Red flags

  • Completion date moved by 49 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedmoved 49 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 85%
48 of 61Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

SHRADHA RESIDENCY is a Others project by KONARK SHRADHA REALTORS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800027190 on 24 Nov 2020. Possession is promised by 31 Jul 2027. The completion date has moved by 49 months from the original filing. 13 of the 61 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHRADHA RESIDENCY
  • TypeOthers
  • Location
    • J P ROAD
    • ANDHERI
    • WEST
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800027190
  • ReraGenie IDRG-MH-03258

Builder

  • NameKONARK SHRADHA REALTORS
  • Entity typePartnership
  • PartnersRAJESH NEMICHAND JAIN, KAMLESH BABULAL JAIN, CHANDRASHEKHER CHAMPALAL HINGARH

Key dates

this monthRegisteredNov 2020First promiseJun 2023Revised toJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Nov 2020
  • Promised completion31 Jul 2027
  • Revised completionRevised to 31 Jul 2027 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed101 files

Current status

21%13 of 61 units booked
28.1%Work done, per cost certificate

Figures as on 5 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRADHA RESIDENCYNA1110461561

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.

SHRADHA RESIDENCY: 58% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Closed/Covered44

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area904 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jul 2025

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI2785.8
Proposed, not sanctioned780 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAIROLI
Estimated costRs 11.75 cr
Cost incurredRs 3.30 cr
Work done28.09%
BuildingWingEstimatedIncurred
SHRADHA RESIDENCYNARs 9.40 crRs 3.30 cr
-NARs 2.35 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPUSHKAR CONSULTANTS
EngineerPARAS CONSULTANTS
Chartered AccountantNehali & Co
PartnerRole in project
KONARK SHRADHA REALTORS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800024283Jun 2023 → Jun 2026

Reason as filed by the promoterDue to shortage of material and labor not able to complete project please grant us extension till 29/06/2026

EXT51800013596Jun 2023 → Jun 2024

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MONTHS

EA05092622474Jun 2023 → Jul 2027

Reason as filed by the promoter1. We have completed till date work to the extent of 59%. Ground plus Two commercial portion is ready for occupation. 2. Due to slow progress in work, our sales got affected resulting in financial crunch. 3. We want extension for further 12 months to complete the project

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jun 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jul 2027

