SHRADDHA SKYLINE

By SHRADDHA DEVELOPERS & REALTORS

RG-MH-06435 · RERA P51800053170 · Last updated on MahaRERA portal: 8 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 7 cases
  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 4 months from the original
4 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 96%
113 of 157Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 174 documents Report an error

SHRADDHA SKYLINE is a Others project by SHRADDHA DEVELOPERS & REALTORS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800053170 on 17 Oct 2023. Possession is promised by 30 Apr 2027. The completion date has moved by 4 months from the original filing. 44 of the 157 units on this registration are recorded sold or booked, and 4 of 22 construction stages are filed complete.

At a glance

Project

  • NameSHRADDHA SKYLINE
  • TypeOthers
  • Location
    • Jambli Gully
    • Borivali West
    • Kanheri
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • RERA no.P51800053170
  • ReraGenie IDRG-MH-06435

Builder

  • NameSHRADDHA DEVELOPERS & REALTORS
  • Entity typePartnership
  • PartnersGUNVANTRAI P VAGHANI, HIREN G VAGHANI, AJAY L SAMANT, VINOD N PATEL, Verendra D Chowdhary, Mahesh Y Malik
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredOct 2023First promiseDec 2026Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Oct 2023
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 31 Dec 2026)
  • Buildings2 building records
  • Documents filed174 files

Current status

28%44 of 157 units booked
81.6%Work done, per cost certificate

Figures as on 8 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shraddha Skyline Wing - ANA33271520152
Shraddha Skyline Wing - BNA22055

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 96%.

Shraddha Skyline Wing - A63%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)50%
Plinth100%
Stilt Floor100%
Slabs of Super Structure96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Shraddha Skyline Wing - B63%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)50%
Plinth100%
Stilt Floor100%
Slabs of Super Structure96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed256

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots256
Closed/Covered256
BuildingClosed/CoveredTotal
Shraddha Skyline Wing - A231231
Shraddha Skyline Wing - B2525

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,345 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Oct 2025
LandownerVillageDistrict
Om Gordhan Baug Chs LtdKanheriMumbai Suburban
Jay Dharma Kripa Co Operative Housing LtdKanheriMumbai Suburban
Jay Anand Co Operative Housing LtdKanheriMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI15194.16
Proposed, not sanctioned15,194 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVed Bunglow 258 Swami Vivekanand Rd Borivali West Mumbai 400092
Estimated costRs 97.12 cr
Cost incurredRs 79.23 cr
Work done81.57%
BuildingWingEstimatedIncurred
Shraddha Skyline Wing - ANARs 82.91 crRs 70.43 cr
Shraddha Skyline Wing - BNARs 9.21 crRs 7.83 cr
-NARs 5.00 crRs 97.25 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDIVYESH PAREKH
EngineerJAYESH A TANK
EngineerSagar Yogesh Makhela
Chartered AccountantY M Desai & Co
Chartered AccountantB L DASHARDA & ASSOCIATES
Chartered AccountantDesai Shah and Associates
PartnerRole in project
SHRADDHA DEVELOPERS & REALTORS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P51800053170/WarDec 2026 → Apr 2027

Reason as filed by the promoterNA

Litigation declared7

CaseCourtStatus
478/2020Bombay High CourtClosed
2936/2022Bombay High CourtClosed
1953/2021Bombay High CourtClosed
509/2023Bombay High CourtClosed
35195/2022Bombay High CourtClosed
289/2018Divisional Joint RegistrarOngoing
478/2020Bombay High CourtClosed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed174

