Red flags

  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 15 months from the original
9 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 50%
31 of 67Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 98 documents Report an error

SHIVRAJ HEIGHTS WING C is a Residential / Group Housing project by KAILASH PUNWASI YADAV in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046085 on 20 Jun 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 15 months from the original filing. 36 of the 67 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHIVRAJ HEIGHTS WING C
  • TypeResidential / Group Housing
  • Location
    • BHABREKAR NAGAR
    • CHARKOP
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • RERA no.P51800046085
  • ReraGenie IDRG-MH-69555

Builder

  • NameKAILASH PUNWASI YADAV
  • Entity typeIndividual
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2022First promiseDec 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Jun 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed98 files

Current status

54%36 of 67 units booked
76.8%Work done, per cost certificate

Figures as on 19 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHIVRAJ HEIGHTS WING CNA202067067

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 50%.

SHIVRAJ HEIGHTS WING C: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 19 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area600 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI3844.16
Proposed, not sanctioned1,671 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKANDIVALI WEST 400067
Estimated costRs 55.23 cr
Cost incurredRs 42.44 cr
Work done76.84%
BuildingWingEstimatedIncurred
SHIVRAJ HEIGHTS WING CNARs 33.13 crRs 21.00 cr
-NARs 22.10 crRs 21.44 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMUKTANAND AND ASSOCIATES
EngineerKAMLA PRASAD PANDEY
Chartered AccountantHARISH OMPRAKASH GUPTA
Chartered AccountantAlok Bhavsar
PartnerRole in project
KAILASH PUNWASI YADAV-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA08012619356Dec 2025 → Mar 2027

Reason as filed by the promoter1. The project construction is currently approximately 95% complete. However, during the course of development, the project faced unforeseen delays due to issues arising from certain commercial slum dwellers in the vicinity. These external disruptions led to a “Stop Work” situation, which was beyond our control and significantly impacted the project timeline by approximately two years. 2. The delay was caused by third-party interference and social issues, not attributable to the promoter. 3. The matter has now been amicably resolved through appropriate legal and administrative channels. 4. Con