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Shradha resid_Quality Assurance Certificate.pdf5 Sep 2026
Withdrawal Update Form 1File: Shradha Residency - Architect Certificate.pdf22 Jul 2026
Withdrawal Update Form 1File: form 1.pdf22 Jul 2026
Withdrawal Update Form 2File: Shradha Residency - Engineer Certificate (1).pdf22 Jul 2026
Withdrawal Update Form 2File: form 2.pdf22 Jul 2026
Withdrawal Update Form 3File: Shradha Residency - CA Certificate.pdf22 Jul 2026
Withdrawal Update Form 3File: form 3.pdf22 Jul 2026
Withdrawal Update Form 1File: Shradha Resid Architect Rera Certificate dt 23 01 2026 signed.pdf13 Mar 2026
Withdrawal Update Form 2File: Shradha Resid Engg Certificate till 31 12 25.pdf13 Mar 2026
Withdrawal Update Form 3File: Shradha Residency CACertificate Till Dec 25 Signed.pdf13 Mar 2026
Withdrawal Update Form 1File: Shradha Residency_Architect Certificate till Septu002725_Signed.pdf6 Dec 2025
Withdrawal Update Form 2File: Shradha Residency_Engg Certificate till Septu002725_Signed.pdf6 Dec 2025
Withdrawal Update Form 3File: Shradha Residency_CA Certificate till Septu00272025 Signed.pdf6 Dec 2025
Withdrawal Update Form 1File: form1.pdf4 Dec 2025
Withdrawal Update Form 2File: form2.pdf4 Dec 2025
Withdrawal Update Form 3File: Shradha Resid_Shradha Resid_Form 3 Till June 2025.pdf4 Dec 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf14 Apr 2025
Certificates of CA (Form 3)File: form 3.pdf14 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf14 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 72- Architect Certificate dec 24.pdf18 Feb 2025
Certificates of CA (Form 3)File: Signed CA Certificate - Shradha Residency Dec 24 signed.pdf15 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 72- Engineer Certificate till Dec 2025.pdf14 Jan 2025
Building plan approvalFile: IOD Approved Plan.PDF11 Jan 2025
Building plan approvalFile: IOD Approved Plan.pdf11 Jan 2025
Building plan approvalFile: IOD Approved Plan.pdf11 Jan 2025
Building Plan Approval (IOD)File: IOD Approved Plan.PDF11 Jan 2025
Building Plan Approval (IOD)File: IOD Approved Plan.pdf11 Jan 2025
Building Plan Approval (IOD)File: IOD Approved Plan.pdf11 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 23-24.pdf21 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf14 Oct 2024
Certificates of CA (Form 3)File: form 3.pdf14 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf14 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf14 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf3 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf3 Aug 2024
Certificates of CA (Form 3)File: form 3.pdf3 Aug 2024
Disclosure of sold/ booked inventoryFile: Inventory Discloser.pdf11 Jul 2024
Certificates of CA (Form 3)File: Resigned_CA Certificate - Shradha Residency Mar'24 Resigned.pdf11 Jul 2024
Certificates of CA (Form 3)File: Resigned_CA Certificate.pdf11 Jul 2024
Declaration in FORM BFile: Form B.pdf6 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 23.pdf6 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 24.pdf6 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf9 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf9 May 2024
Certificates of CA (Form 3)File: form 3.pdf9 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect form 1.pdf13 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2.pdf13 Jan 2024
Certificates of CA (Form 3)File: ca form 3.pdf13 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shradha Resid Architect Certificate.pdf16 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shradha Resid Engineering certificate.pdf16 Oct 2023
Certificates of CA (Form 3)File: Signed CA Certificate - Shradha Residency Sep'23.pdf16 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: KSR Architect Certificate till 30 JUNE.pdf18 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: KSR Engineer Certificate till 30 june.pdf18 Aug 2023
Certificates of CA (Form 3)File: KSR CA certificate till 30 june.pdf18 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 SIGNED KSR signed.pdf18 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf12 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf12 May 2023
Certificates of CA (Form 3)File: form 3.pdf12 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance_FY 21-22.pdf2 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect.pdf21 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer.pdf21 Jan 2023
Certificates of CA (Form 3)File: ca certificate.pdf21 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: konarck chandralok residency engineer form 2A 21-22.pdf12 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Chandralok-Architect certificate till Sept 2022.pdf11 Nov 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Chandralok-Engineer certificate Sept 2022.pdf11 Nov 2022
Disclosure of sold/ booked inventoryFile: Chandralok Resid- inventory disclosure.pdf11 Nov 2022
Certificates of CA (Form 3)File: Chandralok-CA Certificate Sept 2022 (1).pdf11 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 CA 21-22 shraddha realtor_V3signed.pdf11 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Chandralok _Quality Assurance_April 20 To March 2021.pdf17 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Chandralok Residancy - FORM 5 FY 20-21.pdf17 Aug 2022
Disclosure of sold/ booked inventoryFile: Chandralok Resid- inventory disclosure.pdf3 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FOPRM 1.pdf2 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGIEER FORM 2.pdf2 Aug 2022
CERSAI detailsFile: Chandralok Cersai Declaration .pdf2 Aug 2022
Certificates of CA (Form 3)File: CA FORM 3.pdf2 Aug 2022
Layout approvalFile: KSR Aproved plan.pdf11 Apr 2022
Copy of Layout Approval (in case of layout)File: KSR Aproved plan.pdf11 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: NEW CC.pdf11 Apr 2022
Declaration about Commencement CertificateFile: CC COVERING LETTER.pdf11 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate form 1.pdf11 Apr 2022

How this compares with Mumbai Suburban

21%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 49 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHRADHA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ANDHERI, WEST6,700+ in Mumbai Suburban

2 kmSHRADHA RESIDENCYCompleted 43Lapsed / revoked 14Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: KONARK SHRADHA REALTORS

KONARK SHRADHA REALTORS has 1 registration on MahaRERA, including SHRADHA RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHRADHA RESIDENCY is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRADHA RESIDENCY?

The registered promoter entity is KONARK SHRADHA REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRADHA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRADHA RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRADHA RESIDENCY?

The professionals named in the filing: Architect: PUSHKAR CONSULTANTS; Engineer: PARAS CONSULTANTS; Chartered Accountant: Nehali & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRADHA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRADHA RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRADHA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.