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 174 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Form 5-system generated_signed.pdf8 Sep 2026
Withdrawal Update Form 1File: FORM-1-Q1-2026-27.pdf13 Aug 2026
Withdrawal Update Form 2File: FORM-2-Q1-2026-27.pdf13 Aug 2026
Withdrawal Update Form 3File: Form 3 -Q1-2026-27-SIGNED.pdf13 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A Shraddha Skyline.pdf5 Jun 2026
Withdrawal Update Form 1File: FORM 1 Q4 FY 2025-26.pdf12 May 2026
Withdrawal Update Form 2File: FORM 2 Q4 FY-2025-26.pdf12 May 2026
Withdrawal Update Form 3File: Form 3 Q4 FY 25-26 .pdf12 May 2026
Withdrawal Update Form 1File: Final Form 1.pdf10 Mar 2026
Withdrawal Update Form 2File: Final Form 2.pdf10 Mar 2026
Withdrawal Update Form 3File: Final form 3 signed.pdf10 Mar 2026
Withdrawal Update Form 1File: Form 1 Q2.pdf19 Jan 2026
Withdrawal Update Form 2File: signed form 2.pdf19 Jan 2026
Withdrawal Update Form 3File: Form 3 Q2.pdf19 Jan 2026
Withdrawal Update Form 1File: Form 1.pdf3 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf3 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf3 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf3 Nov 2025
Withdrawal Update Form 3File: FORM 3.pdf3 Nov 2025
Withdrawal Update Form 3File: FORM 3 Jamligali as on 30 06 2025 R1.pdf3 Nov 2025
Form 5 (FY 2024-2025)File: System Generated Form 5 Skyline New-30 09 25- signed.pdf30 Sep 2025
Form 2A (FY 2024-2025)File: fORM 2.pdf30 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Jamligali as on 31-03-2025.pdf19 Apr 2025
Details of encumbrances concerned to FinanceFile: Annexure K Non-Encumbrance related to Finance and Legal.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Annexure A RERA Form 1_Signed (2).pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SKY LINE RERA 17042025_Signed (1).pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: JG Disclosure of Sold and Unsold Inventory.pdf18 Apr 2025
CERSAI detailsFile: Annexure G Asset Based Declaration.pdf18 Apr 2025
CERSAI detailsFile: Annexure L Debtor Based Declaration.pdf18 Apr 2025
Details of encumbrances concerned to LegalFile: Annexure K Non-Encumbrance related to Finance and Legal.pdf18 Apr 2025
Details of encumbrances concerned to FinanceFile: Non Encumbrance Declaration.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q3.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shraddha Skyline form 3_compressed.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 q3 compressed.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold Q3.pdf24 Jan 2025
CERSAI detailsFile: Assets Based Declaration.pdf24 Jan 2025
CERSAI detailsFile: Debtor Based Declaration.pdf24 Jan 2025
Details of encumbrances concerned to LegalFile: Non Encumbrance Declaration.pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5- Skyline Project.pdf13 Nov 2024
Details of encumbrances concerned to FinanceFile: encumbrance final.pdf24 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 RERA 5.pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Skyline.pdf24 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 SKY LINE RERA 21102024_Flattened[1].pdf24 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Skyline.pdf24 Oct 2024
CERSAI detailsFile: ASSETS BASED.pdf24 Oct 2024
CERSAI detailsFile: DEBTOR BASED.pdf24 Oct 2024
Details of encumbrances concerned to LegalFile: encumbrance final.pdf24 Oct 2024
Disclosure of sold/ booked inventoryFile: RERA Sold and Unsold_New.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate (1).pdf13 Aug 2024
Details of encumbrances concerned to FinanceFile: Non-Encumbrance Concerned to Legal.pdf7 Aug 2024
Details of encumbrances concerned to LegalFile: Non-Encumbrance Concerned to Legal.pdf7 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2A SHRADDHA SKY LINE_0001.pdf7 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Q1.pdf5 Aug 2024
CERSAI detailsFile: Asset Based Declaration.pdf5 Aug 2024
CERSAI detailsFile: Debtor Based Declaration.pdf5 Aug 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Shraddha sky line separate Account.pdf10 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf2 May 2024
Declaration about Commencement CertificateFile: Declaration about CC_Revalidated on.pdf2 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Q4.pdf2 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_Fy 23-24.pdf2 May 2024
Disclosure of sold/ booked inventoryFile: Declaration of Sold Unsold.pdf2 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Q4_NEW.pdf2 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Shraddha sky line separate Account.pdf2 May 2024
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Legal.pdf19 Apr 2024
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Legal.pdf19 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Q4.pdf19 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Farm-2A_FY 23-24.pdf19 Apr 2024
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf19 Apr 2024
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf9 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Annexure-I Declaration About Separate Bank Account.pdf9 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Q3_compressed.pdf25 Jan 2024
Disclosure of sold/ booked inventoryFile: Declaration of Sold Unsold_Updated_upload both becuz in old area is worng .pdf23 Jan 2024
Disclosure of sold/ booked inventoryFile: Declaration of Sold Unsold.pdf19 Jan 2024
Details of encumbrances concerned to FinanceFile: Annexure k_Non-Encumbrance Legal.pdf16 Jan 2024
Details of encumbrances concerned to LegalFile: Annexure k_Non-Encumbrance Legal.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf16 Jan 2024
CERSAI detailsFile: Annexure G_Asset Based Report.pdf16 Jan 2024

How this compares with Mumbai Suburban

28%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 4 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHRADDHA SKYLINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali West6,700+ in Mumbai Suburban

Builder: SHRADDHA DEVELOPERS & REALTORS

SHRADDHA DEVELOPERS & REALTORS has 2 registrations on MahaRERA, including SHRADDHA ELITE and SHRADDHA SKYLINE. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHRADDHA SKYLINE is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRADDHA SKYLINE?

The registered promoter entity is SHRADDHA DEVELOPERS & REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRADDHA SKYLINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRADDHA SKYLINE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRADDHA SKYLINE?

The professionals named in the filing: Architect: DIVYESH PAREKH; Engineer: JAYESH A TANK; Engineer: Sagar Yogesh Makhela; Chartered Accountant: Y M Desai & Co; Chartered Accountant: B L DASHARDA & ASSOCIATES; Chartered Accountant: Desai Shah and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRADDHA SKYLINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRADDHA SKYLINE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRADDHA SKYLINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.