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed98

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 wing C 31032026.pdf19 May 2026
Withdrawal Update Form 1File: Form 1 wing C 31032026.pdf19 May 2026
Withdrawal Update Form 2File: Form 2 Wing C 31032026.pdf19 May 2026
Withdrawal Update Form 2File: Form 2 Wing C 31032026.pdf19 May 2026
Withdrawal Update Form 3File: Form 3 Wing C 31032026.pdf19 May 2026
Withdrawal Update Form 3File: Form-3-Shivraj Heights Wing C.pdf19 May 2026
Withdrawal Update Form 1File: Form 1 SH 122025.pdf27 Apr 2026
Withdrawal Update Form 2File: Form 2 Dec 2025.pdf27 Apr 2026
Withdrawal Update Form 3File: Form 3-Dec 2025.pdf27 Apr 2026
Withdrawal Update Form 1File: Form 1 SH 122025.pdf31 Mar 2026
Withdrawal Update Form 1File: Form 1 SH 122025.pdf31 Mar 2026
Withdrawal Update Form 2File: Form 2 SH 122025.pdf31 Mar 2026
Withdrawal Update Form 2File: Form 2 Dec 2025.pdf31 Mar 2026
Withdrawal Update Form 3File: Form 3_Shivraj Heights Wing C.pdf31 Mar 2026
Withdrawal Update Form 3File: Form 3-Dec 2025.pdf31 Mar 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2026-01-07 105453.pdf7 Jan 2026
Form 3File: RERA CA FORM 3 Shivraj Heights C Wing 30092025.pdf7 Jan 2026
Form 1File: Form 1 30092025 Wing C.pdf7 Jan 2026
Form 2File: Form 2 30092025 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2025-12-24 160751.pdf7 Jan 2026
Form 3File: RERA CA FORM 3 Shivraj Heights C Wing 30062025.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2026-01-07 105453.pdf7 Jan 2026
Form 3File: RERA CA FORM 3 Shivraj Heights C Wing 31032025.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2026-01-07 105453.pdf7 Jan 2026
Form 3File: RERA CA FORM 3 Shivraj Heights C Wing 31122024.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2026-01-07 105453.pdf7 Jan 2026
Form 3File: RERA CA FORM 3 Shivraj Heights C Wing 30092024.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2026-01-07 105453.pdf7 Jan 2026
Form 3File: RERA CA FORM 3 Shivraj Heights C Wing 30062024.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2026-01-07 105453.pdf7 Jan 2026
Form 3File: RERA CA FORM 3 Shivraj Heights C Wing 31032024 1.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2026-01-07 105453.pdf7 Jan 2026
Form 3File: RERA CA FORM 3 Shivraj Heights C Wing 31122023.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2026-01-07 105453.pdf7 Jan 2026
Form 3File: RERA CA FORM 3_Shivraj Heights C Wing.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2025-12-24 160751.pdf7 Jan 2026
Form 3File: RERA CA FORM 3_Shivraj Heights C Wing.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2025-12-24 160751.pdf7 Jan 2026
Form 3File: RERA CA FORM 3_Shivraj Heights C Wing.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2025-12-24 160751.pdf7 Jan 2026
Form 3File: RERA CA FORM 3_Shivraj Heights C Wing.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2025-12-24 160751.pdf7 Jan 2026
Form 3File: RERA CA FORM 3_Shivraj Heights C Wing.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Disclosure of Sold and Booked InventoryFile: Screenshot 2025-12-24 160751.pdf7 Jan 2026
Form 3File: RERA CA FORM 3_Shivraj Heights C Wing.pdf7 Jan 2026
Form 1File: Form 1 Wing C.pdf7 Jan 2026
Form 2File: Form 2 wing C.pdf7 Jan 2026
Form 2A (FY 2024-2025)File: Adobe Scan Jan 07, 2026.pdf7 Jan 2026
Form 2A (FY 2023-2024)File: Adobe Scan Jan 07, 2026.pdf7 Jan 2026
Form 2A (FY 2022-2023)File: Adobe Scan Jan 07, 2026.pdf7 Jan 2026
Form 5 (FY 2022-2023)File: Shivraj Developers 23-24.pdf7 Jan 2026
Form 5 (FY 2023-2024)File: Shivraj Developers 23-24.pdf24 Dec 2025
Form 5 (FY 2024-2025)File: Shivraj Devlopers 24-25.pdf24 Dec 2025
Layout approvalFile: Layout Plan (1).pdf18 Jun 2022
Building plan approvalFile: 1 (1).pdf18 Jun 2022
Building plan approvalFile: 2 (1).pdf18 Jun 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
KALASH CHSLBHABREKAR NAGAR KANDIVALI WEST188CompletedFeb 2017Jan 2017
SHIVGANGA CHSLBHABREKAR NAGAR221CompletedMar 2012Jan 2012

How this compares with Mumbai Suburban

54%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 15 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVRAJ HEIGHTS WING C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHARKOP6,700+ in Mumbai Suburban

Builder: KAILASH PUNWASI YADAV

KAILASH PUNWASI YADAV has 3 registrations on MahaRERA, including SHIVRAJ HEIGHTS and SHIVRAJ HEIGHTS WING C. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHIVRAJ HEIGHTS WING C is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVRAJ HEIGHTS WING C?

The registered promoter entity is KAILASH PUNWASI YADAV, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVRAJ HEIGHTS WING C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVRAJ HEIGHTS WING C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVRAJ HEIGHTS WING C?

The professionals named in the filing: Architect: MUKTANAND AND ASSOCIATES; Engineer: KAMLA PRASAD PANDEY; Chartered Accountant: HARISH OMPRAKASH GUPTA; Chartered Accountant: Alok Bhavsar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVRAJ HEIGHTS WING C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVRAJ HEIGHTS WING C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVRAJ HEIGHTS WING C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.