P1_0001.pdf29 Mar 2025
Declaration in FORM BFile: 3 Form B Kirti Jain.pdf24 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT PH1 Q2_compressed.pdf24 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Cer Q3 P 1_0001.pdf24 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Shree Atharva Park2 P1 Q2_compressed.pdf24 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Phase 1 Q3_compressed.pdf24 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERTIFICATE PARK 2 PH 1_compressed.pdf24 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase 1.pdf24 Mar 2025
Disclosure of sold/ booked inventoryFile: 1 Sold unsold 31 12 2024.pdf24 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 5 Format A Ph 1.pdf24 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: LO Clarification.pdf24 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Ph 1.pdf24 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: 4 Format B P1.pdf24 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Phase 1 21-22.pdf19 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Phase 1 22-23.pdf19 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Phase 1 23-24.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Cer Q4 P1_0001.pdf5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Crtificate P1.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate P2P1.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1-Phase 1_11zon.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase 1 Engineer -.PDF5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate phase 1.PDF5 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase 1.pdf6 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase 1.pdf6 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 1 Q3 FY 23-24.pdf6 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Park 2 Phase 1.pdf26 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Park 2 Ph 1.PDF26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Park 2 Phase 1.pdf26 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ATHARVASHREE PART 1.PDF30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect RH.pdf12 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RH engineer.pdf12 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: phase 1- Rh.PDF12 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect phase I.PDF15 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers_certificate_Q3_Row_House.pdf15 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE PHASE I 1MB.pdf15 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar RH Q4 21 22.PDF22 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar RH Q1 22-23.PDF22 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar RH Q2 22-23.PDF22 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers_certificate-_new_format-_Phase_I (2).pdf22 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers_certificate_Q1_Row_House.pdf22 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers_certificate_Q2_Row_House.pdf22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park 2 phase I Q4 21-22.PDF22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park 2 phase I Q1 22-23.PDF22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Park 2 phase I Q2 22-23.PDF22 Feb 2023
OtherFile: Letter of Authorisation.PDF21 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Atharvashree Phase-1 RERA Audit FY 21 22.PDF30 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificare PHASE 1.pdf2 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Shree Atharva Park II RH Ph I_compressed.pdf28 Sep 2021
Proforma of Allotment letterFile: SAMPLE SALE FORMAT Phase 1-converted.pdf28 Sep 2021
Layout approvalFile: Row house Type A Layout.pdf21 Sep 2021
Layout approvalFile: Row house Type B layout.pdf21 Sep 2021
Building plan approvalFile: Row house Type A Layout.pdf21 Sep 2021
Building plan approvalFile: Row house Type B layout.pdf21 Sep 2021
PAN CardFile: COMPANY PAN-converted.pdf21 Sep 2021
Copy of the legal title reportFile: Legal Title report.PDF21 Sep 2021
Details of encumbrancesFile: Non Encumbrance Certificate.PDF21 Sep 2021
Copy of Layout Approval (in case of layout)File: Row house Type A Layout.pdf21 Sep 2021
Copy of Layout Approval (in case of layout)File: Row house Type B layout.pdf21 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: Row house Type A Layout.pdf21 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: Row house Type B layout.pdf21 Sep 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SHREE ATHARVA PARK PHASE 1MAKHMALABAD SHIVAR NASHIK29CompletedJun 2021Aug 2020

How this compares with Nashik

5%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 36 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE ATHARVAPARK 2 PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR SHARAD PAWAR APMC MARKET4,100+ in Nashik

Builder: ATHARVASHREE BUILDMAT PVT LTD

ATHARVASHREE BUILDMAT PVT LTD has 2 registrations on MahaRERA, including SHREE ATHARVAPARK 2 PHASE 2 and SHREE ATHARVAPARK 2 PHASE 1. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SHREE ATHARVAPARK 2 PHASE 1 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE ATHARVAPARK 2 PHASE 1?

The registered promoter entity is ATHARVASHREE BUILDMAT PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE ATHARVAPARK 2 PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE ATHARVAPARK 2 PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE ATHARVAPARK 2 PHASE 1?

The professionals named in the filing: Architect: AR PANKAJ JADHAV; Engineer: MILIND RATHI; Chartered Accountant: CA CHETAN BUMB; Chartered Accountant: Bhavana Loya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE ATHARVAPARK 2 PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE ATHARVAPARK 2 PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE ATHARVAPARK 2 PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.